Several terms and common clauses are used in contracts to refer to time, including usage in reference to the time at which, or the length of the period during which, a contracted activity is to be undertaken.
"Time is of the essence" is a term used in contract law in England and Wales (a legal jurisdiction within the United Kingdom), Canada, Australia, New Zealand, other Commonwealth countries and the United States, expressing the need for timely performance of a contractual obligation, [1] i.e. indicating that one or more parties to the agreement must perform by the time to which the parties have agreed if a delay will cause material harm. Were a time is of the essence clause is included in a contract, a court may nonetheless determine that minor delay did not cause material harm and thus that no breach of contract occurred. [2]
"Time is of the essence" may be contrasted with "reasonable time", where a delay in performing may be justified if it is reasonably required, based upon subjective circumstances such as unexpected weather, [1] and with the phrase time at large, which describes a situation where a party to a contract is relieved from the duty to perform work by a specific deadline due to actions of the principal that prevent timely completion. [3]
"Time is of the essence" may also be contrasted with an "express condition", where a specific contract term must be performed to avoid breach, such as in the Court of Appeals of Indiana's decision in Dove v. Rose Acre Farms, Inc. 434 N.E.2d 931 (Ct. App. Ind. 1982). [4]
"Time at large" is a common law principle [5] which is covered by a large body of case law. [6] It can arise in four types of situation:
The case of Holme v Guppy (1838) confirms the "prevention principle", which states that "if the party be prevented by the refusal of the other contracting party from completing the contract within the time limited he is not liable in law for the default". [8]
Where time is "at large", there is an implied term obliging the contractor to complete the work within a reasonable time. [6] The facts of the case will determine what is a reasonable time. [7] It is generally agreed that it is not in the interests of either an employer or a contractor to move into time being "at large", [6] and Bellhouse and Cowan note that most forms of contract now have "adequate extension of time procedures", so it has become difficult to argue that an "at large" situation has arisen in most situations. [5]
"The principle in Bramall & Ogden" (referring to the case of Bramall & Ogden v Sheffield City Council (1983) 29 BLR 73) [9] established that confused legal drafting can give rise to a situation where time is "at large" due to the absence of agreement on contractual time for performance. In this case, Sheffield had contracted for the construction of 123 houses, which were completed on various dates. The contract provided for liquidated damages applicable on the number of houses incomplete, and stated a date for completion as 6 December 1976. The contract did not provide for sectional completion and the court held that the sectional basis on which the liquidated damages clause was to operate was inconsistent with the single end-date for anticipated completion, meaning that Sheffield were unable to enforce a damages claim for delay. [10] [5]
"Time at large" arguments may also be utilised in a civil law context. [5]
Standard form contracts such as the Joint Contracts Tribunal (JCT) contract and the New Engineering Contract (NEC) family include various mechanisms for extending contracts to account for delay but still retain the need for the works to be completed by an agreed date. [11]
At common law, damages are a remedy in the form of a monetary award to be paid to a claimant as compensation for loss or injury. To warrant the award, the claimant must show that a breach of duty has caused foreseeable loss. To be recognized at law, the loss must involve damage to property, or mental or physical injury; pure economic loss is rarely recognized for the award of damages.
Breach of contract is a legal cause of action and a type of civil wrong, in which a binding agreement or bargained-for exchange is not honored by one or more of the parties to the contract by non-performance or interference with the other party's performance. Breach occurs when a party to a contract fails to fulfill its obligation(s), whether partially or wholly, as described in the contract, or communicates an intent to fail the obligation or otherwise appears not to be able to perform its obligation under the contract. Where there is breach of contract, the resulting damages have to be paid to the aggrieved party by the party breaching the contract.
In employment law, constructive dismissal occurs when an employee resigns due to the employer creating a hostile work environment. This often serves as a tactic for employers to avoid payment of statutory severance pay and benefits. In essence, although the employee resigns, the resignation is not truly voluntary but rather a response to intolerable working conditions imposed by the employer. These conditions can include unreasonable work demands, harassment, or significant changes to the employment terms without the employee’s consent.
In contract law, force majeure is a common clause in contracts which essentially frees both parties from liability or obligation when an extraordinary event or circumstance beyond the control of the parties, such as a war, strike, riot, crime, epidemic, or sudden legal change prevents one or both parties from fulfilling their obligations under the contract. Force majeure often includes events described as an act of God, though such events remain legally distinct from the clause itself. In practice, most force majeure clauses do not entirely excuse a party's non-performance but suspend it for the duration of the force majeure.
Quantum meruit is a Latin phrase meaning "what one has earned". In the context of contract law, it means something along the lines of "reasonable value of services".
An employment contract or contract of employment is a kind of contract used in labour law to attribute rights and responsibilities between parties to a bargain. The contract is between an "employee" and an "employer". It has arisen out of the old master-servant law, used before the 20th century. Employment contracts relies on the concept of authority, in which the employee agrees to accept the authority of the employer and in exchange, the employer agrees to pay the employee a stated wage.
Liquidated damages, also referred to as liquidated and ascertained damages (LADs), are damages whose amount the parties designate during the formation of a contract for the injured party to collect as compensation upon a specific breach. This is most applicable where the damages are intangible.
Fundamental breach of contract, is a controversial concept within the common law of contract. The doctrine was, in particular, nurtured by Lord Denning, Master of the Rolls from 1962 to 1982, but it did not find favour with the House of Lords.
Penal damages are liquidated damages which exceed reasonable compensatory damages, making them invalid under common law. While liquidated damage clauses set a pre-agreed value on the expected loss to one party if the other party were to breach the contract, penal damages go further and seek to penalise the breaching party beyond the reasonable losses from the breach. Many clauses which are found to be penal are expressed as liquidated damages clauses but have been seen by courts as excessive and thus invalid.
The law of contract in Australia is similar to the contract law of other Anglo-American common law jurisdictions, but differences from other jurisdictions have arisen over time because of statute law and divergent development of common law in the High Court, particularly since the 1980s.
At common law, substantial performance is an alternative principle to the perfect tender rule. It allows a court to imply a term that allows a partial or substantially similar performance to stand in for the performance specified in the contract.
In contract law, the implied covenant of good faith and fair dealing is a general presumption that the parties to a contract will deal with each other honestly, fairly, and in good faith, so as to not destroy the right of the other party or parties to receive the benefits of the contract. It is implied in a number of contract types in order to reinforce the express covenants or promises of the contract.
Canadian contract law is composed of two parallel systems: a common law framework outside Québec and a civil law framework within Québec. Outside Québec, Canadian contract law is derived from English contract law, though it has developed distinctly since Canadian Confederation in 1867. While Québecois contract law was originally derived from that which existed in France at the time of Québec's annexation into the British Empire, it was overhauled and codified first in the Civil Code of Lower Canada and later in the current Civil Code of Quebec, which codifies most elements of contract law as part of its provisions on the broader law of obligations. Individual common law provinces have codified certain contractual rules in a Sale of Goods Act, resembling equivalent statutes elsewhere in the Commonwealth. As most aspects of contract law in Canada are the subject of provincial jurisdiction under the Canadian Constitution, contract law may differ even between the country's common law provinces and territories. Conversely; as the law regarding bills of exchange and promissory notes, trade and commerce, maritime law, and banking among other related areas is governed by federal law under Section 91 of the Constitution Act, 1867; aspects of contract law pertaining to these topics are harmonised between Québec and the common law provinces.
English contract law is the body of law that regulates legally binding agreements in England and Wales. With its roots in the lex mercatoria and the activism of the judiciary during the Industrial Revolution, it shares a heritage with countries across the Commonwealth, from membership in the European Union, continuing membership in Unidroit, and to a lesser extent the United States. Any agreement that is enforceable in court is a contract. A contract is a voluntary obligation, contrasting to the duty to not violate others rights in tort or unjust enrichment. English law places a high value on ensuring people have truly consented to the deals that bind them in court, so long as they comply with statutory and human rights.
A contract is an agreement that specifies certain legally enforceable rights and obligations pertaining to two or more parties. A contract typically involves consent to transfer of goods, services, money, or promise to transfer any of those at a future date. The activities and intentions of the parties entering into a contract may be referred to as contracting. In the event of a breach of contract, the injured party may seek judicial remedies such as damages or equitable remedies such as specific performance or rescission. A binding agreement between actors in international law is known as a treaty.
In English law, implied terms are default rules for contracts on points where the terms which contracting parties expressly choose are silent, or mandatory rules which operate to override terms that the parties may have themselves chosen. The purpose of implied terms is often to supplement a contractual agreement in the interest of making the deal effective for the purpose of business, to achieve fairness between the parties or to relieve hardship.
South African contract law is "essentially a modernized version of the Roman-Dutch law of contract", and is rooted in canon and Roman laws. In the broadest definition, a contract is an agreement two or more parties enter into with the serious intention of creating a legal obligation. Contract law provides a legal framework within which persons can transact business and exchange resources, secure in the knowledge that the law will uphold their agreements and, if necessary, enforce them. The law of contract underpins private enterprise in South Africa and regulates it in the interest of fair dealing.
Australian Construction Contracts govern how the parties to a construction contract behave and how the project manager and the contract manager administer the relationship between the parties. There are several popular standard forms of construction contracts that are currently used in Australia.
Penalties in English law are contractual terms which are not enforceable in the courts because of their penal character. Since at least 1720 it has been accepted as a matter of English contract law that if a provision in a contract constitutes a penalty, then that provision is unenforceable by the parties. However, the test for what constitutes a penalty has evolved over time. The Supreme Court most recently restated the law in relation to contractual penalties in the co-joined appeals of Cavendish Square Holding BV v Talal El Makdessi, and ParkingEye Ltd v Beavis.
Cavendish Square Holding BV v Talal El Makdessi[2015] UKSC 67, together with its companion case ParkingEye Ltd v Beavis, are English contract law cases concerning the validity of penalty clauses and the application of the Unfair Terms in Consumer Contracts Directive. The UK Supreme Court ruled on both cases together on 4 November 2015, updating the established legal rule on penalty clauses and replacing the test of whether or not a disputed clause is "a genuine pre-estimate of loss" with a test asking whether it imposed a proportionate detriment in relation to any "legitimate interest" of the innocent party.