The Elbe Project (German : Elbe-Projekt) was the name of the first commercial, static high voltage direct current transmission system constructed in the world. The scheme was based on mercury arc valves.

Contents

Experimental installations between Wettingen and Zürich in Switzerland, and Charlottenburg and Moabit, Berlin, were demonstrated between 1933 and 1942. Contracts were signed with AEG and Siemens in 1941, and construction began of a bipolar direct current line from the Vockerode power station near Dessau on the Elbe, to Berlin-Marienfelde, in 1943. The line was designed to transmit 60 megawatts using a symmetrical bipolar operating voltage of +200 kV and 200 kV. Two single-core buried cables with aluminum conductors were used. A piece of the cable used can be seen in the Deutsches Museum, Munich.

The southern terminus was south of the Vockerode power plant. The hall built for this purpose (coordinates: 51°50'32"N 12°21'26"E) was later used as a workshop hall for the power plant and today houses some offices. The cable ran from Vockerode via Coswig, Straach, Boßdorf, Kropstädt, Treuenbrietzen, Beelitz, Michendorf, Saarmund and Großbeeren to the northern terminus in Berlin-Marienfelde. This was located in the area between the railway line from Berlin to Dresden, Beißlstrasse (until 1947 Wagemannstrasse), Friedrichsrodaer Strasse and Trachenbergring. The power converter hall built in this area (coordinates: 52°25'39"N 13°22'13"E) now serves as a sports hall. A 30 kV cable was laid from Berlin-Marienfelde to Steglitz substation (near Steglitz power plant), where the transmitted power should be fed into the power grid of Berlin.

A cable with an aluminum conductor with a cross section of 150 mm² and an outer diameter of 52 mm was used for each of the two high-voltage poles, while the earth was used as the neutral pole. For this purpose, there was close to both power converter stations a well equipped with a ground electrode. The exact location of these wells is no longer known.

The system was never put into service owing to the chaos in Germany at the end of World War II. The Soviets dismantled the system as part of war reparation payments, and reused it in building the 115 kilometre long 200 kV Moscow–Kashira monopolar high voltage direct current line with a maximum transmission rating of 30 megawatts in 1951. [1] This transmission line is no longer operating.

Sites

SiteCoordinates
Vockerode converter station (today workshop) 51°50′32″N12°21′26″E / 51.84222°N 12.35722°E / 51.84222; 12.35722 (Elbe-Project - Vockerode converter station (today workshop))
Berlin-Marienfelde converter station (today sports hall) 52°25′39″N13°22′13″E / 52.42750°N 13.37028°E / 52.42750; 13.37028 (Elbe-Project - Marienfelde converter station (today sports hall))

Related Research Articles

<span class="mw-page-title-main">High-voltage direct current</span> Electric power transmission system

A high-voltage direct current (HVDC) electric power transmission system uses direct current (DC) for electric power transmission, in contrast with the more common alternating current (AC) transmission systems.

<span class="mw-page-title-main">Kontek</span> HVDC connector between Germany and Denmark

The Kontek HVDC is a 170-kilometre (110 mi) long, monopolar 400 kV high-voltage direct current cable between Germany and the Danish island Zealand. Its name comes from "continent" and the name of the former Danish power transmission company "Elkraft", which operated the power grid on the Danish islands Lolland, Falster and Zealand and had the abbreviation "ek". As of today, the cable is operated by Energinet.dk in Denmark and 50Hertz Transmission GmbH in Germany.

<span class="mw-page-title-main">Baltic Cable</span>

The Baltic Cable is a monopolar HVDC power line running beneath the Baltic Sea that interconnects the electric power grids of Germany and Sweden. Its maximum transmission power is 600 megawatts (MW).

The HVDC Inter-Island link is a 610 km (380 mi) long, 1200 MW high-voltage direct current (HVDC) transmission system connecting the electricity networks of the North Island and South Island of New Zealand together. It is commonly referred to as the Cook Strait cable in the media and in press releases, although the link is much longer than its Cook Strait section. The link is owned and operated by state-owned transmission company Transpower New Zealand.

<span class="mw-page-title-main">Pacific DC Intertie</span> HVDC power line in the United States

The Pacific DC Intertie is an electric power transmission line that transmits electricity from the Pacific Northwest to the Los Angeles area using high voltage direct current (HVDC). The line capacity is 3.1 gigawatts, which is enough to serve two to three million Los Angeles households and represents almost half of the Los Angeles Department of Water and Power (LADWP) electrical system's peak capacity.

<span class="mw-page-title-main">Nelson River DC Transmission System</span> Electric power transmission system

The Nelson River DC Transmission System, also known as the Manitoba Bipole, is an electric power transmission system of three high voltage, direct current lines in Manitoba, Canada, operated by Manitoba Hydro as part of the Nelson River Hydroelectric Project. It is now recorded on the list of IEEE Milestones in electrical engineering. Several records have been broken by successive phases of the project, including the largest mercury-arc valves, the highest DC transmission voltage and the first use of water-cooled thyristor valves in HVDC.

HVDC Kingsnorth was a high-voltage direct-current (HVDC) transmission system connecting Kingsnorth in Kent to two sites in London. It was at one time the only application of the technology of high voltage direct current transmission for the supply of transformer stations in a city, and the first HVDC link to be embedded within an AC system, rather than interconnecting two asynchronous systems. It was also the first HVDC scheme to be equipped with self-tuning harmonic filters and to be controlled with a "Phase Locked Oscillator", a principle which subsequently became standard on all HVDC systems.

<span class="mw-page-title-main">Inga–Shaba HVDC</span> Electric power transmission line

The Inga–Shaba EHVDC Intertie is a 1,700 kilometres (1,100 mi)-long high-voltage direct current overhead electric power transmission line in the Democratic Republic of Congo, linking the Inga hydroelectric complex at the mouth of the Congo River to mineral fields in Shaba (Katanga). It was primarily constructed by Morrison-Knudsen International, an American engineering company, with the converter equipment supplied by ASEA. Construction was completed in 1982 and it cost US$900 million. The scheme was, for many years, the longest HVDC line in the world.

<span class="mw-page-title-main">HVDC converter station</span> Type of substation

An HVDC converter station is a specialised type of substation which forms the terminal equipment for a high-voltage direct current (HVDC) transmission line. It converts direct current to alternating current or the reverse. In addition to the converter, the station usually contains:

<span class="mw-page-title-main">Path 27</span> Electrical transmission line in Southwestern United States

Path 27, also called the Intermountain or the Southern Transmission System (STS), is a high-voltage direct current (HVDC) electrical transmission line running from the coal-fired Intermountain Power Plant near Delta, Utah, to the Adelanto Converter Station at Adelanto, California, in the Southwestern United States. It was installed by Asea, a company based in Sweden, and commercialized in July 1986. The system is designed to carry power generated at the power plant in Utah to areas throughout Southern California. It is owned and operated by the Intermountain Power Agency, a cooperative consisting of six Los Angeles-area cities, the largest member being the Los Angeles Department of Water and Power (LADWP), and 29 smaller Utah municipalities.

Square Butte is the designation of a high-voltage direct current transmission line in the United States between the Milton R. Young Power Plant near Center, North Dakota at 47°4′18″N101°11′45″W and the Arrowhead converter station near Adolph at 46°46′25″N92°17′39″W. It was built by Minnkota Power Cooperative and Minnesota Power and went in service in 1977. In 2009, an agreement was executed between the two companies whereby Minnkota gets the rights to all the power currently transmitted over the line while Minnesota Power takes full ownership of the line to transmit power from new sources in the Center area.

HVDC Leyte–Luzon is a high-voltage direct current transmission link in the Philippines between geothermal power plants on the islands of Leyte and Luzon.

The HVDC Sileru–Barsoor is a high voltage direct current transmission system between Sileru and Barsoor in India. It is in service since 1989 as the first HVDC line in the country. The HVDC Sileru–Barsoor is a bipolar HVDC with a voltage of 200 kV and a transmission rate of 400 megawatts. The HVDC Sileru–Barsoor couples two asynchronously operated parts of Indian electricity mains over a 196 kilometres (122 mi) long overhead line, which was originally a double-circuit 220 kV AC line from which three conductors are paralleled.

The HVDC Rihand–Delhi is a HVDC connection between Rihand and Dadri in India, put into service in 1990. It connects the 3,000 MW coal-based Rihand Thermal Power Station in Uttar Pradesh to the northern region of India. The project has an 814 kilometres (506 mi) long bipolar overhead line. The transmission voltage is 500 kV and the maximum transmission power is 1,500 megawatts. The project was built by ABB.

NorNed is a 580-kilometre (360 mi) long high-voltage direct current submarine power cable between Feda, Norway and the seaport of Eemshaven in the Netherlands, which interconnects both countries' electrical grids. It was once the longest submarine power cable in the world. Budgeted at €550 million, and completed at a cost of €600m, the NorNed cable is a bipolar HVDC link with a voltage of ±450 kV and a capacity of 700 MW. NorNed is a joint project of the Norwegian transmission system operator Statnett and its Dutch counterpart TenneT. The cable system itself and the two converter stations were produced by ABB.

Murraylink is an Australian high voltage direct current electricity transmission link between Berri in South Australia and Red Cliffs in Victoria, connecting the two state electricity grids. Murraylink was commissioned in 2002 and is believed to be the world's longest underground transmission system and cost more than A$177 million. It was built by TransEnergie Australia, a subsidiary of Hydro-Québec. It was sold to the Australian Pipeline Trust in March 2006 for A$153 million. In December 2008 ownership of Murraylink was transferred to the newly formed Energy Infrastructure Investments Group, while APA continued as the operator. The ownership of EII is APA with 19.9%, with the balance with Japan-based Marubeni Corporation with 49.9% and Osaka Gas with 30.2%.

<span class="mw-page-title-main">Submarine power cable</span> Transoceanic electric power line placed on the seabed

A submarine power cable is a transmission cable for carrying electric power below the surface of the water. These are called "submarine" because they usually carry electric power beneath salt water but it is also possible to use submarine power cables beneath fresh water. Examples of the latter exist that connect the mainland with large islands in the St. Lawrence River.

<span class="mw-page-title-main">HVDC BorWin1</span>

HVDC BorWin1 is the first HVDC facility in the world to be built for importing power from an offshore wind park to shore, and the first to use voltage source converters (VSC) in Germany. It connects the offshore wind park BARD Offshore 1 and other offshore wind farms in Germany near Borkum to the European power grid. The facility was built by ABB and has a capacity of 400 MW at a bipolar voltage of ±150 kV. HVDC BorWin1, which leads from BorWin Alpha Offshore Platform to Diele substation, consists of a 75 kilometres (47 mi) of underground and 125 kilometres (78 mi) of submarine cable.

The HVDC Hokkaidō–Honshū or Hokkaidō–Honshū HVDC Link, Kitahon HVDC Link for short, is a 193-kilometre-long (120 mi) high voltage direct current transmission line for the interconnection of the power grids of Hokkaidō and Honshū, Japan. The project went into service in 1979 by the Electric Power Development Company (J-POWER). A 149-kilometre-long (93 mi) overhead line and a 44-kilometre-long (27 mi) submarine cable connect the terminals. The HVDC Hokkaidō–Honshū is a monopolar HVDC line with an operating voltage of 250 kV and rated power of 300 megawatts. This HVDC system uses thyristor converters.

The Chandrapur–Padghe HVDC transmission system is an HVDC connection between Chandrapur and Padghe in the state of Maharashtra in India, which was put into service in 1999.

References

  1. Kimbark, E.W., Direct current transmission, volume 1, Wiley Interscience, 1971, pp 78.