Country | Scotland, United Kingdom |
---|---|
City | Flotta, Orkney |
Coordinates | 58° 20’ 22” N 03° 06’ 24” W |
Refinery details | |
Operator | Occidental (1974–1991), Elf Enterprises (1991–2000), Repsol Sinopec Resources UK Limited (since 2000) |
Owner(s) | Occidental (1974–1991), Elf Enterprises (1991–2000), Repsol Sinopec Resources UK Limited (since 2000) |
Commissioned | 1976 |
Capacity | 375,000 barrels/day (2017) |
No. of employees | 275 (in 1987), 200 (in 1995) |
The Flotta oil terminal is a major crude oil reception, processing, storage and export facility on the island of Flotta, in the south of Scapa Flow in the Orkney Islands. It receives and processes crude oil delivered by a subsea pipeline from the Piper, Claymore, Tartan and Golden Eagle platforms and associated fields. The terminal includes facilities for exporting stabilised crude oil (and formerly liquefied petroleum gases) by tanker.
The Piper oil field was discovered by the Occidental Group in January 1973 and the adjacent Claymore field in May 1974. [1] Occidental considered a number of options for exporting oil from the planned installations, these included offshore loading and pipelines to shore. Nine potential onshore sites for the pipeline terminal were considered. [1] The island of Flotta was selected as it met operational needs and minimised the impact on the natural environment.
The Planning Authority gave planning consent in January 1974 for phase 1 of the development for the Piper field. [1] The terminal (coordinates 58° 20’ 22” N 03° 06’ 24” W) received ‘live’ crude oil from Piper Alpha via a 125-mile (210 km) 30-inch diameter trunk pipeline. The facilities at Flotta included a plant for stabilising crude oil at up to 250,000 barrels/day; storage tanks; and stabilised crude and liquefied petroleum gases (LPG) ship loading facilities.
Phase 2, to accommodate the processing of oil from the Claymore field, was granted in summer 1976 and entailed additional plant and tanks. The cost of the Flotta terminal was about $240 million (1978 prices). [1] The total cost of the terminal and associated pipelines was estimated in 1984 to be $650 million (1984 prices). [2]
Phase 1 of the development of the Flotta terminal included: [1]
The engineering, procurement and construction was undertaken by Bechtel International Limited. Turiff Taylor Tarmac was the general construction contractor. Motherwell Bridge Engineering was responsible for the crude oil storage tanks, LPG tanks, desalter tanks, flare system and firewater system. NATCO was responsible for design of the process equipment. [1]
Phase 1 of the Flotta terminal was complete by Christmas 1976 and oil processing operations started.
Permission was granted to extend the plant (phase 2) in summer 1976 to accommodate the additional flow of crude oil exported from Claymore via the Piper to Flotta pipeline. Phase 2 included: [1]
The engineering procurement and construction was undertaken by Occidental Engineering Company. Motherwell Bridge Engineering constructed the tanks. Phase 2 was completed by late 1977. By summer 1978 the landscaping of the terminal was complete. [1]
The Flotta oil pipeline system comprises the following lines. [3] [2] [4]
From – To | Length, miles | Diameter, inches | Year commissioned |
---|---|---|---|
Piper A – Flotta | 130 | 30 | 1976 |
Claymore – Claymore TEE on Piper to Flotta trunkline | 8 | 30 | 1977 |
Tartan – Claymore | 17 | 24 | 1980 |
Scapa – Claymore | 3 | 10 | 1985 |
Petronella – Tartan | 6 | 8 | 1986 |
Highlander – Tartan | 9 | 12 | 1985 |
Rob Roy & Ivanhoe – Claymore | 25 | 14 | 1989 |
Hamish – Rob Roy | 1990 | ||
Chanter – Piper B | 7 | 6 | 1993 |
Piper B – Claymore tie in | 20 | 30 | 1993 |
Saltire – Piper B | 4 | 10 | 1993 |
Iona – Saltire | 1997 | ||
MacCulloch (Northern Producer) – Piper B | 22 | 10 | 1997 |
Galley – Tartan | 9 | 10 | 1998/2007 |
Tweedsmuir – Piper B | 34 | 6 | 2007 |
Duart – Tartan | 5 | 8 | 2007 |
Golden Eagle – Claymore | 49 | 14 | 2014 |
The oil entry specification to the Piper to Flotta pipeline and hence to the Flotta terminal is as shown in the table. [5]
Parameter | Value |
---|---|
°API gravity | 30 to 40 |
Water | 2 % volume |
Base sediment | 0.05 % vol. |
Viscosity @ 25 °C | 10 cP |
Pour point | –3 °C |
Wax content | 6 % weight |
True Vapor Pressure @ 100 °F | 120 psia |
Total sulphur | 1 % wt. |
H2S | 1 ppm wt. |
CO2 | 0.25 % mol |
Total acid number | 0.05 mgKOH/g |
Nickel | 4 ppm wt. |
Vanadium | 8 ppm wt. |
Mercury | 0.35 ppb wt. |
Live crude oil from the Piper to Flotta pipeline is routed to one or more of the four 125,000 barrels/day stabiliser trains. [1] The trains include two stages of desalting to remove salt and water from the oil. Oil is heated and enters the stabiliser towers where the lighter fractions boil off. Stabilised crude from the base of the stabilisers is routed to the crude oil storage tanks.
The light ends from the top of the stabiliser are compressed and flow to the de-methaniser. The methane and ethane are removed from the top of the vessel and used as fuel gas with the surplus burned in the flare. [1] The flaring rate in 1993 was 40,000 m3/day or 1,460,000 cubic feet/day. [3] Heavy ends from the base of the de-methaniser were routed to the de-ethaniser and then the de-propaniser. Propane from the top of the de-propaniser was chilled and liquefied and stored at –40 °C in two 100,000 barrel capacity insulated tanks. Butane and any heavier ends from the bottom of the de-propaniser are comingled with the stabilised crude. [1]
Stabilised crude typically had the following properties. [5]
Parameter | Value |
---|---|
Density at 15 °C | 0.8412 kg/m3 |
API gravity | 36.64°API |
Total sulphur | 0.66 % weight |
Total salts | 2.4 lb NaCl/1000 bbl |
Water content | 0.03 % weight |
Reid Vapor Pressure | 9.61 psi |
Stabilised crude oil from the storage tanks was routed via 48-inch diameter lines to either of the single point moorings (SPM) in Scapa Flow or to the jetty. LPG was loaded to the jetty. [1] [6]
The SPM loading rate was 50,000 BPH. The jetty had an oil loading rate of 80,000 BPH. [5]
Ballast water from tankers was pumped to a 500,000 barrel storage tank. It was treated in a floatation unit before discharge via a 1.5 mile 36-inch diameter pipeline into the turbulent waters of the Pentland Firth to aid dispersal. [1]
The total oil throughput of the terminal up to the end of 1997 was 258,529 thousand tonnes. [7]
Peak production was 421,590 barrels/day on 4 November 1978. [8]
The initial Occidental Group comprised: Occidental of Britain Incorporated, Allied Chemicals (Great Britain) Limited, Thomson North Sea Limited, and Getty Oil Britain Limited. [1]
In 1984 the Occidental Consortium comprised Occidental Petroleum (Caledonia) Limited, 36.50%; Texaco Britain Limited, 23.50%; International Thomson plc, 20.00%; Union Texas Petroleum Limited, 20.00%. [2]
Following the Piper Alpha disaster in July 1988 Elf Enterprises Caledonia Limited and its partners assumed ownership of the pipeline and the Flotta terminal. [3]
Repsol Sinopec Resources UK Limited became the major shareholder and operator in May 2000. [5]
Following commissioning of Piper Alpha in December 1976 the following developments took place.
By 31 December 1984 883 million barrels of oil had been processed at Flotta and 1,554 tankers had been loaded. [2]
The following fields producing to the Flotta system were developed in the mid-1980s. [2]
Field | Installation | Production to | Oil production rate, million tonnes /year | Year commissioned |
---|---|---|---|---|
Highlander | Subsea | Tartan | 1.4 | 1985 |
Scapa | Subsea | Claymore | 1.4 + 0.01 NGL | 1985 |
Petronella | Subsea | Tartan | 0.6 | 1986 |
The Piper Alpha disaster occurred on 6 July 1988. [9] Production from, and via, Piper ceased.
The following fields, producing to the Flotta system, were developed from 1989. [3] [2] [8]
Field | Installation | Production to | Oil production rate, million tonnes /year | Year commissioned |
---|---|---|---|---|
Rob Roy | Subsea | Claymore | 1.7 | 1989, decommissioned [10] |
Ivanhoe | Subsea | Claymore | 1.3 | 1989, decommissioned [10] |
Hamish | Subsea | Rob Roy | 0.1 | 1990, decommissioned [10] |
Piper Bravo | Platform | Flotta via Claymore tie in | 4.5 | 1993 |
Chanter | Subsea | Piper B | 0.2 + 0.2 condensate | 1993 |
Saltire | Platform | Piper B | 2.3 + 0.10 NGLs | 1993 |
Iona | Subsea | Saltire | 0.05 + 0.006 NGLs | 1997 |
MacCulloch | Semi-submersible (Northern Producer) /Subsea | Piper B | 2.9 | 1997, decommissioned [11] |
Galley | Semi-submersible (AH001) / Subsea | Tartan | 35,000 bbl/d | 1998 & 2007 |
Tweedsmuir | Subsea | Piper B | 2007 | |
Duart | Subsea | Tartan | 6,000 bbl/d | 2007 |
Golden Eagle | Platform | Claymore | 70,000 bbl/d | 2014 |
The Golden Eagle development effectively doubled the production through Flotta terminal. [8]
By 2017, 40 years after being commissioned, 2.6 billion barrels of oil had been processed through the Flotta terminal. [8]
By 2017 one of the stabiliser trains had been decommissioned. The three remaining trains had a combined capacity of 375,000 barrels/day. [2]
By 2017 there were insufficient volumes of gas to make the operation of the gas plant economically viable. There was a proposal to decommission the system. Gas from the stabilisers was used to generate electricity and as fuel gas in the hot oil heaters. [2]
The Single Point Moorings have been mothballed and are not operational. [2] [6]
As currently operated (2020) the terminal only exports stabilised crude oil through tankers loaded at the jetty. In 2016 50 tankers visited the terminal. [8]
Flotta is a small island in Orkney, Scotland, lying in Scapa Flow. The island is known for its large oil terminal and is linked by Orkney Ferries to Houton on the Orkney Mainland, Lyness on Hoy and Longhope on South Walls. The island has a population of 80.
Singapore Petroleum Company Limited, in short SPC, is a Singaporean multinational oil and gas company. It is involved in the exploration and production of petroleum, refining, trading and petroleum product distribution.
The Piper oilfield is a substantial North Sea oilfield covering 30.1 km2. It lies roughly halfway between Aberdeen and Bergen, at the eastern end of the Moray Firth basin. Oil extracted from it is piped to Scotland, where it is stabilised at an oil plant on the island of Flotta, in the Orkney archipelago, while gas is shipped via the Frigg gas pipeline. In June 1975, the Piper Alpha oil platform was placed over the field in 144 metres of water, secured in place by 24 piles extending 116 metres beneath the seabed. The platform was designed for simultaneous drilling and production. Piper Alpha was the site of one of the world's worst oil platform disasters when it was destroyed by an explosion in 1988, with the loss of 167 lives. Piper Bravo was installed in 1992. Talisman Energy acquired a controlling interest in 2000.
The Eilat Ashkelon Pipeline Company operates several crude petroleum and refined petroleum products pipelines in Israel, most notably the Eilat Ashkelon Pipeline – which transports crude oil across southern Israel, between the Red Sea and the Mediterranean Sea. The EAPC also operates two maritime oil terminals as well as oil storage depots in the country.
An oil terminal is an industrial facility for the storage of oil, petroleum and petrochemical products, and from which these products are transported to end users or other storage facilities. An oil terminal typically has a variety of above or below ground tankage; facilities for inter-tank transfer; pumping facilities; loading gantries for filling road tankers or barges; ship loading/unloading equipment at marine terminals; and pipeline connections.
Foinaven oilfield is a deep-water oil development approximately 190 kilometres (120 mi) west of the Shetland Islands. Together with Schiehallion, Loyal, Solan, Clair and Lancaster fields it forms the area generally termed as the West of Shetland.
An oil production plant is a facility which processes production fluids from oil wells in order to separate out key components and prepare them for export. Typical oil well production fluids are a mixture of oil, gas and produced water. An oil production plant is distinct from an oil depot, which does not have processing facilities.
Onshore, when used in relation to hydrocarbons, refers to an oil, natural gas or condensate field that is under the land or to activities or operations carried out in relation to such a field.
Fawley Refinery is an oil refinery located at Fawley, Hampshire, England. The refinery is owned by Esso Petroleum Company Limited, a subsidiary of Exxon Mobil Corporation, which acquired the site in 1925. Situated on Southampton Water, it was rebuilt and extended in 1951 and is now the largest oil refinery in the United Kingdom, and one of the most complex refineries in Europe. With a capacity of 270,000 barrels (43,000 m3) per day, Fawley provides 20 per cent of the UK's refinery capacity. Over 2,500 people are employed at the site.
Grangemouth Refinery is an oil refinery complex located on the Firth of Forth in Grangemouth, Scotland, currently operated by Petroineos.
The BPRefinery (Kent) was an oil refinery on the Isle of Grain in Kent. It was commissioned in 1953 and had a maximum processing capacity of 11 million tonnes of crude oil per year. It was decommissioned in August 1982.
Sture Terminal is an oil terminal at Stura in Øygarden municipality, 50 km (31 mi) northwest of Bergen, Norway. It receives oil and condensate from Oseberg, Veslefrikk, Brage, Oseberg Sør, Oseberg Øst, Tune and Huldra fields through 115 km (71 mi) Oseberg Transport System (OTS) and oil from Grane oil field through 212 km (132 mi) Grane oil pipeline.
Eastham Oil Terminal is situated close to the small town of Eastham on the Wirral Peninsula, beside the Manchester Ship Canal. It was commissioned in 1954 close to the Queen Elizabeth II Dock and is a storage and export facility for oil products refined at Stanlow Refinery, to which it is connected by pipeline. The site is currently operated by Nynas.
Canaport is a Canadian marine crude oil receiving terminal located on the north shore of the Bay of Fundy at Mispec Point, approximately 9 km (5.6 mi) southeast of the city of Saint John, New Brunswick.
The Claymore oil field is located in Block 14/19 on the United Kingdom's Continental Shelf. It is 161 km (100 mi) northeast of Aberdeen in the Central North Sea. The field is named after a double-edged broadsword used by Highland Scots. Recoverable oil reserves were estimated to be 511 million barrels from an initial oil in place of 1452.9 million barrels. The field was developed through a large steel jacket platform standing in 110 m of water. A separate accommodation platform was installed in 1995. Fluid production was supported by gas lift and significant water injection. The production platform also supports production from the Scapa field, the Golden Eagle field and the Tartan field. Oil is exported to the Flotta terminal.
Oil terminals are key facilities for the import, export, storage, blending, transfer and distribution of oil and petroleum products. Many terminals are located at coastal sites, such as Teesside and the lower Thames, to allow the offloading and loading of coastal shipping. Inland terminals, located around major cities, such as Birmingham and Manchester, facilitate the distribution of products to local industrial and commercial users. Many terminals have road tanker loading equipment for local distribution of products such as petrol, diesel, and heating oil. The terminals are connected through a network of underground pipelines to enable the transfer of oil and refined products across Britain.
Crude oil stabilisation is a partial distillation process that renders crude oil suitable for storage in atmospheric tanks, or of a quality suitable for sales or pipeline transportation. Stabilization is achieved by subjecting ‘live’ crude to temperature and pressure conditions in a fractionation vessel, which drives off light hydrocarbon components to form a ‘dead’ or stabilized crude oil with a lower vapor pressure.
The Teesside oil terminal is a major crude oil reception, processing, storage and export facility at Seal Sands, Middlesbrough. It receives and processes crude oil delivered by the subsea NORPIPE pipeline from the Norwegian Ekofisk field and the UK Fulmar and J-Block fields. The terminal includes facilities for exporting stabilised crude oil and liquefied petroleum gases (LPG) by tanker and pipeline.
The Montrose oil field is a significant crude oil producing field in the UK sector of the central North Sea, 210 km east of Aberdeen. Production of oil started in 1976 and a major upgrade in 2016 extended the field life to beyond 2030.
The Tartan oil field is a significant crude oil producing field in the UK sector of the North Sea, 187 km north-east of Aberdeen. Production of oil started in 1981 and ceased in 2020, the Tartan Alpha installation is currently (2021) undergoing decommissioning.