| Thorpe Marsh Power Station | |
|---|---|
| Thorpe Marsh power station's cooling towers | |
| |
| Country | England |
| Location | South Yorkshire, Yorkshire and the Humber |
| Coordinates | 53°34′50″N1°05′07″W / 53.580602°N 1.08534°W |
| Construction began | 1959 |
| Commission date | 1963 [1] |
| Decommission date | 1994 |
| Operators | Central Electricity Generating Board (1963-1990) National Power (1990-1994) |
| Thermal power station | |
| Primary fuel | Coal |
| Tertiary fuel | Heavy Fuel Oil |
| Power generation | |
| Nameplate capacity | 1,100 MW |
| External links | |
| Commons | Related media on Commons |
grid reference SE605097 | |
Thorpe Marsh Power Station was a 1 GW coal-fired power station near Barnby Dun in South Yorkshire, England. The station was commissioned in 1963 and closed in 1994. [2] In 2011, permission was given for the construction of a gas-fired power station on the site.
The Central Electricity Authority proposed in December 1956 to construct a power station containing 550MW turbo alternators. These were vastly bigger units than had been built which at the time was 200MW. The sets were actually 2 x 275MW units powered by one turbine as that was the maximum size that could be transported. Thorpe Marsh was selected for a 1,100 MW station to be delivered as a part of its 1962 programme [3] .
Construction of the station began in 1959; [4] it was built as a prototype for all the large modern power stations in the UK. It was commissioned between 1963 and 1965. [5] Thorpe Marsh was one of the CEGB's twenty steam power stations with the highest thermal efficiency; in 1963–4 the thermal efficiency was 31.50 per cent, 32.76 per cent in 1964–5, and 33.09 per cent in 1965–6. [6]
There were 2 × 28 MW auxiliary gas turbines on the site, these had been commissioned in December 1966. [7]
The plant was officially opened in 1967. [8]
The station contained two Parsons 550 MW generating units. These turbo-generator itself is a two-shaft machine operating two alternators, each of 275 MW cross compound turbines, each supplied from a International Combustion boiler that could provide 3,750,000 lb/ of steam an hour, at a pressure of 2,400 lb per sq in and a temperature of 1,055 deg F. The steam was reheated after passing through the high-pressure turbine back to 1,055 deg F before passing back through the remaining stages of the turbine. [9] [10] These were the biggest boilers ever constructed at the time and were two separately cased twin furnace units but with a single steam output. [11]
The annual electricity output of Thorpe Marsh was: [6]
| Year | 1963–4 | 1964–5 | 1965–6 | 1966–7 | 1971–2 | 1978–9 | 1981–2 |
|---|---|---|---|---|---|---|---|
| Electricity supplied, GWh | 581 | 1,697 | 1,803 | 2,804 | 3,660 | 3,750 | 4,296 |
On 7 January 1973, four workmen died. A coroner's report gave a verdict of accidental death; subsequently the Factory Inspectorate began legal proceedings against the Central Electricity Generating Board (CEGB) for breaches in safety provisions. [12]
After the privatisation of the CEGB in 1990, the station was operated by National Power. The station subsequently closed in 1994. [5] [13]
The 45 ha (110 acres) site was acquired by Able UK in 1995. [14]
During the 2007 United Kingdom floods, the 400 kV substation at the site was temporarily shut down on 27 June, whilst the 275 kV substation was not affected; operational service was fully restored by early 28 June. [15]
In October 2011, the Department of Energy and Climate Change approved the construction of a 1,500 MW combined cycle gas turbine power station at Thorpe Marsh by Thorpe Marsh Power Limited (parent Acorn Power Developments, see Acorn Energy) with an estimated cost of £984 million. [16] [17] [18] Thorpe Marsh Power Limited proposed an initial capacity of 960 MW. [18] The proposed development would also require the construction of an 18 km (11 mi) gas pipeline from Camblesforth; [19] the gas pipeline was approved in 2016. [20]
Able UK demolished the original power station's cooling towers in 2012. [21] [22]
In 2022 plans were unveiled to build a 1.4 GW [23] / 3.1 GWh battery energy storage system on the site for £445 million by 2027, [24] named the Thorpe Marsh Green Energy Hub. A 1 GW / 2 GWh battery is also planned at the adjacent Almholme site. [25] Local news sources have highlighted the projects' potential in repurposing the old power station's infrastructure. [26]
{{cite book}}: CS1 maint: others (link){{cite book}}: CS1 maint: others (link){{cite book}}: CS1 maint: others (link)