Flexible Plug and Play

Last updated

[1]

Flexible Plug and Play is a research project looking at how to improve the connection of renewable energy generation, like wind farms, to electricity distribution networks in the UK. According to the original submission [2] to Ofgem, the electricity regulator, it will test new technical solutions to problems on the network and develop new commercial arrangements between the energy supplier and network operator.

Contents

Funding

The total cost of the project is £9.7 million. In 2011 Ofgem awarded £6.7 million to UK Power Networks from its Low Carbon Network Fund. UK Power Networks is contributing £2 million and the project partners a further £1 million.

Geographical area of research

According to the original bid submission a rural area of around 700km2 between Peterborough, March and Wisbech in Cambridgeshire has been chosen as the test bed for the Flexible Plug and Play project. There are said to be 9 operational wind farms in the area with a total installed capacity of 100MW; a further 10 renewable generation sites have won consent or are at the submission stage, with an additional 10 sites currently subject to scoping studies. This gives a total of a further 188MW of potential wind generation in the same area. However, the progress report of June 2012 says the potential has increased to 200MW. [3] Apparently connecting these extra wind farms to the existing distribution network would be difficult for a number of reasons including voltage constraints, thermal constraints and reverse power flows. It's said that using a traditional approach of network upgrading/reinforcement would be costly and time consuming. As a result the research project will try out new ways of managing the existing network to accommodate this extra power without reinforcing the network.

Smart devices

The Flexible Plug and Play project, according to the submission documents, will test a number of so called smart devices on a distribution network to improve its efficiency and to allow more power to flow through it without reinforcement. 1) Dynamic Line Rating device. The maximum current an overhead power line can carry is an ever changing value affected by the weather. However, in distribution networks the conventional approach is to operate lines with static or seasonal limits. In theory dynamic line rating allows constant monitoring of a line's capacity. Knowing the limits of a section of the network at any moment will help to operate the network at its peak. 2) Automatic Voltage Control. An AVC device monitors voltage levels and automatically adjusts them within pre set limits. In the Flexible Plug and Play project it is envisaged AVCs will be working as part of an Automatic Network Management system. 3) Modern Protection Relay. The existing network uses directional over-current (DOC) protection relays which cannot handle reverse power flows. It's said the modern protection relay will be designed to overcome this problem. It will be tested at the March and Peterborough sub stations. 4) Frequent Use Switches. The distribution network in the test area uses isolator switches at Normally Open Points (NOPs) however, they are not designed for frequent use and have to be reset manually. Frequent Use Switches would be controlled remotely, allowing different network configurations to be used. 5) Quadrature Booster transformer. Quad Boosters are common on transmission networks but not on distribution grids. According to the Flexible Plug and Play progress report dated June 2012 a Quad Booster could be fitted at the British Sugar factory site in Wissington. Apparently the Combined Heat & Power plant operated by British Sugar has seasonal limits on generation export due to the suboptimal loading of the three incoming 33kV circuits. The Quadrature Booster will be connected to one of the circuits to ensure load balancing and it will enable the export of additional generation from the CHP unit onto the electricity grid.

IEC 61850 Standard

IEC 61850 is a standard for the engineering process for the configuration of Intelligent Electronic Devices (IEDs), the structure and naming of their data models and a number of communication mechanisms to support the real time operation of automation systems. The Flexible Plug and Play project plans, it is said, to deploy it on the distribution network in the test area. Silver Spring Networks and Cable and Wireless Worldwide are quoted as being the developing partners.

Related Research Articles

Mains electricity Type of lower-voltage electricity most commonly provided by utilities

Mains electricity is the general-purpose alternating-current (AC) electric power supply. It is the form of electrical power that is delivered to homes and businesses, and it is the form of electrical power that consumers use when they plug items such as domestic appliances, televisions and electric lamps into wall outlets.

Power-line communication carries data on a conductor that is also used simultaneously for AC electric power transmission or electric power distribution to consumers. It is

Distributed generation, also distributed energy, on-site generation (OSG), or district/decentralized energy, is electrical generation and storage performed by a variety of small, grid-connected or distribution system-connected devices referred to as distributed energy resources (DER).

The Electricity Supply Board is a state owned electricity company operating in Ireland. While historically a monopoly, the ESB now operates as a commercial semi-state concern in a liberalised and competitive market. It is a statutory corporation whose members are appointed by the Government of Ireland.

Scottish Power British energy company

Scottish Power is a vertically integrated energy company based in Glasgow, Scotland. It is a subsidiary of Spanish utility firm Iberdrola.

National Grid (Great Britain) high-voltage electric power transmission network in Great Britain

In the electricity sector in the United Kingdom the National Grid is the high-voltage electric power transmission network serving Great Britain, connecting power stations and major substations and ensuring that electricity generated anywhere on it can be used to satisfy demand elsewhere. The network covers the great majority of Great Britain and several of the surrounding islands. It does not cover Ireland; Northern Ireland is part of a single electricity market with the Republic of Ireland.

The Renewables Obligation (RO) is designed to encourage generation of electricity from eligible renewable sources in the United Kingdom. It was introduced in England and Wales and in a different form in Scotland in April 2002 and in Northern Ireland in April 2005, replacing the Non-Fossil Fuel Obligation which operated from 1990.

Electricity meter Device that measures the amount of electric energy consumed by a residence or a business

An electricity meter, electric meter, electrical meter, or energy meter is a device that measures the amount of electric energy consumed by a residence, a business, or an electrically powered device.

Grid energy storage collection of methods used to energy storage on a large scale within an electrical power grid

Grid energy storage is a collection of methods used for energy storage on a large scale within an electrical power grid. Electrical energy is stored during times when electricity is plentiful and inexpensive or when demand is low, and later returned to the grid when demand is high, and electricity prices tend to be higher.

Quadrature booster specialised power transformer used to control the flow of real power on three-phase electricity transmission networks

A phase angle regulating transformer, phase angle regulator, phase-shifting transformer, phase shifter, or quadrature booster, is a specialised form of transformer used to control the flow of real power on three-phase electric transmission networks.

Electrical devices are considered grid friendly if they operate in a manner that supports electrical power grid reliability through demand response. Basic grid-friendly devices may incorporate features that work to offset short-term undesirable changes in line frequency or voltage; more sophisticated devices may alter their operating profile based on the current market price for electricity, reducing load when prices are at a peak. Grid-friendly devices can include major appliances found in homes, commercial building systems such as HVAC, and many industrial systems.

A fault current limiter (FCL), or fault current controller (FCC), is a device which limits the prospective fault current when a fault occurs without complete disconnection. The term includes superconducting, solid-state and inductive devices.

Electrical power system simulation involves power system modeling and network simulation in order to analyze electrical power systems using design/offline or real-time data. Power system simulation software's are a class of computer simulation programs that focus on the operation of electrical power systems. These types of computer programs are used in a wide range of planning and operational situations for:

  1. Electric power generation - Nuclear, Conventional, Renewable
  2. Commercial facilities
  3. Utility transmission
  4. Utility distribution
  5. Railway power systems
  6. Industrial power systems
Load management Process of balancing the supply of electricity on a network

Load management, also known as demand-side management (DSM), is the process of balancing the supply of electricity on the network with the electrical load by adjusting or controlling the load rather than the power station output. This can be achieved by direct intervention of the utility in real time, by the use of frequency sensitive relays triggering the circuit breakers, by time clocks, or by using special tariffs to influence consumer behavior. Load management allows utilities to reduce demand for electricity during peak usage times, which can, in turn, reduce costs by eliminating the need for peaking power plants. In addition, some peaking power plants can take more than an hour to bring on-line which makes load management even more critical should a plant go off-line unexpectedly for example. Load management can also help reduce harmful emissions, since peaking plants or backup generators are often dirtier and less efficient than base load power plants. New load-management technologies are constantly under development — both by private industry and public entities.

The electricity sector in New Zealand uses mainly renewable energy sources such as hydropower, geothermal power and increasingly wind energy. 82% of energy for electricity generation is from renewable sources, making New Zealand one of the lowest carbon dioxide emitting countries in terms of electricity generation. Electricity demand has grown by an average of 2.1% per year from 1974 to 2010 but decreased by 1.2% from 2010 to 2013.

UK Power Networks distribution network operator for electricity covering South East England

UK Power Networks is a distribution network operator for electricity covering South East England, the East of England and London. It manages three licensed distribution networks which together cover an area of 30000 square kilometres and approximately eight million customers.

Shetland HVDC Connection is a planned high-voltage direct current submarine power cable to connect the Shetland Islands to the Scottish mainland.

The electricity sector of Kosovo relies on coal-fired power plants (97%) and is considered one of the sectors with the greatest potential of development. The inherited issues after the war in Kosovo and the transition period have had an immense effect on the progress of this sector.

An interconnector is a structure which enables energy to flow between networks. The term is used more specifically to refer to international connections between electricity and natural gas networks. An electrical interconnector allows electricity to flow between separate interconnections, or synchronous grids. They can be formed of submarine power cables or underground power cables or overhead power lines. The longest interconnection as of 2016 was the undersea NorNed link between Norway and the Netherlands, spanning nearly 600 km and delivering 700 MW of high voltage direct current power.

Electricity sector in Armenia

The electricity sector of Armenia includes several companies engaged in electricity generation and distribution. Generation is carried out by multiple companies both state-owned and private.

References

  1. Flexible Plug and Play website. "Flexible Plug and Playaccessed 18 October 2012".Missing or empty |url= (help)
  2. UK Power Networks (27 November 2011). "Flexible Plug and Play".
  3. UK Power Networks (June 2012). "Flexible Plug and Play progress report".