Bengaluru Commuter Rail

Last updated

Bengaluru Suburban Railway
Indian Railways Suburban Railway Logo.svg
Overview
Owner Indian Railways
Area served Bangalore Metropolitan Region
Locale Bangalore, Karnataka, India
Transit type Suburban rail
Number of lines4
Line numberUnder construction
  Sampige  
  Mallige  
  Paarijata  
  Kanaka  
Number of stations69
Operation
Operator(s) Bangalore Suburban Rail Company Limited
Technical
System length160.457 kilometres (99.703 mi)
Track gauge Broad gauge
System map

NammaMetroUptoPh-3withKannada.png

Bengaluru Suburban Railway (also Bengaluru Commuter Railway) is an under-construction suburban rail network for the city of Bangalore. A suburban rail system for the city was first proposed in 1983. Since then, several different route proposals were made but no suburban rail project took shape. It was finally approved in the 2019 Railway Budget.

Contents

History

A suburban rail service existed in Bangalore as early as in 1963 for HAL employees to commute from KSR Bangalore to Vimanapura Railway station. In 1983 a formal suburban rail system for Bangalore had first been proposed by a team from Southern Railway under then Railway Minister C. K. Jaffer Sharief and Member of Parliament representing Bangalore. Their recommendation had been to invest in three suburban rail lines and a 58-km ring railway. The package was estimated to cost ₹650 crore in 1983 terms (US$628.6 million) spread over a 25-year period.

In 1993 C. K. Jaffer Sharief Minister of Railways, India, influenced the State of Karnataka to established another committee to look into mass rapid transit. This committee recommended essentially the same put forward by Southern Railway in 1983 and the same circular railway. Both in 1983 and 1993 the proposal was rejected by then Prime Minister of India.

In 2007, RITES (Rail Indian Technical and Economic Services) was commissioned by the Government of Karnataka to conduct a CTTP (Comprehensive Traffic & Transportation Plan) for the city of Bangalore. Their report called for ten suburban rail routes totalling 204.0 km. As per the report, suburban rail (along existing rail routes) would cost much less than mass rapid transit systems.

Proposal made by Praja in 'Call To Action' report (July 2010) CRS route map - Schematic.jpg
Proposal made by Praja in 'Call To Action' report (July 2010)
Existing and proposed rail network Bangalore Suburban Rail Network1.png
Existing and proposed rail network

In July 2010, a proposal was made by Praja Bangalore in a 'Call To Action' report. This plan was supported & presented at the center for infrastructure, Sustainable Transportation and Urban Planning (CisTup), Indian Institute of Science (IISc), Bangalore. The proposal had suggested a 376 km network around three hubs (Yesvantpur Junction, Benniganahalli & Yelahanka Junction) with 42 new stations. [1] A key recommendation was to use the congested Bangalore City railway station only as a pass-through station.

In November 2011, RITES conducted a feasibility study exclusively for suburban rail services in Bangalore and submitted their final report to the Directorate of Urban Land Transport (DULT) in November 2012. [2] The 179-page report studied all existing routes totalling 440.8 km of the rail network in and around the city, and development of suburban rail services over three phases. [3]

The state government approved the suburban rail system on 5 July 2013. Chief Minister Siddaramaiah approved the system in the 2013-14 state budget that he presented on 9 July 2013. [4] The budget proposed the setting up of the Bengaluru Suburban Rail Corporation Limited, a special purpose vehicle (SPV) to implement the project estimated to cost 8,759 crore (US$1.1 billion). [5] [6]

In the 2016-17 Railway budget, Union Railway Minister Suresh Prabhu announced a partnership with Karnataka government for a ₹9,000 crore suburban rail network for Bangalore, but did not allocate any funds. [7] [8] On 3 February 2016, the state government proposed a modified version of the original RITES plan. This looked to kick-start the project with a ₹1,000 crore investment to connect Mandya with Kengeri, Whitefield with Baiyappanahalli and Tumakuru with Yeshwanthpura Junction. The state government released 100 crore towards this. [9] The state appointed RITES again to study the feasibility of the project, and the latter's survey deemed the project as feasible. [7] However, Railways stated that the proposed Phase Two of the project (linking Tumakuru and Yeshwanthpura Junction) was not feasible. [10]

In November 2018, RITES prepared a revised plan for a 161 km network that was again amended in August 2019 to reduce costs. Out of 82 stations, 29 stations were deleted, route length reduced to 148 km & costs lowered to ₹16,000 crores. This was finally accepted by Government of India. [11]

2007 proposal

CorridorLength (km)
Kengeri – KSR Bengaluru13.0
KSR Bengaluru – Whitefield24.0
KSR Bengaluru – Baiyappanahalli via Lottegollahalli23.0
Lottegollahalli – Yelahanka Junction7.0
Banaswadi – BMR Boundary29.0
Kengeri – BMR Boundary9.0
Yeshwanthpura Junction – BMR Boundary14.0
BMR Boundary – Hosur12.0
BMR Boundary – Ramanagara23.0
BMR Boundary – Tumakuru50.0
Total204.0

2010 proposal

RouteDistance (km)
Yeshwanthpura Junction – Yelahanka Junction – Devanahalli – Chikkaballapura60
Benniganahalli – Thanisandra Y elahanka Junction – Doddaballapura37
Yeshwanthpura Junction – Benninganahalli – Anekal Road – Hosur66
Tumakuru or Nelamangala – Yeshwanthpura Junction – Benniganahalli83
Yelahanka Junction – Benniganahalli – Whitefield – Malur – Bangarpet80
Yelahanka Junction – Yeshwanthpura Junction – KSR Bengaluru – Kengeri – Ramanagara50
Total route length (km)376

2012 proposal

FromToDistance (km)
KSR BengaluruMandya92.88
KSR BengaluruYeshwanthpura Junction5.35
Yeshwanthpura JunctionTumakuru64.00
Yeshwanthpura JunctionYelahanka Junction12.45
Yelahanka JunctionBaiyappanahalli19.23
Yeshwanthpura JunctionBaiyappanahalli16.12
Yelahanka JunctionDoddaballapura20.72
Yelahanka JunctionChikkaballapura46.05
BaiyappanahalliHosur48.59
KSR BengaluruBaiyappanahalli10.76
BaiyappanahalliBangarpet Junction59.45
SoladevanahalliKunigal45.2
Total →440.8

Funding

On 1 February 2020, finance minister, Nirmala Sitharaman mentioned in her budget that the project would be implemented at cost of ₹18,600 crores. The central government would provide 20% of the equity and facilitate external assistance up to 60 per cent of the project cost. It will be first of its kind and unique in India as it will have metro like facilities and rolling stock. It has slowest design speed among all the new suburban rail projects currently being implemented in India as Nagpur broad-gauge Metro and National Capital Region Transport Corporation are building rail tracks for design speed of 200 km/h with operating speed of 160 km/h.

Facilities

DPR for the project has included many rare and unique facilities in the system. [12]

Integrated multi-modal transport and last mile connectivity

Comprehensive Mobility Plan for Bangalore provides a roadmap for integrated public transport experience. [14]

Bengaluru suburban rail stations will be integrated with other modes of transport for seamless transfer between travel modes - as in European cities. Public Bus Service, Metro trains, Inter-city bus, Inter-city trains, Metrolite, Metro Neo, Hyperloop, BRTS, Peripheral Ring Road, Bus priority corridors, Airport metro, Airport Bus service, High speed Airport Train will be integrated with the Suburban train network.

Public Bicycle Sharing (PBS) and the Shared Micro-Mobility System initiatives have been launched to provide last mile connectivity to suburban rail stations. [15]

K-RIDE plans to evolve all 57 stations to integrated commercial hubs (smart station hubs) where people can work, park, shop, eat and trade. Approaches to suburban train stations will be provided from all directions. [16]

The suburban train station plan will not only focus on the development of modern station itself, but also on traffic circulation and road improvement plan, easy switch to other public transport, widening of approach roads, ramp based multi-level access as in the New Delhi Railway station re-development model. [17] [18]

Network

Existing services

Indian Railways currently operates MEMU and DEMU services.

  1. Indian Railway's South Western Railway zone operates several MEMU and DEMU train services from Bangalore to Hosur, Dharmapuri, Jolarpettai, Tumkur, Marikuppam near Kolar Gold Fields, Bangarapet, Hindupur, Mysore, Kolar, Kuppam and Hassan. [19]
  2. Hosur, Dharmapuri and Jolarpettai are across the state border in Tamil Nadu. Hindupur and Kuppam are across state border in Andhra Pradesh, while Tumakuru, Bangarapete, Mysuru, Marikuppam, Kolar and Hassan are in Karnataka.
  3. Service to and from Hassan, Hindupur, Hosur, Dharmapuri and Tumakuru are operated from Yesvantpur Junction, while services to Mysore, Kolar, Marikuppam, Kuppam, Bangarapet and Jolarpettai are from Bangalore City and Bangalore Cantonment.
Map of suburban rail with Namma metro's planned phase 3 expansions NammaMetroSchematicwithKannada.png
Map of suburban rail with Namma metro's planned phase 3 expansions

Though approved in principle by Government of India, budget allocations have been paltry over the last few years as only token amounts have been allocated. [20] [21] On 7 October 2020, the project was approved by Prime Minister's Office and the Cabinet Committee on Economic Affairs (headed by the Prime Minister). [22] [23] The State Government commenced providing budgetary support for the suburban rail project & ₹500 crores were allocated in the 2020-21 budget. [24] [25] Meanwhile, K-RIDE [26] has kick-started the Suburban project by calling tenders for Land Survey, hiring staff etc. [27] [28] [29] [30]

Two priority lines will be taken up first as per Government of Karnataka's advice. [31] These are Mallige Line and Kanaka Line. The suburban rail routes are named after local flowers. [32]

As of 2022, Prime Minister Narendra Modi planned to lay the foundation stone for the start of construction of the project on 20 June. [33]

Routes and lengths approved initially

Route [34] Line nameDistanceRidership
(estd, lakhs)
Length (km)No. of stations
ElevatedSurfaceElevatedSurface
KSR Bengaluru – Sriramapura – Yeshwanthpura Junction – Lottegollahalli – Yelahanka JunctionDevanahalli Sampige41.402.8218.9822.4287
Chikkabanavara JunctionYeshwanthpura Junction – Lottegollahalli – BenniganahalliMallige25.012.0312.90512.10568
Kengeri – Jnanabharathi – Bangalore CityBangalore CantonmentBaiyyappanahalliKrishnarajapuraWhitefield. [35] Parijaata35.521.6410.4025.12410
Heelalige – Karmelaram – Marathahalli – Doddanekundi – Yelahanka Junction – RajanukunteKanaka46.243.3413.2932.95415
Total148.179.8355.57592.5952240*

*The total number of stations is 58 (figures under individual routes include interchange stations).

Routes and lengths amended (May 2023)

In May 2023, K-Ride released amendments and the following changes were made:

Corridor-1: length amended to 42.522 km; Corridor-1A: a 5.95 km link to the airport has been planned; Corridor-2: extended to Soladevanahalli, length amended to 28.722 km; Corridor-4: length amended to 47.743km.

The total route length for Phase 1 would thus be 160.457 km.

Additional stations:

Corridor-1: (i) Between Airport-KIADB and Devanahalli (near Chikkasanne /IVC road); (ii) Between Judicial Layout and Yelahanka (near Allalasandra).

Corridor-1A: (i) Airport City; (ii) Airport Terminal.

Corridor-4: (i) Between Jakkur and Yelahanka (near Allalasandra); (ii) Between Yelahanka and Muddanahalli (near Nagenahalli); (iii) Between Muddanahalli and Rajanakunte (near Honnenahalli).

RouteNameFrom/toElevatedAt gradeLength (km)Stations
Elevated
Stations
At grade
Future stns
At grade
1  SampigeKSR Railway Station - Devanahalli17.81124.71142.522771
1AAirport Link3.5502.4005.9502 (Cut and Cover)-
2  MalligeBenniganahalli - Chikkabanawara9.25019.47228.7223102
3  ParijaataKengeri - Whitefield10.40025.12035.520851
4  KanakaHeelalige - Rajanakunte9.47538.26847.7433164
Total50.486109.971160.45722378

There will be five inter-change stations at (i) KSR Bengaluru city, (ii) Yesvantapur, (iii) Yelahanka, (iv) Benniganahalli and (v) Airport Trumpet.

Construction

During November 2021, tenders were called for the elevated viaduct portion of Corridor-2. However, there was a delay in awarding the tender due to land acquisition issues, railway land transfer, approval by IR, formalities etc. Meanwhile, a consortium of Egis, Louis Berger & AECOM JV won bid and were appointed General Consultants in February 2022. The tender for Corridor-2 was awarded to L&T in August 2022 for 8km of elevated viaduct. Construction began in mid-2023 after all hurdles were removed.

Tender for construction of Corridor-4 was awarded to L&T in August 2023.

As of August-2023, tender for Corridor-1 was under preparation.

Depots

Two depots were initially planned at Jnanabharathi (56.9 acres) and near Devanahalli at Akkupete (61.2 acres). Neither of these are on the priority Corridors 2 and 4. Hence, feasibility for a depot at Huskuru along Corridor-4 (Kanaka Line) was being explored.

Subsequently (in January 2023), the depot at Jnanabharathi was cancelled. A depot is planned at Soladevenahalli on 52.2 acres.

See also

Related Research Articles

<span class="mw-page-title-main">Mumbai Metro</span> Rapid transit system in Mumbai, India

The Mumbai Metro is a rapid transit (MRT) system serving the city of Mumbai and the wider Mumbai Metropolitan Region in Maharashtra, India.

<span class="mw-page-title-main">Namma Metro</span> Rapid transit system in Bengaluru, Karnataka, India

Namma Metro, also known as Bengaluru Metro, is a rapid transit system serving the city of Bengaluru, the capital city of the state of Karnataka, India. It is the second longest operational metro network in India with an operational length of 73.75 kilometers, just behind Delhi Metro. Upon its inauguration, it became the first underground metro system in South India. Namma Metro has a mix of underground, at grade, and elevated stations. Out of the 66 operational metro stations of Namma Metro as of October 2023, there are 57 elevated stations, eight underground stations and one at-grade station. The system runs on standard-gauge tracks.

<span class="mw-page-title-main">Yelahanka</span> Suburb / satellite town in Bengaluru Urban, Karnataka, India

Yalahanka is a suburb and Taluk of Bangalore Urban district in the Indian state of Karnataka. One of the zones of BBMP. It is the oldest part of present Municipal Bengaluru (Bangalore) city and the northern end of the city. It is Nadaprabhu Kempegowda I, of the Yelahanka Prabhu clans, who laid the foundation of present-day Bengaluru through the creation of a "mud fort town" in 1537 CE

<span class="mw-page-title-main">Urban rail transit in India</span> Overview of the urban rail transit system in India

Urban rail transit in India plays an important role in intracity transportation in the major cities which are highly populated. It consists of rapid transit, suburban rail, monorail, and tram systems.

<span class="mw-page-title-main">Purple Line (Namma Metro)</span> Line of Bengalurus Namma Metro

The Purple Line is a part of the Namma Metro rail system for the city of Bengaluru, Karnataka, India. As of 2023, the line is 43.49 km (27.02 mi) long and spans 37 stations from Challaghatta in the southwest to Whitefield (Kadugodi) to the east. The Purple Line is mostly elevated, with 31 elevated stations, 5 underground stations and 1 at-grade station. The Line passes through many prime activity centers of the city including Whitefield, Krishnarajapura, MG Road, Vidhana Soudha and Majestic station, which is an interchange station between Purple and Green Lines. Phase I of the Purple Line was the first underground metro section in South India.

<span class="mw-page-title-main">Yelahanka Lake</span> Lake in Karnataka, India

Yelahanka Lake is a water body near Yelahanka, a suburb of Bangalore.

The Srinagar Metro is a light rail transit planned for the city of Srinagar, Jammu and Kashmir. The plans for the Srinagar Metro have been finalised with the work expected to start once the project gets nod from union cabinet. The proposed network will have two corridors. Each corridor of Srinagar metro will have 12 stations each with the total cost expected to be ₹5,559 crore.

<span class="mw-page-title-main">Varanasi Metro</span> Light rail transit system

The Varanasi Metro is a light rail transit system proposed for the city of Varanasi, Uttar Pradesh, India. The proposed system consists of 2 corridors that span from BHEL to Banaras Hindu University (19.35 km) and Benia Bagh to Sarnath (9.885 km). The feasibility study of the project was done by RITES and was completed in June 2015.

Coimbatore Metro, also known as Kovai Metro, is a proposed rapid transit system for Coimbatore, Tamil Nadu.

The Pink Line of Namma Metro is under construction and will form part of the metro rail network for the city of Bangalore, Karnataka, India. The 21.25 km (13.20 mi) line connects Kalena Agrahara station on Bannerghatta Road in the south with Nagawara station on Outer Ring Road in the north. The Pink Line is mostly underground but also has a 6.98 km (4.34 mi) elevated section and a 0.48 km (0.30 mi) at-grade (surface) section. There are 18 stations on the line, including 12 underground and 6 elevated ones. Pink Line will have an interchange with the Purple Line at MG Road station. It will also have interchanges with the Yellow line at Jayadeva Hospital station and with the Blue Line at Nagawara. Both these lines are under construction. The entire line is planned to open at the end of March 2025.

Transport in Bangalore consists of several intracity commute modes such as BMTC buses, Namma Metro rail services, taxis and auto rickshaws, as well as several intercity forms of transport: Government operated KSRTC, NWKRTC, KKRTC, other states RTC buses, Private bus operators, trains, and flights.

Kerala Rail Development Corporation d/b/a Kerala-Rail is a public sector joint venture company under the ownership of the Government of Kerala for the railway infrastructure development in Kerala. The company was incorporated on 3 January 2017.

Kempegowda International Airport Halt railway station is an Indian Railways' railway station located near Kempegowda International Airport, Bangalore in the Indian state of Karnataka which is located about 45 km away from the Bangalore City on Yelahanka–Kolar line. This station will serve the Kempegowda International Airport.

The Blue Line or ORR-Airport Metro Line is part of the Namma Metro rail network for the city of Bangalore, Karnataka, India. It consists of two sections - Phase-2A and Phase-2B. Construction of Phase-2A began in August 2021. Construction of Phase-2B began in February 2022. The 58.19 km line connects Central Silk Board with the Kempegowda International Airport. The Line is mostly elevated but also has an at-grade (surface) section close to the Airport and 2 short underground sections where it passes the Jakkur Aerodrome and Yelahanka AFB. There are 30 stations on the line of which the two station/s at the Airport may be at surface level or underground. Blue Line will have interchanges with the Yellow Line at Central Silk Board, Purple Line at KR Pura, Pink Line at Nagawara and with the future /proposed Orange Line at Hebbal.

<span class="mw-page-title-main">Nagawara metro station</span> Upcoming Namma Metro station under Pink & Blue Lines

Nagawara is an upcoming important underground northern terminal metro station on the North-South corridor of the Pink Line and upcoming elevated metro station on the Blue Line of Namma Metro in Bangalore, India. This metro station will be an interchange metro station between Pink Line and Blue Line.

Yelahanka is an upcoming important elevated metro station on the North-South corridor of the Blue Line of Namma Metro in Bangalore, India. This metro station will serve the main Yelahanka suburban area, which contains Yelahanka Junction, along with its Rail Wheel Factory, Yelahanka Lake and Yelahanka Air Force Station. It also includes many residential areas such as SOBHA Palm Court Apartments, Park View Apartments and SLV Nest Apartments.

Bagalur Cross is an upcoming elevated metro station on the North-South corridor of the Blue Line of Namma Metro in Bangalore, India. This metro station will comprise of the main Bagalur area with many educational institutions like Chrysalis High (Yelahanka), Ryan International School, Nitte Meenakshi Institute of Technology followed by prime locations like Zodiac Clothing Company Ltd., Palanahalli Lake Park, Manipal Academy of Higher Education and BSF Institute of Technology. This metro station is slated to be operational around June 2026.

<span class="mw-page-title-main">Airport City metro station</span> Upcoming Namma Metro station under Blue Line

Airport City is an upcoming at-grade metro station on the north-south corridor of the Blue Line of Namma Metro in Bangalore, India. This will be an important metro station that will comprise many commercial infrastructures that will be developed by BIAL, including the KIA Air Traffic Control Tower, Nadaprabhu Kempegowda Statue, a few catering manufacturing companies including SATS, Air India's SATS, Blue Dart Express, and IndiGo Hangar for maintenance and training purposes. This metro station is to become operational around June 2026.

Delhi–Varanasi High Speed Rail Corridor is India's second High-speed rail project after the Mumbai-Ahmedabad High Speed Rail Corridor. The 958-kilometre (595 mi) HSR corridor will connect Varanasi to Delhi through 13 stations along with a 123 km long spur connecting Lucknow and Ayodhya.

The Chennai-Mysuru high speed rail corridor is India's third high-speed rail project after the Mumbai Ahmedabad High Speed Rail Corridor and Delhi Varanasi High Speed Rail Corridor. The 435 km HSR corridor will connect Chennai to Mysuru through 9 stations.

References

  1. "CRS: Call to Action Report".
  2. Aparajita Ray (18 June 2012). "RITES sent commuter rail feasibility study to DULT". The Times of India . Archived from the original on 12 January 2014. Retrieved 7 April 2013.
  3. Suchith Kidiyoor (10 November 2012). "440-km commuter rail network planned in Karnataka". Dnaindia.com. Retrieved 30 July 2013.
  4. ref>Chitra V. Ramani (13 July 2013). "Green signal for suburban train system". The Hindu . Retrieved 30 July 2013.
  5. "Bangalore suburban rail a Kharge-Siddu dream". The Times of India . TNN. 13 July 2013. Archived from the original on 30 July 2013. Retrieved 30 July 2013.
  6. "Govt to set up SPV to implement Bangalore suburban rail system". Business Standard . Press Trust of India. 12 July 2013. Retrieved 30 July 2013.
  7. 1 2 "Phase 1 of suburban rail network feasible: George". The Times of India. 17 November 2016.
  8. "State seeks Centre's nod for suburban rail project". The Hindu. 25 September 2015. ISSN   0971-751X . Retrieved 29 September 2020.
  9. "Suburban rail gets a push, railways to link 4 stations". The New Indian Express. Retrieved 18 November 2016.
  10. "Whitefield-Byappanahalli suburban rail link okayed". Deccan Herald. Retrieved 18 November 2016.
  11. "RITES submits revised DPR of Bengaluru Suburban Rail project".
  12. https://kride.in/wp-content/uploads/2021/09/Detailed-Project-Report-BSRP.pdf [ bare URL PDF ]
  13. "Bengaluru suburban rail to offer Metro-like facilities; launch only by 2026 | Bengaluru News - Times of India". The Times of India . 21 November 2019.
  14. "Bengaluru's Draft Mobility Plan in a nutshell: Elevated corridors get Rs 18,480 crore". 18 December 2019.
  15. "DULT calls operators to set up bicycle sharing network under 'Trin Trin' initiative in Bengaluru". 16 September 2021.
  16. "Explained: What is the Bengaluru Suburban Rail Project, and how will it help people living in and around the city?". 30 June 2021.
  17. "Railways to restart skeletal suburban train services in and around Bengaluru". The News Minute. 4 December 2020. Retrieved 4 December 2020.
  18. Philip, Christin Mathew (5 February 2020). "Rs 18,600-cr Bengaluru suburban rail gets just Rs 1 crore in Pink Book". The Times of India. Retrieved 29 September 2020.
  19. "Budget 2020: Push to Bengaluru suburban rail project will boost urban transport in Karnataka". ETGovernment.com. Retrieved 29 September 2020.
  20. "K-RIDE floats Land Survey Tender for Bengaluru Suburban Rail". 27 February 2020.
  21. "K-RIDE begins survey process for suburban rail project". 27 February 2020.
  22. "Karnataka Budget: Rs 500 crore for Bengaluru suburban railway comes as a saving grace". Deccan Herald. 6 March 2020. Retrieved 29 September 2020.
  23. "Suburban Rail Project Bangalore: Mooted 37 yrs ago, 148km Bengaluru suburban rail project wins nod | Bengaluru News - Times of India". The Times of India . 8 October 2020.
  24. "Suburban rail SPV to take shape in a month". Deccan Herald. 5 July 2019. Retrieved 29 September 2020.
  25. "Tender for Land Survey floated". The Times of India . 26 February 2020.
  26. "Preparatory works begin for suburban rail project". The New Indian Express. Retrieved 29 September 2020.
  27. "Long-pending Bengaluru Suburban Rail Project, worth Rs 17,000 crore awaits clearance from Centre; details here". The Financial Express. 6 December 2019. Retrieved 29 September 2020.
  28. "With Finance Ministry Clearing Bangalore Suburban Project, K-Ride Starts Hiring Engineers". 27 June 2020.
  29. "Latest Real Estate News, Information & Trends 2021". realtybeat.in. Retrieved 10 July 2021.
  30. Philip, Christin Mathew (6 March 2021). "Bengaluru suburban rail corridors likely to be named after flowers". The Times of India. Retrieved 10 July 2021.
  31. "PM Modi to lay foundation stone for Bengaluru Suburban Rail project on June 20". The Indian Express. 7 June 2022. Retrieved 7 June 2022.
  32. "Sampige, Mallige, Parijaata, Kanaka: Bengaluru suburban rail corridors may be named after flowers". Deccan Herald. 7 March 2021. Retrieved 11 December 2021.
  33. "Bengaluru's suburban rail dream now closer to reality". The Times of India. 5 November 2019. Retrieved 7 November 2019.