Tilbury power stations

Last updated

Tilbury power stations
Tilbury power station.jpg
Tilbury B Power Station
Viewed from the west in May 2008
Tilbury power stations
CountryEngland
Location Tilbury
Coordinates 51°27′18″N0°23′30″E / 51.454926°N 0.391677°E / 51.454926; 0.391677
StatusDecommissioned and demolished
Construction beganA station: 1951
B station: 1961
Commission date A station: 1956
B station: 1968 [1] [2]
Decommission dateA station: 1981
B station: 2013
Owner(s) Central Electricity Authority
(1955–1957)
Central Electricity Generating Board
(1958–1990)
National Power
(1990–2000)
Innogy plc
(2000–2002)
npower
(2002–2013)
Operator(s)CEGB 1958-1990
Thermal power station
Primary fuel Coal
Secondary fuelOil
Tertiary fuelBiomass
Site area91.5 hectare
ChimneysA station: 2 (100 metres); B station: 2 (168 metres)
Cooling towersNone
Cooling sourceRiver water
Power generation
Units operationalA station: 6 × 60 MW; B station: 4 × 350 MW
Units decommissionedAll
Nameplate capacity A station: 360 MW
B station: 1,428 MW
Annual net output A station: 2662 MWh max; B station: 4587 MWh max
External links
Website web.archive.org/web/20100518173833/http://www.rwe.com/web/cms/en/97606/rwe-npower/about-us/our-businesses/power-generation/tilbury/
Commons Related media on Commons

grid reference TQ661756

The Tilbury power stations were two thermal power stations on the north bank of the River Thames at Tilbury in Essex. The 360 MW dual coal- and oil-fired Tilbury A Power Station operated from 1956 until 1981 when it was mothballed, prior to demolition in 1999. [1] The 1,428 MW Tilbury B Power Station operated between 1968 and 2013 and was fueled by coal, [1] as well as co-firing with oil and, from 2011, biomass. Tilbury B was demolished in 2016–19. [3] Since 2013 three other power stations have been proposed or constructed in Tilbury.

Contents

History

Tilbury A and B stations in 1973 TilburyPS1973.jpg
Tilbury A and B stations in 1973

A station

Tilbury A power station was planned from 1947 by the County of London Electricity Supply Company Limited. Following the nationalisation of the electricity industry in 1948 the plans were taken forward successively by the British Electricity Authority, the Central Electricity Authority and from 1958 the Central Electricity Generating Board. Construction of Tilbury A was sanctioned in 1950 and began in 1951 and was initially commissioned in 1956 by the Central Electricity Authority. [4] After operating for 25 years the A station was mothballed by the CEGB in 1981 and eventually demolished in 1999, mostly everything including the turbine hall was demolished. The waste water and a small part of the station remained due to being a listed building [5] The site was entirely cleared in 2019 for the construction of the Tilbury2 port. [6]

B station

The CEGB began construction of the larger 1,428 MW Tilbury B station in 1961. This was commissioned in 1968 [4] and was operating at full capacity by 1969. [3] On privatisation of the electricity industry in 1990 it was assigned to National Power, and was later operated by RWE npower.

Conversion to biomass

In May 2011, RWE began converting the B station to burn biomass only. They hoped the conversion would allow 750 MW of electricity to be generated from burning wood pellets imported from a pelleting plant in Georgia, USA, and other sources from Europe by the winter of 2011. This conversion made the station the biggest biomass generating site in the world. [7]

In July 2013 RWE npower announced they were halting the conversion due to difficulty in converting and financing the plant. It was mothballed after failing to receive a government grant and was decommissioned and subsequently demolished during 2016–9. [8] [9]

C station

In early 2007, npower announced plans to replace the B station with a 1,600 MW 'cleaner' coal-fired power station. The station would have cost £1 billion to build and was hoped to be operational by 2014. The plans were supported by the Port of London Authority. [10] RWE had also planned to build a clean coal power station at Blyth but they have since postponed both schemes.

Design and specification

A station

Sir Alexander Gibb and Partners were the civil consulting engineers and architects of Tilbury A; the main consulting engineers were Merz & McLellan. [4] The A station was built on the 226 acre (91.5 hectare) site and was a steel framed construction with elevations in London stock brick. The integrated boiler house and turbine hall were lit by tall rectangular windows, with ancillary buildings by smaller square windows. [4] The A station had two 100 metre high concrete chimneys. [4]

Tilbury A had six 60 MW steam turbo-alternators three were manufactured by English Electric and three by Parsons giving a total output of 360 MW. It was designed as a coal-fired station with coal delivered to the jetty on the Thames and stored initially to the east and later to the north of the building. Soon after completion in 1958 the station was adapted to also burn oil. The total steam capacity of the John Thompson boilers was 3,240,000 lb/hr (408 kg/s). [11] The steam pressure and temperature at the turbine stop-valve was 900 psi (62 bar) and 482 °C. The alternators generated current at 11.4 kV. [11] Cooling water was drawn from, and returned to, the Thames via caissons in the fueling jetty. The station connected to the National Grid at the nearby 275 kV Tilbury substation. Tilbury A had several railway sidings accessed via a connection to the London, Tilbury and Southend railway between the former Tilbury Riverside and Low Street railway stations. [12]

Tilbury A and B power stations and coaling jetty 1981 Tilbury power stations 1981.tif
Tilbury A and B power stations and coaling jetty 1981

In 1963 Tilbury A was used in experiments by the CEGB on the behaviour of pollutants (principally sulphur dioxide) in flue gas plumes emitted from the power station chimneys. The results showed that the maximum pollutant concentrations occurred 2.4 km downwind of the station in strong winds and 9.6 – 13 km downwind in light winds. [13]

B station

The B station was built on the site of coal store to the east of the A station; the coal store for both stations was then relocated to the north of the site. [4] The B station was a steel framed construction with unfenestrated elevations of concrete cladding. The taller boiler house block was orientated north–south to the west of the adjoining turbine hall; control rooms and offices were at the south end. [4]

Tilbury B comprised four generating units each of 350 MW. When all four units were available the combined output capacity was 1428 MW, enough power for 1.4 million people, approximately 80% of the population of Essex. [3] The boiler steam pressure was 158.58 bar at a temperature of 566 °C. Discharge from the HP turbine was returned to the boilers for reheat to 566 °C. The boilers had a capacity of 4 × 296 kg/s. [11] The station had two 168 metre high concrete chimneys. One unit was later decommissioned and was used for spare parts for maintenance of the remaining 3 generating units.

In addition to the steam generating sets Tilbury power station had auxiliary gas turbines for peak-shaving. This comprised four 17.5 MW gas turbines, the oldest set was commissioned in February 1965. [11]

Two 800 tonne coal unloaders were installed on the jetty in 1990. [4] The jetty was enlarged in 2004 to accommodate ships carrying up to 65,000 tons of coal. [5]

Decommissioned Tilbury B power station seen from Gravesend Tilbury B Power Station.jpg
Decommissioned Tilbury B power station seen from Gravesend

Electricity output

Electricity output for Tilbury A & B stations over the period 1957-1987 was as follows. [14] [15] [16] [17]

Tilbury A annual electricity output GWh.

Tilbury B annual electricity output GWh.

The steam turbo-alternators of B station were not commissioned until 1968; the output of B station before this date was from the gas-turbine sets commissioned in February 1965. [14]

The maximum thermal efficiency of the A station was 30.84%; and for the B station was 32.19%. [14]

Incidents

1977 fire

In the early hours of 16 November 1977 a fire broke out at Tilbury B. It spread from the control room along cable ducts and caused severe cracks in the £70 million building. The site was evacuated but three engineers who had stayed behind to shut down the plant were taken to hospital after inhaling fumes. Foam equipment was brought from other power stations and by the evening the fire had been contained. [18]

2008 boiler incident

On 1 July 2008, an engineer servicing an offline boiler at the station fell 20 ft (6.1 m) from scaffolding into the boiler. Crews used an internal staircase in the boiler to rescue him. [19]

2009 fire

A fire broke out at the power station on 29 July 2009 shortly after 3 pm, with the failure of one of the station's high-pressure turbine units. Workers were evacuated immediately and the fire was reported to be under control by 5:30 pm. There were no casualties. [20]

2012 fire

A major fire broke out in a fuel storage area of the station on the morning of 27 February 2012. Essex County Fire and Rescue Service mobilised over 120 firefighters to the fire, which involved some 4,000 to 6,000 tonnes of fuel in storage cells, two of which were described as "well alight".

Essex Chief Fire Officer David Johnson reported that firefighting operations were hindered by the fact that the blaze was high up in the main structure of the station, which was also heavily smoke-logged. In addition to 15 pumping appliances, crews used three aerial ladder platforms, one major rescue tender, three bulk foam tenders and a thermal-imaging camera in a helicopter to help tackle the fire. Support crews were drafted in from the London Fire Brigade. [21]

Despite initial reports, another fire in the adjacent Tilbury docks which started around the same time was not connected to the larger blaze at the power station. It took firefighters several hours to bring the power station fire under control, and relief crews remained at the site for days afterward dousing and removing embers.

Chimneys and power station demolition

The chimneys of the B station were demolished on 28 September 2017. [22]

In March 2019, the 14th and final explosive demolition took place. [23]

Ash disposal site

Ash from the boilers at Tilbury power station was deposited on the low lying marshland to the east of the site. The land at Goshems Farm East Tilbury had also been subject to other landfill activity over the years and the fill comprised a mixture of ash and glass bottles. [24] The site had been poorly restored and had little topsoil cover and was uneven and littered with debris. In 2003 a plan was inaugurated to restore the site. This would entail raising the height of the land using soil from civil engineering works along the River Thames and restore the site to high quality arable farmland. Inert construction material is transported in barges to the wharf at Goshems Farm. The first barge was unloaded in 2011 and the restoration works are ongoing. A public footpath will be created along the riverside. Tilbury Ash Disposal Site is operated by Ingrebourne Valley Ltd. [24]

Other power stations in Tilbury

In addition to Tilbury A and B there are three other power stations in Tilbury that are planned or are now operational.

Tilbury Energy Centre

The Tilbury Energy Centre is a planned natural gas Combined Cycle Gas Turbine (CCGT) power station which also includes a peaking plant and a battery energy storage unit. The centre is owned and will be operated by RWE Generation UK plc. [25] It is located on the site of the demolished Tilbury B power station.

The Tilbury Energy Centre will comprise three gas-fired CCGT generating units with a total output capacity of 2500 MW; a 300 MW peaking plant comprising open cycle gas turbines (OCGT); and batteries with a capacity of 100 MW. The centre will also have the capability to act as a combined heat and power facility and will be provided with carbon capture readiness capability. [25]

The flue stacks of the CCGT will be 95 metres in height and the OCGT stack(s) will 45 metres high. [25]

In November 2018 RWE evaluated its UK energy options and decided to freeze the Tilbury Energy Centre development. [26]

Thurrock Flexible Generation Plant

The Thurrock Flexible Generation Plant is a planned natural gas engine and battery energy electricity supply facility. [27] The plant will be developed, owned and operated by Thurrock Power Limited, a subsidiary of Statera Energy. It is located immediately north of the former Tilbury A & B power station site and south of the London, Tilbury and Southend Railway. The main site occupies an area of 18.5 hectares. [27]

The plant will comprise up to 60 fast-starting gas engines fuelled by natural gas connected to electricity generators which will generate a total of 600 MW of electricity. In addition, batteries will store up to 600 MWh and export up to 150 MW of electricity. The engines will not run continuously but will start up for short periods several times a day as the National Grid requires, it is envisaged that they will run for up to 4000 hours per year, i.e. less than half the year. [27] Electrical transformers and switchgear step-up the voltage from the batteries and generators to match the 275 kV National Grid voltage at Tilbury substation. [27]

The flue stacks from the engines may be grouped together; the stacks will be 40 metres tall. The engine building will be 20 metres high and the battery building up to 10 metres high. [27]

It is envisaged that advance works will start in 2020; main construction work will start in 2021 and take 18 months to six years in total over several phases. The plant will have a design operational life of 35 years. [27]

Tilbury Green Power

The Tilbury Green Power plant is an operational electricity generating facility which uses wood as a fuel source. The plant is owned and operated by Tilbury Green Power Limited. [28] The plant is located within the Port of Tilbury, Essex. There are two phases of development: Phase 1 is a 40 MW waste wood power plant; and Phase 2 is a 20 MW Solid Recovered Fuel power plant. Only Phase 1 has currently been developed; construction started in August 2015 and the plant was commissioned in early 2019. [28]

The plant utilises about 270,000 tonnes of waste wood to produce up to 319,000 MWh of renewable electricity each year. Wood is processed onsite to produce wood-chip which is burned in a single travelling grate boiler to produce high pressure steam. This steam passes through a single steam turbine to generate electricity. Electricity (at 132 kV) is supplied to the National Grid via a 4.5 km underground cable to the existing 132 kV substation at Tilbury. [28]

Flue gases from the boiler are treated by emissions control technology including Selective Non-Catalytic Reduction (SNCR), fabric filters, and dry lime and activated carbon injection. Exhaust gases are discharged via a 100 metre high stack. [28]

Related Research Articles

<span class="mw-page-title-main">Ironbridge power stations</span> Two former power stations in Shropshire, England

The Ironbridge power stations refers to a series of two power stations that occupied a site on the banks of the River Severn at Buildwas in Shropshire, England. The Ironbridge B Power Station was operated by E.ON UK but the site is now owned by Haworth Group. The station stands near the Ironbridge Gorge World Heritage Site. Originally powered by coal, they were converted to use 100% biomass fuel. Ironbridge B Power Station stopped generating electricity on 20 November 2015, with the decommissioning process continuing into 2017. The main phase of the 27-month demolition process began at 11:00 GMT on 6 December 2019, commencing with the four cooling towers.

<span class="mw-page-title-main">Ferrybridge power stations</span> Three coal-fired power stations in West Yorkshire, England

The Ferrybridge power stations were a series of three coal-fired power stations on the River Aire near Ferrybridge in West Yorkshire, England, in operation from 1927 to 2016 on a site next to the junction of the M62 and A1(M) motorways.

<span class="mw-page-title-main">Aberthaw power stations</span> Two decommissioned power stations in Wales

Aberthaw Power Station refers to two decommissioned coal-fired and co-fired biomass power stations on the coast of South Wales, near Barry in the Vale of Glamorgan. They were located at Limpert Bay, near the villages of Gileston and West Aberthaw. The most recent power station on the site, Aberthaw B Power Station, co-fired biomass and as of 2008 had a generating capacity of 1,560 megawatts (MW). The power station closed on 31 March 2020.

<span class="mw-page-title-main">Littlebrook Power Station</span> Series of four oil and coal-fired power stations in Dartford, Kent

The Littlebrook Power Station were a series of four oil and coal-fired power stations situated on the south bank of the River Thames, next to the Queen Elizabeth 2 Bridge and the Dartford Tunnel in Dartford, Kent. The final power station, Littlebrook D, ceased operating in March 2015, and has now been demolished.

<span class="mw-page-title-main">West Thurrock Power Station</span>

West Thurrock Power Station was a coal-fired power station on the River Thames at Stone Ness, West Thurrock in Essex. The station was at the northern end of the 400 kV Thames Crossing of the National Grid.

<span class="mw-page-title-main">Little Barford Power Station</span>

Little Barford Power Station is a gas-fired power station just north of the village of Little Barford in Bedfordshire, England. It lies just south of the A428 St Neots bypass and east of the Wyboston Leisure Park. The River Great Ouse runs alongside. It was formerly the site of two coal-fired power stations, now demolished. The station is operated by RWE.

<span class="mw-page-title-main">Great Yarmouth Power Station</span> Gas power station in Norfolk, England

Great Yarmouth Power Station is combined cycle gas turbine power station on South Denes Road in Great Yarmouth in Norfolk, England, with a maximum output of 420 MW electricity, opened in 2001. It is built on the site of an oil-fired power station, built in 1958 and closed and demolished in the 1990s. A coal-fired power station was built in Great Yarmouth in 1894 and operated until 1961. The station is operated by RWE.

<span class="mw-page-title-main">Roosecote Power Station</span>

Roosecote Power Station was a gas-fired, originally coal-fired power station, situated in the Roosecote district of Barrow-in-Furness in Cumbria, North West England. The gas-fired station opened in 1991 and was the first CCGT power station to supply electricity to the United Kingdom's National Grid, but was mothballed in 2012 after a proposed biomass power station was cancelled. It was situated directly adjacent to Rampside Gas Terminal. The plant was demolished between 2014 and 2015. The site is now a 49 MW battery storage facility.

<span class="mw-page-title-main">Blyth Power Station</span> Thermal Power Station in England

Blyth Power Station refers to a pair of now demolished coal-fired power stations, which were located on the Northumberland coast in North East England. The two stations were built alongside each other on a site near Cambois in Northumberland, on the northern bank of the River Blyth, between its tidal estuary and the North Sea. The stations took their name from the town of Blyth on the opposite bank of the estuary. Blyth A Power Station was built and opened first but had a smaller generating capacity than its sister station, Blyth B Power Station, which was built to its west four years later. The power stations' four large chimneys were a landmark of the Northumberland skyline for over 40 years; the A Station's two chimneys each stood at 140 metres (460 ft); the B Station's two chimneys were taller, at 170 metres (560 ft) each.

<span class="mw-page-title-main">Staythorpe Power Station</span>

Staythorpe C Power Station is a 1,735 MWe gas-fired power station at Staythorpe between Southwell and Newark-on-Trent in Nottinghamshire, England, between the River Trent and Nottingham to Lincoln railway line. The station was handed over to the owner RWE from Alstom Power with full commercial operation being achieved in December 2010. The official opening ceremony attended by Charles Hendry, Minister of State took place on 9 May 2011.

<span class="mw-page-title-main">Pembroke Power Station</span> Gas fired power station in Pembrokeshire, Wales

Pembroke B Power Station is a 2,200 MWe natural gas-fired power station near Pembroke in Wales. The power station was officially opened in September 2012 and is the largest gas-fired power station in Europe. It is also the largest power station to be built in the UK since Drax power station came online in 1986. Pembroke Power Station currently generates enough power to supply 3.5 million homes and businesses. It is operated by RWE.

The Rugeley power stations were a series of two coal-fired power stations located on the River Trent at Rugeley in Staffordshire. The first power station on the site, Rugeley A power station was opened in 1961, but has since been closed and demolished. Rugeley B power station was commissioned in 1970, and closed on 8 June 2016. The cooling towers of which were demolished on 6 June 2021. It had an output of 1,000 megawatts (MW) and had a 400 kilovolt (kV) connection to the national grid. The B station provided enough electricity to power roughly half a million homes.

<span class="mw-page-title-main">North Tees Power Station</span>

North Tees Power Station refers to a series of three coal-fired power stations on the River Tees at Billingham in County Durham. Overall, they operated from 1921 until 1983, and the C station, the last on the site, was demolished in 1987. Billingham Biomass Power Station is to be built on their site.

Carrington Power Station is a combined cycle gas turbine power station, which was completed in Autumn 2016 and began commercial operation on 18 September 2016. It is located on the site of a former coal-fired power station, close to the villages of Carrington and Partington in the Greater Manchester Area and 12 km (7.5 mi) southwest of Manchester City Centre. The Manchester Ship Canal and the River Mersey run alongside the site, in Trafford, Greater Manchester, in North West England.

<span class="mw-page-title-main">Uskmouth power stations</span> Series of two coal-fired power stations south-east of Newport, Wales

The Uskmouth power stations refers to a series of two coal-fired power stations at the mouth of the River Usk in the south-east of Newport, Wales. The first of the two station, Uskmouth A power station, was built in the 1940s and demolished in 2002.

Blackburn Meadows power station is a biomass power station situated at Blackburn Meadows on the River Don, between Sheffield and Rotherham in South Yorkshire, England. Operated by E.ON UK, it was opened in 2014 and has an operating capacity of 30 megawatts.

<span class="mw-page-title-main">Croydon power stations</span>

The Croydon power stations refers to a pair of demolished coal-fired power stations and to a gas-fired power station in the Purley Way area of Croydon, London.

<span class="mw-page-title-main">Northfleet Power Station</span>

Northfleet Power Station was a coal-fired, later oil-fired, power station on the south bank of the Thames at Northfleet, Kent. Opened in 1963, it was converted to burn oil in 1972, and closed in 1991.

<span class="mw-page-title-main">Skelton Grange power station</span>

Skelton Grange Power Station refers to two now-demolished coal fired power stations that served the city of Leeds and surrounding areas. They were located in the Stourton area of the city. The power stations were built in the early 1950s and early 1960s, taken out of use in 1983 and 1994 and subsequently dismantled but the associated 275 kV switching substation was retained and remains in use.

Watford Power Station was a coal-fired power station situated in Watford's Riverside area. The station was built by the Watford Corporation Electricity Department starting with the installation of cables in 1899 with completion around 1900, near the banks of the River Colne. A gas turbine power station was commissioned in 1980.

References

  1. 1 2 3 "Down Memory Lane - End of an industrial era". Thurrock Gazette. 15 February 2016. Retrieved 7 January 2021.
  2. "Power Stations in the United Kingdom (operational at the end of May 2004)" (PDF). Retrieved 7 January 2021.
  3. 1 2 3 "Tilbury Power Station". RWE . Archived from the original on 18 May 2010. Retrieved 2 November 2009.
  4. 1 2 3 4 5 6 7 8 Royal Commission on the Historical Monuments of England (1985). The Power Stations of the Lower Thames. Swindon: RCHME.
  5. 1 2 Essex County Council Field Archaeology Unit. "Tilbury Wildlife Pond Tilbury Essex: Archaeological Monitoring and Recording" (PDF). Archaeology Data Service. p. 3. Retrieved 31 August 2011.
  6. "Tilbury2". Tilbury2. 2020. Retrieved 18 January 2020.
  7. Macalister, Terry (30 May 2011). "RWE to convert Tilbury power station into biomass plant". The Guardian . Retrieved 30 August 2011.
  8. Fiona Harvey and Natalie Starkey (5 July 2013). "RWE npower closes Tilbury biomass power station". The Guardian. Retrieved 7 July 2013.
  9. Terry Macalister (16 August 2013). "Tilbury power station mothballed after investment burns out". The Guardian. Retrieved 12 March 2016.
  10. "PLA welcome for proposed new power station on Thames". Port of London Authority . 14 March 2007. Archived from the original on 20 November 2008. Retrieved 15 November 2009.
  11. 1 2 3 4 The Electricity Council (1990). Handbook of Electricity Supply Statistics 1989. London: The Electricity Council. pp. 4, 8. ISBN   085188122X.
  12. Brown, Joe (2015). London Railway Atlas. Hersham: Ian Allan Publishing Ltd. p. 46. ISBN   9780711038196.
  13. Sheail, John (1990). Power in Trust: The Environmental History of the Central Electricity Generating Board. Oxford: Clarendon Press. p. 172. ISBN   0198546734.
  14. 1 2 3 CEGB. CEGB Statistical Yearbooks (various dates). London: CEGB.
  15. "British Power Stations operating at 31 December 1961". Electrical Review. 1 June 1962: 931.
  16. Garrett, Frederick C., ed. (1959). Garcke's Manual of Electricity Supply. London: Electrical Press. pp. A-136.
  17. GEGB Annual report and accounts, various years
  18. 'Power station seriously damaged', The Times, 17 November 1977, p. 2
  19. "Incidents". Essex County Fire & Rescue Service. 1 July 2008. Archived from the original on 18 July 2011. Retrieved 15 November 2009.
  20. "Fire breaks out at power station" (STM). BBC News . 29 July 2009. Retrieved 2 November 2009.
  21. "Tilbury power station blazes as wood pellets catch fire". BBC News . 27 February 2012. Retrieved 27 February 2012.
  22. "Tilbury power station chimneys demolished in seconds". BBC News . 28 September 2017. Retrieved 28 September 2017.
  23. "Final blow in power station's demolition". BBC News . 14 March 2019. Retrieved 17 March 2019.
  24. 1 2 "Goshems Farm landfill" . Retrieved 19 July 2020.
  25. 1 2 3 "Tilbury Energy Centre". 2018. Archived from the original on 16 January 2020. Retrieved 16 January 2020.
  26. "RWE freezes 2.5GW UK gas and energy storage project". Energy Live News. November 2018. Retrieved 16 January 2020.
  27. 1 2 3 4 5 6 "Thurrock Power". Thurrock Energy. Retrieved 16 January 2020.
  28. 1 2 3 4 "Tilbury Green Power". Tilbury Green Power. Retrieved 16 January 2020.