Percentage of completion (PoC) is an accounting method of work-in-progress evaluation, for recording long-term contracts. GAAP allows another method of revenue recognition for long-term construction contracts, the completed-contract method.

Contents

When to use

The accounting for long term contracts using the percentage of completion method is an exception to the basic realization principle. This method is used wherein the revenues are determined based on the costs incurred so far. The percentage of completion method is used when:

  1. Estimate profitability
  2. Measure progress toward completion.

Losses are recognized in the year when they are discovered, the same way as for the completed contract method. The balance sheet presentation is the same as in the completed contract method.

Formulas used

Revenues and gross profit are recognized each period based on the construction progress, in other words, the percentage of completion. Construction costs plus gross profit earned to date are accumulated in an asset account (construction in process, also called construction in progress), and progress billings are accumulated in a liability account (billing on construction in process). Construction-in-progress are generally not classified as inventory as it would not be in-line with IAS2.9 (Inventories to be stated at lower of cost or NRV).

Although the formula for recognizing income in the current period can vary, a widely accepted one is as follows:

where... the number of periods lapsed since the inception of the contract.

the expected length of the contract
the current period
the total estimated cost of contract

Examples

For example, let's say our total estimated cost for the contract is $10,000 and our contract value is $12,000. We know that project will be completed in 2 years. Now, after the first year we see that total cost incurred in this first year is $3,000. So according to the percentage-of-completion method: Cost percentage = 3000/10000 = 30%; so we will recognize 30% revenue in the income statement for the first year.

Income statement of AnantPurohit corporation Pvt. Ltd. for the year ended on xx/yy/zzzz:

Sales3,600 (30% of 12,000)
Cost of goods3,000
Profit600

In the next year, some more complicated parts enter the game. Let's say that after completion of the second year, our expected cost changes to 11,000. Assume our cost to date is 5,500 (3,000 in the first year, 2,500 in the second), the percentage completed is 5,500/11,000 = 50%. Thus, the revenue to be recognized is (50% of 12,000) – 3,600 (previously recognized) = 2,400

Income statement of AnantPurohit corporation Pvt. Ltd. for the year ended on xx/yy/zzzz+1:

Sales2,400
Cost of goods2,500 (5,500 till date – 3,000 last year)
Loss100

Now let's say that for the next year, our total cost estimation is increased to 15,000 due to increases in raw material and labor costs. We know that we are going to incur a loss of 3000 at the end of the contract period. For the third year, our cost to date reaches 10,500, so according to PoC: Percentage completion = 10,500/15,000 = 70% Revenue = 70% of 12,000 – previously recognized = 8,400 – 6,000 = 2,400. However, because we are going to have a total loss of 3,000 on the contract..... we must recognize the total loss in the period it is estimated. As a result, our Cost of goods will be 5,900 (total loss recognized because of 500 profit recognized in previous periods [3,500] + Sales [2,400]); we reached this inductively by figuring the Sales and the Loss before the Cost of goods.

Income statement of AnantPurohit corporation Pvt. Ltd. for the year ended on xx/yy/zzzz+2:

Sales2,400
Cost of goods5,900
Loss3,500

In final year, our cost is 4,500 and revenue is 3,600. But we record only 3,600 in Cost of goods because we already recognized the total loss in the last period.

Sales3,600
Cost of goods3,600
Profit/loss0

Total Profit/Loss from the contract = 600-100-3,500= 3,000 Net Loss

Balance sheet presentation

Disclosures

As per IAS 11.42-43, an entity shall present:

(a) the gross amount due from customers for contract work as an asset; and

(b) the gross amount due to customers for contract work as a liability.

(These should be separate line-items on the face on the balance sheet.)

The gross amount due from/to customers for contract work is the net amount of:

(a) costs incurred plus recognized profits; less

(b) the sum of recognized losses and progress billings

for all contracts in progress.

Related Research Articles

<span class="mw-page-title-main">Cost accounting</span> Procedures to optimize practices in cost efficient ways

Cost accounting is defined by the Institute of Management Accountants as "a systematic set of procedures for recording and reporting measurements of the cost of manufacturing goods and performing services in the aggregate and in detail. It includes methods for recognizing, classifying, allocating, aggregating and reporting such costs and comparing them with standard costs". Often considered a subset of managerial accounting, its end goal is to advise the management on how to optimize business practices and processes based on cost efficiency and capability. Cost accounting provides the detailed cost information that management needs to control current operations and plan for the future.

The net present value (NPV) or net present worth (NPW) applies to a series of cash flows occurring at different times. The present value of a cash flow depends on the interval of time between now and the cash flow. It also depends on the discount rate. NPV accounts for the time value of money. It provides a method for evaluating and comparing capital projects or financial products with cash flows spread over time, as in loans, investments, payouts from insurance contracts plus many other applications.

<span class="mw-page-title-main">Depreciation</span> Decrease in asset values, or the allocation of cost thereof

In accountancy, depreciation is a term that refers to two aspects of the same concept: first, the actual decrease of fair value of an asset, such as the decrease in value of factory equipment each year as it is used and wears, and second, the allocation in accounting statements of the original cost of the assets to periods in which the assets are used.

<span class="mw-page-title-main">Project accounting</span> Accounting systems geared toward project management

Project accounting is a type of managerial accounting oriented toward the goals of project management and delivery. It involves tracking, reporting, and analyzing financial results and implications, and sometimes the creation of financial reports designed to track the financial progress of projects; the information generated by this analysis is used to aid project management.

<span class="mw-page-title-main">Net income</span> Income less all expenses and losses

In business and accounting, net income is an entity's income minus cost of goods sold, expenses, depreciation and amortization, interest, and taxes for an accounting period.

<span class="mw-page-title-main">Deferral</span> Term in accounting

A deferral, in accrual accounting, is any account where the income or expense is not recognised until a future date, e.g. annuities, charges, taxes, income, etc. The deferred item may be carried, dependent on type of deferral, as either an asset or liability. See also accrual.

In business, operating margin—also known as operating income margin, operating profit margin, EBIT margin and return on sales (ROS)—is the ratio of operating income to net sales, usually expressed in percent.

<span class="mw-page-title-main">Gross margin</span> Gross profit as a percentage

Gross margin is the difference between revenue and cost of goods sold (COGS), divided by revenue. Gross margin is expressed as a percentage. Generally, it is calculated as the selling price of an item, less the cost of goods sold, then divided by the same selling price. "Gross margin" is often used interchangeably with "gross profit", however the terms are different: "gross profit" is technically an absolute monetary amount and "gross margin" is technically a percentage or ratio.

<span class="mw-page-title-main">Revenue recognition</span>

The revenue recognition principle is a cornerstone of accrual accounting together with the matching principle. They both determine the accounting period in which revenues and expenses are recognized. According to the principle, revenues are recognized when they are realized or realizable, and are earned, no matter when cash is received. In cash accounting—in contrast—revenues are recognized when cash is received no matter when goods or services are sold.

<span class="mw-page-title-main">Matching principle</span>

In accrual accounting, the matching principle instructs that an expense should be reported in the same period in which the corresponding revenue is earned, and is associated with accrual accounting and the revenue recognition principle states that revenues should be recorded during the period in which they are earned, regardless of when the transfer of cash occurs. By recognizing costs in the period they are incurred, a business can see how much money was spent to generate revenue, reducing "noise" from timing mismatch between when costs are incurred and when revenue is realized. Conversely, cash basis accounting calls for the recognition of an expense when the cash is paid, regardless of when the expense was actually incurred.

Construction accounting is a form of project accounting applied to construction projects. See also production accounting. Construction accounting is a vitally necessary form of accounting, especially when multiple contracts come into play. The construction field uses many terms not used in other forms of accounting, such as "draw" and progress billing. Construction accounting may also need to account for vehicles and equipment, which may or may not be owned by the company as a fixed asset. Construction accounting requires invoicing and vendor payment, more or less as to the amount of business done.

A cost overrun, also known as a cost increase or budget overrun, involves unexpected incurred costs. When these costs are in excess of budgeted amounts due to a value engineering underestimation of the actual cost during budgeting, they are known by these terms.

<span class="mw-page-title-main">Installment sales method</span>

The installment sales method is one of several approaches used to recognize revenue under the US GAAP, specifically when revenue and expense are recognized at the time of cash collection rather than at the time of sale. Under the US GAAP, it is the principal method of revenue recognition when the recognition occurs subsequently to the sale.

In insurance, deferred acquisition costs (DAC) is an asset on the balance sheet representing the deferral of the cost of acquiring new insurance contracts, thereby amortising the costs over their duration. Insurance companies face large upfront costs incurred in issuing new business, such as commissions to sales agents, underwriting, bonus interest and other acquisition expenses.

The value of work done (VOWD) is a project management technique for measuring and estimating the project cost at a point in time. It is mainly used in project environments of the Petroleum industry and is defined as the value of goods and services progressed, regardless of whether or not they have been paid for or received. The primary purpose of determining VOWD is to get an accurate and comprehensive as possible estimate of cost for a project at a point in time. This is used in overall project management including reporting and cost control.

Notional profit is an estimate of earnings primarily used in the building and construction industry. It is used to smooth out fluctuations in reported revenue due to contracts that take a long time to complete. It is calculated by the equation:

The Completed-contract method is an accounting method of work-in-progress evaluation, for recording long-term contracts. GAAP allows another method of revenue recognition for long-term construction contracts, the percentage-of-completion method. With this method, revenue is recognized when the contract is fulfilled. The contract is considered complete when the costs remaining are insignificant.

The following is a glossary of terms relating to construction cost estimating.

A construction contract is a mutual or legally binding agreement between two parties based on policies and conditions recorded in document form. The two parties involved are one or more property owners and one or more contractors. The owner, often referred to as the 'employer' or the 'client', has full authority to decide what type of contract should be used for a specific development to be constructed and to set out the legally-binding terms and conditions in a contractual agreement. A construction contract is an important document as it outlines the scope of work, risks, duration, duties, deliverables and legal rights of both the contractor and the owner.

The IAS 11 standard of International Accounting Standards set out requirements for the accounting treatment of the revenue and costs associated with long-term construction contracts. By their nature, construction activities and contracts are long-term projects, often beginning and ending in different accounting periods. Until its replacement with IFRS 15 in January 2018, IAS 11 helped accountants with measuring to what extent costs, revenue and possible profit or loss on the project are incurred in each period.

References

    Sources