HVDC DolWin3

Last updated

HVDC DolWin3 is a high voltage direct current (HVDC) link to transmit Offshore wind power to the power grid of the German mainland. The project differs from most HVDC systems in that one of the two converter stations is built on a platform in the sea. Voltage-Sourced Converters with DC ratings of 900 MW, ±320 kV are used and the total cable length is 160 km.

Contents

The overall project is being built by Alstom with the cables supplied by Prysmian and offshore platform by Nordic Yards. Construction commenced on the onshore converter station at Dörpen West in May 2014 [1] and on the offshore platform in October 2014. [2] [3] As of summer 2015 the platform was being fitted out and the first converter transformer was installed on 17 July 2015. [4] The project was handed over to its owner, TenneT, in 2017. The grid connection is in operation since September 2018. [5] A fund managed by Copenhagen Infrastructure Partners has invested in this offshore transmission platform. [6]

See also

Related Research Articles

<span class="mw-page-title-main">High-voltage direct current</span> Electric power transmission system

A high-voltage direct current (HVDC) electric power transmission system uses direct current (DC) for electric power transmission, in contrast with the more common alternating current (AC) transmission systems.

<span class="mw-page-title-main">HVDC Cross-Channel</span>

The HVDC Cross-Channel is the 73-kilometre-long (45 mi) high-voltage direct current (HVDC) interconnector that has operated since 1986 under the English Channel between the continental European grid at Bonningues-lès-Calais and the British electricity grid at Sellindge. The cable is also known as IFA, and should not be confused with the new IFA-2, another interconnect with France that is three times as long but only half as powerful.

NorNed is a 580-kilometre (360 mi) long high-voltage direct current submarine power cable between Feda in Norway and the seaport of Eemshaven in the Netherlands, which interconnects both countries' electrical grids. It was once the longest submarine power cable in the world. Budgeted at €550 million, and completed at a cost of €600m, the NorNed cable is a bipolar HVDC link with a voltage of ±450 kV and a capacity of 700 MW. NorNed is a joint project of the Norwegian transmission system operator Statnett and its Dutch counterpart TenneT. The cable system itself and the two converter stations were produced by ABB.

<span class="mw-page-title-main">Submarine power cable</span> Transoceanic electric power line placed on the seabed

A submarine power cable is a transmission cable for carrying electric power below the surface of the water. These are called "submarine" because they usually carry electric power beneath salt water but it is also possible to use submarine power cables beneath fresh water. Examples of the latter exist that connect the mainland with large islands in the St. Lawrence River.

TenneT is a transmission system operator in the Netherlands and in a large part of Germany.

<span class="mw-page-title-main">HVDC BorWin1</span>

HVDC BorWin1 is the first HVDC facility in the world to be built for importing power from an offshore wind park to shore, and the first to use voltage source converters (VSC) in Germany. It connects the offshore wind park BARD Offshore 1 and other offshore wind farms in Germany near Borkum to the European power grid. The facility was built by ABB and has a capacity of 400 MW at a bipolar voltage of ±150 kV. HVDC BorWin1, which leads from BorWin Alpha Offshore Platform to Diele substation, consists of a 75 kilometres (47 mi) of underground and 125 kilometres (78 mi) of submarine cable.

BritNed is a 1,000 MW high-voltage direct-current (HVDC) submarine power cable between the Isle of Grain in Kent, the United Kingdom; and Maasvlakte in Rotterdam, the Netherlands.

<span class="mw-page-title-main">North Sea Link</span> Subsea electricity transmission line

The North Sea Link is a 1,400 MW high-voltage direct current submarine power cable between Norway and the United Kingdom.

HVDC DolWin1 is a high voltage direct current link built to transmit offshore wind power to the power grid of the German mainland. The project differs from most HVDC systems in that one of the two converter stations is built on a platform in the sea. Voltage-Sourced Converters are used and the total cable length is 165 km. The project was built by ABB and was handed over to its owner, TenneT, in July 2015, the fifth such project to be completed in Germany in 2015.

<span class="mw-page-title-main">HVDC HelWin1</span>

HVDC HelWin1 is a high voltage direct current (HVDC) link built to transmit Offshore wind power to the power grid of the German mainland. The project differs from most HVDC systems in that one of the two converter stations is built on a platform in the sea. Voltage-Sourced Converters are used and the total cable length is 130 km. The project was completed and handed over to its owner, TenneT, in February 2015.

<span class="mw-page-title-main">HVDC BorWin2</span>

HVDC BorWin2 is a high voltage direct current (HVDC) link built to transmit offshore wind power to the power grid of the German mainland. The project differs from most HVDC systems in that one of the two converter stations is built on a platform in the sea. Voltage-Sourced Converters are used and the total cable length is 200 km. The project was completed by the Siemens/ Prysmian consortium and handed over to its owner, TenneT, in January 2015, becoming the first such project to be completed.

<span class="mw-page-title-main">HVDC HelWin2</span> Offshore HVDC connection in Germany

HVDC HelWin2 is a high voltage direct current (HVDC) link built to transmit offshore wind power to the power grid of the German mainland. The project differs from most HVDC systems in that one of the two converter stations is built on a platform in the sea. Voltage-Sourced Converters with DC ratings of 690 MW, ±320 kV are used and the total cable length is 130 km. The project was built by the Siemens/Prysmian consortium with the offshore platform built by Heerema in Zwijndrecht, Netherlands. The topside measures 98 m x 42 m x 28 m and weighs 10200 tonnes. The project was handed over to its owner, TenneT, in June 2015, the fourth such project to be completed in 2015.

HVDC SylWin1 is a high voltage direct current (HVDC) link under construction to transmit offshore wind power to the power grid of the German mainland. The project differs from most HVDC systems in that one of the two converter stations is built on a platform in the sea. Voltage-Sourced Converters with DC ratings of 864 MW, ±320 kV are used and the total cable length is 205 km. The project is similar to the HVDC BorWin2 project but has slightly higher power and voltage ratings. It is being built by the Siemens/ Prysmian consortium and was handed over to its owner, TenneT, in April 2015.

<span class="mw-page-title-main">HVDC DolWin2</span>

HVDC DolWin2 is a high voltage direct current (HVDC) link to transmit offshore wind power to the power grid of the German mainland. The project differs from most HVDC systems in that one of the two converter stations is built on a platform in the sea. Voltage-Sourced Converters with DC ratings of 900 MW, ±320 kV are used and the total cable length is 135 km. The project is similar to the HVDC DolWin1 project but has a slightly higher power rating and uses a different design of offshore platform. The platform was designed by Norwegian company Aibel and built by Drydocks World in Dubai and transported to Europe in the summer of 2014 to be fitted out at the Aibel yard in Haugesund in Norway. The platform, which is of a floating, self-installing design not previously used in an HVDC project, sailed out from Haugesund on 1 August 2015 and was installed in the North Sea ten days later.

HVDC BorWin3 is a high voltage direct current (HVDC) link under construction to transmit offshore wind power to the power grid of the German mainland. The project differs from most HVDC systems in that one of the two converter stations is built on a platform in the sea. Voltage-Sourced Converters with DC ratings of 900 MW, ±320 kV are used and the total cable length is 160 km. The project is the most recent of the German offshore HVDC projects to be awarded. It is being built by the Siemens/ Petrofac consortium with the offshore platform contract awarded to Drydocks World in Dubai. The project is expected to be handed over to its owner, TenneT, in 2019. The project started power transmission in August 2019. TenneT took control of operations in February 2020.

The Jindo–Jeju HVDC system is a 105 km HVDC submarine cable connection in South Korea between the island of Jindo, close to the Korean Peninsula, and the more distant island of Jeju. The system has a capacity of 400 MW and transmission voltage of ±250 kV and was put into service in 2014. It is the second HVDC link to Jeju Island, after the Haenam–Cheju link completed in the late 1990s.

Kriegers Flak is a 605 MW offshore wind farm in the Baltic Sea on the Danish part of the reef of the same name. It forms part of a new 400 MW interconnector between Denmark and Germany.

<span class="mw-page-title-main">Veja Mate Offshore Wind Farm</span>

Veja Mate is a German 402 MW offshore wind farm in the German Bight of the North Sea about 95 km northwest of Borkum. The wind farm consists of 67 Siemens Wind Power SWT-6.0-154 turbines, each with a 6 MW capacity.

Hitachi Energy Ltd is a global technology company headquartered in Zurich, Switzerland. The company provides sustainable energy solutions to buildings, utilities, industries, and infrastructure sectors. The company’s portfolio includes high-voltage equipment, transformers, grid integration and grid automation technologies, and services for renewable energy sectors.

References

  1. Construction begins on offshore grid connection DolWin3 Sun & Wind Energy, 27 May 2014.
  2. Yards Starts Building DolWin Gamma, Offshore Wind.biz, 9 October 2014.
  3. Nordic Yards Holds DolWin Gamma Dock Laying Ceremony, Offshore Wind.biz, 2 February 2015.
  4. Alstom and TenneT to reach another important milestone in the offshore DolWin3 project, Alstom Press Release, 17 July 2015.
  5. "DolWin3 - TenneT". www.tennet.eu. Retrieved 2021-05-11.
  6. "Artemis I, Germany - Copenhagen Infrastructure Partners" . Retrieved 2021-05-11.