Buttevant Rail Disaster

Last updated
Buttevant rail disaster
Ireland adm location map.svg
Red pog.svg
Details
Date1 August 1980
12:45
Location Buttevant
Coordinates 52°13′59″N8°40′01″W / 52.2331°N 8.6669°W / 52.2331; -8.6669 Coordinates: 52°13′59″N8°40′01″W / 52.2331°N 8.6669°W / 52.2331; -8.6669
Country Ireland
Line Dublin–Cork railway line
Operator Iarnród Éireann
CauseExpress sent into sidings as points not interlocked
Statistics
Trains1
Passengers~230
Deaths18
Injuries70+
Irish railway accidents

The Buttevant Rail Disaster was a train crash that occurred at Buttevant Railway Station, County Cork in Ireland, 220 kilometres (137 mi) from Heuston Station on the Dublin to Cork main line, on 1 August 1980. More than 70 people were injured, and 18 died, resulting as one of Ireland's worst rail disasters to ever occur.

Contents

The accident

At 12:45 the 10:00 am Dublin (Heuston) to Cork (Kent) express train entered Buttevant station carrying some 230 bank holiday passengers. The train was diverted off the main line across a 1:8 temporary set of points into a siding. The locomotive remained upright but carriages immediately behind the engine and generator van jack-knifed and were thrown across four sets of rail lines. Two coaches and the dining car were totally demolished by the impact. It resulted in the deaths of 18 people and over 70 people being injured.

The accident happened because a set of manual facing points were set to direct the train into the siding. These points were installed about four months previously and had not been connected to the signal cabin. The permanent way maintenance staff were expecting a stationary locomotive at the Up platform to move into the siding and had set the points for the diversion to the siding, without obtaining permission from the signalman. Upon seeing that this had been done, the signalman at Buttevant manually set the signals to the Danger aspect and informed the pointsman to reset the points.

The train was travelling too fast to stop in time. The derailment occurred at around 60 mph (97 km/h).

Local doctor Finnbarr Kennedy was on hand at the time of the crash, while waiting to cross the line, and was able to give aid to those injured.

The train

The train consisted of 071 Class locomotive number 075, a generator van and 11 coaches. Six of the coaches consisted of wooden bodies on steel underframes. Four of these were either destroyed or badly damaged in the impact, the two which survived being at the rear of the train. The remainder of the coaches were light-alloy Cravens stock; most of which survived the crash. The generator van, a modified BR Mark 1, was severely damaged. All of the vehicles were coupled using screw shackle couplings.

Aftermath

This event, and the subsequent Cherryville junction accident, which killed a further seven people, [1] accounted for 70% of all Irish rail deaths over a 28-year period. CIÉ and the Government came under severe public pressure to improve safety and to modernise the fleet. A major review of the national rail safety policy was held and resulted in the rapid elimination of the wooden-bodied coaches that had formed part of the train.

The passengers who were most severely injured or killed were seated in coaches with wooden frames. This structure was incapable of surviving a high-speed crash and did not come near to the safety standards provided by modern (post-1950s) metal-body coaches. The expert bodies that reviewed that accident discovered that the old timber-frame carriage bodies mounted on a steel frame were totally inadequate as they were prone to complete collapse (the "accordion" effect) under the enormous compression forces of a high-speed collision. While the steel underbody remained structurally intact, other carriages could "mount" the frame, completely compress and destroy the wooden frame body.

The more modern steel-framed carriage bodies survived due to their greater structural rigidity. On this basis, the decision to purchase a new fleet of modern intercity coaches based on the British Rail Mark 3 design was quickly made. The Mark 3's longitudinally corrugated roof can survive compression forces of over 300 tonnes. These coaches, an already well proven design, were built by BREL in Derby, England and, under licence, at CIÉ's own workshops at Inchicore in Dublin between 1983 and 1989.

Commemoration

On 8 August 2005, a commemoration marking the 25th anniversary was held at the station. A bronze sculpture in the shape of two crossing train tracks was unveiled alongside a plaque commemorating the names of the victims at the Buttevant Railway station.

Related Research Articles

Romney, Hythe and Dymchurch Railway Light railway in Kent, England

The Romney, Hythe & Dymchurch Railway (RH&DR) is a 15 in gauge light railway in Kent, England, operating steam and internal combustion locomotives. The 13 34-mile (22.1 km) line runs from the Cinque Port of Hythe via Dymchurch, St. Mary's Bay, New Romney and Romney Sands to Dungeness, close to Dungeness nuclear power station and Dungeness Lighthouse.

History of rail transport in Ireland

The history of rail transport in Ireland began only a decade later than that of Great Britain. By its peak in 1920, Ireland had 3,500 route miles (4,200 km). The current status is less than half that amount, with a large unserviced area around the border area between Northern Ireland and The Republic of Ireland.

Rail transport in Ireland Transport Infrastructure

Rail transport in Ireland is provided by Iarnród Éireann in the Republic of Ireland and by Northern Ireland Railways in Northern Ireland.

Driving Van Trailer Control car for train sets

A Driving Van Trailer (DVT) is a purpose-built control car railway vehicle that allows the driver to operate with a locomotive in push-pull formation from the opposite end of a train. Trains operating with a DVT consequently do not need the locomotive to be moved around to the other end of the train at terminal stations. Unlike many other control cars, DVTs resemble locomotives and thus when the train is operating in push mode, it does not appear to be travelling backwards. The vehicles do not have any passenger accommodation due to health and safety rules in place at the time of building that prohibited passengers in the leading carriages of trains that run faster than 100 miles per hour (160 km/h). Historically, it was believed that a train would be unstable at high speeds unless pulled from the front but extensive testing, and the experience of high speed trains with central power cars such as the British Rail APT and the Eurostar, have altered this view.

Driving Brake Standard Open

A Driving Brake Standard Open (DBSO) is a type of railway carriage, converted to operate as a control car. Fourteen such vehicles, numbered 9701 to 9714, were converted from Mark 2F Brake Standard Open carriages. Modifications included adding a driving cab and TDM equipment to allow a locomotive to be driven remotely. Using a system known as push–pull, the driver in the DBSO can drive the locomotive, even though it is at the rear of the train.

British Railways Mark 1 Railway coaching stock

British Railways Mark 1 is the family designation for the first standardised designs of railway carriages built by British Railways (BR) from 1951 until 1974, now used only for charter services on the main lines or on preserved railways.

British Railways Mark 2

The Mark 2 family of railway carriages are British Rail's second design of carriages. They were built by British Rail workshops between 1964 and 1975. They were of steel construction.

A wide variety of hauled coaches have been used on the railways of Ireland. This page lists all those since 1945.

The Charfield railway disaster was a fatal train crash which occurred on 13 October 1928 in the village of Charfield in the English county of Gloucestershire. The Leeds to Bristol London, Midland and Scottish Railway (LMS) night mail train failed to stop at the signals protecting the down refuge siding at Charfield railway station. The weather was misty, but there was not a sufficiently thick fog for the signalman at Charfield to employ fog signalmen. A freight train was in the process of being shunted from the down main line to the siding, and another train of empty goods wagons was passing through the station from the Bristol (up) direction.

Harrow and Wealdstone rail crash Train wreck in England

The Harrow and Wealdstone rail crash was a three-train collision at Harrow and Wealdstone station in Wealdstone, Middlesex during the morning rush hour of 8 October 1952. 112 were killed and 340 injured, 88 of these being detained in hospital, and it remains the worst peacetime rail crash in the United Kingdom.

Polmont rail accident rail accident in Scotland in 1984

The Polmont rail accident, also known as the Polmont rail disaster, occurred on 30 July 1984 to the west of Polmont, near Falkirk, in Scotland. A westbound push-pull express train travelling from Edinburgh to Glasgow struck a cow, which had gained access to the track through a damaged fence from a field near Polmont railway station. The collision caused all six carriages and the locomotive of the train to derail, killing 13 people and injuring 61 others. The accident led to a debate about the safety of push-pull trains on British Rail.

Glenbrook Vintage Railway vintage steam railway in New Zealand

The Glenbrook Vintage Railway (GVR) is a heritage steam railway in Glenbrook, New Zealand.

There have been a number of train accidents on the railway network of Victoria, Australia. Some of these are listed below.

The railways of New South Wales, Australia have had many incidents and accidents since their formation in 1831..

The rolling stock used on the Isle of Man Railway today is entirely original but the serviceable passenger coaches number 14, out of an original total of 75 carriages. The railway was provided with a variety of stock from different manufacturers over its time, and types of coach were categorised according to a lettering system, with the original four-wheeled coaches being of A, B, C and D types, and so on. The types of stock can be summarised as follows:-

The Wigan rail crash was a railway accident which occurred at Wigan North Western station, England, to a northbound excursion train in the very early morning of 3 August 1873. Thirteen passengers were killed after derailed carriages collided with station buildings.

The Kirtlebridge rail crash took place in 1872 at Kirtlebridge railway station in Dumfriesshire. An express passenger train ran into a goods train that was shunting; 11 people lost their lives immediately, and one further person succumbed later. The cause was a failure to communicate between the station master in charge of the shunting operation, and the signalman. There was not full interlocking of the points, and the block system of signalling was not in use.

The Marden rail crash occurred on 4 January 1969 near Marden, Kent, United Kingdom, when a passenger train ran into the rear of a parcels train, having passed two signals at danger. Four people were killed and 11 were injured. One person was awarded the British Empire Medal for his part in the aftermath of the collision.

This is a list of significant Railway Accidents in Queensland, Australia.

References

  1. Archived October 8, 2006, at the Wayback Machine