Termination for convenience

Last updated

A termination for convenience clause, or "T for C" clause, [1] enables a party to a contract to bring the contract to an end without the need to establish that the other party is in default, for example because the client party's needs have changed, or in order to arrange for another party to complete the contract. [2]

Contents

Parties may agree to include a termination for convenience clause in a contract under the freedom of contract principle. However, in some countries and legal jurisdictions they may be statute law or case law which affects the operation or interpretation of such a clause.

Use in the United States

In the United States, Part 49 of the Federal Acquisition Regulation (FAR) establishes policies and procedures relating to the complete or partial termination of contracts for the convenience of the Government, alongside making provision for termination due to the default of the contractor. When it is in the government's interest, the FAR provides for contracts to be terminated. In circumstances where there is no contractor default, the grounds for termination will be for "the convenience of the government". [3] Part 49.104 includes an opportunity for a terminated contractor to submit a termination settlement proposal, which is to be submitted "promptly". [3] :Part 49.104

Termination policies for contracts for the acquisition of commercial items are covered separately in FAR 12.403, and the FAR notes that the concepts involved in such termination are different from the Part 49 concepts. [4]

Normally, where the price of the undelivered balance of the contract is less than $5,000, the contract would not be terminated for convenience but would be permitted to run to completion. [5]

In the case of G. L. Christian and Associates v. United States (1963), [6] which gave rise to the Christian Doctrine, the US Department of the Army sought to rely on the standard termination for convenience clause outlined in the Armed Services Procurement Regulations (ASPR) even though the Army had failed to include this termination for convenience clause in the contract.

Other examples

In Canada, the Supreme Court of Canada has recognised that good faith contractual performance is a general organising principle of the common law. This duty applies to all contracts, requiring parties to act honestly in the performance of their obligations, and therefore would operate to determine whether activation of a termination for convenience clause had been done in good faith. [7]

In Qatar, under Article 707 of the Qatar Civil Code, an employer has a right to terminate a construction contract at any time, and if it does so the contractor is entitled to payment for loss of profit on unperformed works. [8]

In Singapore, clause 31.4(1) of the Public Sector Standard Conditions Of Contract (PSSCOC) issued by the Building and Construction Authority allows the employer to terminate a contract "at any time" by virtue of "a written notice of Termination". [9] [8]

The FIDIC Red Book 1999 contains similar provisions to the PSSCOC form. [8] Under most of the family of JCT contracts, there is no general right to terminate without cause. [10]

Parties to a contract may agree that they will not terminate it during a specified period, but that either party may opt to do so once that period has expired. In the Austrian case of pressetext Nachrichtenagentur GmbH v Republic of Austria (1998), one of the issues addressed at the European Court of Justice was a clause to this effect. The court, referring to the 1992 European Union regulations which were then current, confirmed that an indefinite term contract with an agreement not to terminate for a specified period would not be automatically considered a breach of EU rules. [11]

Related Research Articles

<span class="mw-page-title-main">Breach of contract</span> Type of civil wrong in contract law

Breach of contract is a legal cause of action and a type of civil wrong, in which a binding agreement or bargained-for exchange is not honored by one or more of the parties to the contract by non-performance or interference with the other party's performance. Breach occurs when a party to a contract fails to fulfill its obligation(s), whether partially or wholly, as described in the contract, or communicates an intent to fail the obligation or otherwise appears not to be able to perform its obligation under the contract. Where there is breach of contract, the resulting damages have to be paid to the aggrieved party by the party breaching the contract.

A work of the United States government is defined by the United States copyright law, as "a work prepared by an officer or employee of the United States Government as part of that person's official duties". Under section 105 of the Copyright Act of 1976, such works are not entitled to domestic copyright protection under U.S. law and are therefore in the public domain.

A subcontractor is a person or business that undertakes to perform part or all of the obligations of another's contract.

An employment contract or contract of employment is a kind of contract used in labour law to attribute rights and responsibilities between parties to a bargain. The contract is between an "employee" and an "employer". It has arisen out of the old master-servant law, used before the 20th century. Employment contracts relies on the concept of authority, in which the employee agrees to accept the authority of the employer and in exchange, the employer agrees to pay the employee a stated wage.

The Federal Acquisition Regulation (FAR) is the principal set of rules regarding Government procurement in the United States, and is codified at Chapter 1 of Title 48 of the Code of Federal Regulations, 48 CFR 1. It covers many of the contracts issued by the US military and NASA, as well as US civilian federal agencies.

In the United States, the processes of government procurement enable federal, state and local government bodies in the country to acquire goods, services, and interests in real property. Contracting with the federal government or with state and local public bodies enables interested businesses to become suppliers in these markets.

The Joint Contracts Tribunal, also known as the JCT, produces standard forms of contract for construction, guidance notes and other standard documentation for use in the construction industry in the United Kingdom. From its establishment in 1931, JCT has expanded the number of contributing organisations. Following recommendations in the 1994 Latham Report, the current operational structure comprises seven members who approve and authorise publications. In 1998 the JCT became a limited company.

<i>Photo Production Ltd v Securicor Transport Ltd</i>

Photo Production Ltd v Securicor Transport Ltd[1980] UKHL 2 is an English contract law case decided by the House of Lords on construction of a contract and the doctrine of fundamental breach.

Several terms and common clauses are used in contracts to refer to time, including usage in reference to the time at which, or the length of the period during which, a contracted activity is to be undertaken.

Construction law is a branch of law that deals with matters relating to building construction, engineering, and related fields. It is in essence an amalgam of contract law, commercial law, planning law, employment law and tort. Construction law covers a wide range of legal issues including contract, negligence, bonds and bonding, guarantees and sureties, liens and other security interests, tendering, construction claims, and related consultancy contracts. Construction law affects many participants in the construction industry, including financial institutions, surveyors, quantity surveyors, architects, carpenters, engineers, construction workers, and planners.

<i>Burger King Corporation v Hungry Jacks Pty Ltd</i> Australian court case between Burger King and Hungry Jacks

Burger King Corporation v Hungry Jack's (2001) 69 NSWLR 558 was an Australian court case decided in the New South Wales Court of Appeal on 21 June 2001, concerning a dispute between United States-based fast food chain Burger King, and its Australian franchisee Hungry Jack's. It related to the breach of a business development agreement between the two companies, and the resulting attempts of Burger King to terminate the contract. The Court of Appeal decided that Burger King could not terminate the contract, for several reasons, one of which was that it was in breach of an implied term of good faith, having taken steps to engineer the breach of the contract.

The New Engineering Contract (NEC), or NEC Engineering and Construction Contract, is a formalised system created by the UK Institution of Civil Engineers that guides the drafting of documents on civil engineering, construction and maintenance projects for the purpose of obtaining tenders, awarding and administering contracts. The NEC contract is widely used in both the United Kingdom. There have been attempts, largely unsuccessful, to introduce the NEC contract into both Australia and New Zealand from at least 1994 but the contract remains relatively obscure in both countries.

An equitable adjustment, in government contracting, is a contract adjustment pursuant to a changes clause, to compensate the contractor expense incurred due to actions of the Government or to compensate the Government for contract reductions. An equitable adjustment includes an allowance for profit; clauses that provide for adjustments, excluding profit, are not considered "equitable adjustments."

<i>G. L. Christian and Associates v. United States</i> 1963 United States Federal Acquisition Regulation (FAR) court case

G.L. Christian and Associates v. United States is a 1963 United States Federal Acquisition Regulation (FAR) court case which has become known as the Christian Doctrine. The case held that standard clauses established by regulations may be considered as being in every Federal contract. Because the FAR is the law, and government contractors are presumed to be familiar with the FAR, a mandatory clause that expresses a significant or deeply ingrained strand of public procurement policy will be incorporated into a Government contract by operation of law, even if the parties intentionally omitted it.

<i>Bunge Corp v Tradax Export SA</i>

Bunge Corporation v Tradax Export SA[1981] UKHL 11 is an English contract law case concerning the right to terminate performance of a contract.

Retainage is a portion of the agreed upon contract price deliberately withheld until the work is substantially complete to assure that contractor or subcontractor will satisfy its obligations and complete a construction project. A retention is money withheld by one party in a contract to act as security against incomplete or defective works. They have their origin in the British construction industry Railway Mania of the 1840s but are now common across the industry, featuring in the majority of construction contracts. A typical retention rate is 5% of which half is released at completion and half at the end of the defects liability period. There has been criticism of the practice for leading to uncertainty on payment dates, increasing tensions between parties and putting monies at risk in cases of insolvency. There have been several proposals to replace the practice with alternative systems.

<span class="mw-page-title-main">Austria Press Agency</span>

The Austria Press Agency is the national news agency and the leading information provider in Austria. It is owned by Austrian newspapers and the national broadcaster ORF.

A notice period or period of notice within a contract may by defined within the contract itself, or subject to a condition of reasonableness. In an employment contract, a notice period is a period of time between the receipt of the letter of dismissal and the end of the last working day. This time period does not have to be given to an employee by their employer before their employment ends. The term also refers to the period between a termination date or resignation date and the last working day in the company when an employee leaves or when a contract ends.

General Dynamics Corp. v. United States, 563 U.S. 478 (2011), is a U.S. Supreme Court case in which the State Secrets Privilege prevented the plaintiff from using the evidence it needed to protect itself from an expensive judgement.

References

  1. McGreevy, S., T for C clauses set no limits on termination, accessed 27 December 2020
  2. Garrett, L., UK: Termination For Convenience, published 5 August 2013, accessed 18 April 2020
  3. 1 2 FAR Part 49, accessed 28 March 2020
  4. FAR 12.403, accessed 3 April 2020
  5. FAR 49.101(c), accessed 3 April 2020
  6. G. L. Christian and Associates v. the United States, 312 F.2d 418 (Ct. Cl. 1963), accessed 28 December 2020
  7. Mireault, A., An Uncertain Fate: Changing Principles of Termination for Convenience, MLT Aikins LLP, published 17 December 2018, accessed 23 April 2020
  8. 1 2 3 White and Case, Termination for convenience: What is the contractor entitled to?, Justin Bailey, Michael Turrini and Therese Marie Rogers, published 26 April 2017, accessed 21 April 2020
  9. Building and Construction Authority, Public Sector Standard Conditions Of Contract 2014, seventh edition, accessed 21 April 2020
  10. Joint Contracts Tribunal, Termination under JCT building contracts, published 22 July 2016, accessed 23 April 2020
  11. European Court of Justice, pressetext Nachrichtenagentur GmbH v Republik Österreich (Bund), APA-OTS Originaltext-Service GmbH and APA Austria Presse Agentur registrierte Genossenschaft mit beschränkter Haftung, Case C-454/06, paragraph 75, delivered on 19 June 2008, accessed 9 January 2024