Hochster v De La Tour | |
---|---|
Court | Queen's Bench |
Decided | 25 June 1853 |
Citation(s) | [1853] EWHC J72(QB), (1853) 2 E&B 678, [1843-1860] All ER Rep 12 |
Transcript(s) | Full transcript |
Case opinions | |
Lord Campbell CJ |
Hochster v De La Tour [1853] EWHC J72(QB) is a landmark English contract law case on anticipatory breach of contract. It held that if a contract is repudiated before the date of performance, damages may be claimed immediately.
In April, De La Tour agreed to employ Hochster as his courier for three months from 1 June 1852, to go on a trip around the European continent. On 11 May, De La Tour wrote to say that Hochster was no longer needed. On 22 May, Hochster sued. De La Tour argued that Hochster was still under an obligation to stay ready and willing to perform till the day when performance was due, and therefore could commence no action before.
Lord Campbell CJ held that Hochster did not need to wait until the date performance was due to commence the action and awarded damages.
If a man promises to marry a woman on a future day, and before that day marries another woman, he is instantly liable to an action for breach of promise of marriage; Short v Stone . [1] If a man contracts to execute a lease on and from a future day for a certain term, and, before that day, executes a lease to another for the same term, he may be immediately sued for breaking the contract; Ford v Tiley . [2] So, if a man contracts to sell and deliver specific goods on a future day, and before the day he sells and delivers them to another, he is immediately liable to an action at the suit of the person with whom he first contracted to sell and deliver them; Bowdell v Parsons . [3] One reason alleged in support of such an action is, that the defendant has, before the day, rendered it impossible for him to perform the contract at the day: but this does not necessarily follow; for, prior to the day fixed for doing the act, the first wife may have died, a surrender of the lease executed might be obtained, and the defendant might have repurchased the goods so as to be in a situation to sell and deliver them to the plaintiff. Another reason may be, that, where there is a contract to do an act on a future day, there is a relation constituted between the parties in the meantime by the contract, and that they impliedly promise that in the meantime neither will do any thing to the prejudice of the other inconsistent with that relation. As an example, a man and woman engaged to marry are affianced to one another during the period between the time of the engagement and the celebration of the marriage.
In the present case, of traveller and courier, from the day of the hiring till the day when the employment was to begin, they were engaged to each other; and it seems to be a breach of an implied contract if either of them renounces the engagement. This reasoning seems in accordance with the unanimous decision of the Exchequer Chamber in Elderton v Emmens , [4] which we have followed in subsequent cases in this Court. The declaration in the present case, in alleging a breach, states a great deal more than a passing intention on the part of the defendant which he may repent of, and could only be proved by evidence that he had utterly renounced the contract, or done some act which rendered it impossible for him to perform it. If the plaintiff has no remedy for breach of the contract unless he treats the contract as in force, and acts upon it down to the 1st June 1852, it follows that, till then, he must enter into no employment which will interfere with his promise "to start with the defendant on such travels on the day and year," and that he must then be properly equipped in all respects as a courier for a three months' tour on the continent of Europe.
But it is surely much more rational, and more for the benefit of both parties, that, after the renunciation of the agreement by the defendant, the plaintiff should be at liberty to consider himself absolved from any future performance of it, retaining his right to sue for any damage he has suffered from the breach of it. Thus, instead of remaining idle and laying out money in preparations which must be useless, he is at liberty to seek service under another employer, which would go in mitigation of the damages to which he would otherwise be entitled for a breach of the contract. It seems strange that the defendant, after renouncing the contract, and absolutely declaring that he will never act under it, should be permitted to object that faith is given to his assertion, and that an opportunity is not left to him of changing his mind. If the plaintiff is barred of any remedy by entering into an engagement inconsistent with starting as a courier with the defendant on the 1st June, he is prejudiced by putting faith in the defendant's assertion: and it would be more consonant with principle, if the defendant were precluded from saying that he had not broken the contract when he declared that he entirely renounced it.
Suppose that the defendant, at the time of his renunciation, had embarked on a voyage for Australia, so as to render it physically impossible for him to employ the plaintiff as a courier on the continent of Europe in the months of June, July and August 1852: according to decided cases, the action might have been brought before the 1st June; but the renunciation may have been founded on other facts, to be given in evidence, which would equally have rendered the defendant's performance of the contract impossible. The man who wrongfully renounces a contract into which he has deliberately entered cannot justly complain if he is immediately sued for a compensation in damages by the man whom he has injured: and it seems reasonable to allow an option to the injured party, either to sue immediately, or to wait till the time when the act was to be done, still holding it as prospectively binding for the exercise of this option, which may be advantageous to the innocent party, and cannot be prejudicial to the wrongdoer.
An argument against the action before the 1st of June is urged from the difficulty of calculating the damages: but this argument is equally strong against an action before the 1st of September, when the three months would expire. In either case, the jury in assessing the damages would be justified in looking to all that had happened, or was likely to happen, to increase or mitigate the loss of the plaintiff down to the day of trial.
We do not find any decision contrary to the view we are taking of this case... The only other case cited in the argument which we think it necessary to notice is Planche v Colburn , [5] which appears to be an authority for the plaintiff. There the defendants had engaged the plaintiff to write a treatise for a periodical publication. The plaintiff commenced the composition of the treatise; but, before he had completed it, and before the time when in the course of conducting the publication it would have appeared in print, the publication was abandoned. The plaintiff thereupon, without completing the treatise, brought an action for breach of contract. Objection was made that the plaintiff could not recover on the special contract for want of having completed, tendered and delivered the treatise, according to the contract. Tindal CJ said: "The fact was, that the defendants not only suspended, but actually put an end to, 'The Juvenile Library;' they had broken their contract with the plaintiff." The declaration contained counts for work and labour: but the plaintiff appears to have retained his verdict on the count framed on the special contract, thus shewing that, in the opinion of the Court, the plaintiff might treat the renunciation of the contract by the defendants as a breach, and maintain an action for that breach, without considering that it remained in force so as to bind him to perform his part of it before bringing an action for the breach of it.
If it should be held that, upon a contract to do an act on a future day, a renunciation of the contract by one party dispenses with a condition to be performed in the meantime by the other, there seems no reason for requiring that other to wait till the day arrives before seeking his remedy by action: and the only ground on which the condition can be dispensed with seems to be, that the renunciation may be treated as a breach of the contract.
Upon the whole, we think that the declaration in this case is sufficient. It gives us great satisfaction to reflect that, the question being on the record, our opinion may be reviewed in a Court of Error. In the meantime we must give judgment for the plaintiff.
Judgment for plaintiff.
At common law, damages are a remedy in the form of a monetary award to be paid to a claimant as compensation for loss or injury. To warrant the award, the claimant must show that a breach of duty has caused foreseeable loss. To be recognised at law, the loss must involve damage to property, or mental or physical injury; pure economic loss is rarely recognised for the award of damages.
Negligence is a failure to exercise appropriate and/or ethical ruled care expected to be exercised amongst specified circumstances. The area of tort law known as negligence involves harm caused by failing to act as a form of carelessness possibly with extenuating circumstances. The core concept of negligence is that people should exercise reasonable care in their actions, by taking account of the potential harm that they might foreseeably cause to other people or property.
A tort is a civil wrong that causes a claimant to suffer loss or harm, resulting in legal liability for the person who commits the tortious act. In some, but not all, civil and mixed law jurisdictions, the term delict is used to refer to this category of civil wrong, though it can also refer to criminal offences in some jurisdictions and tort is the general term used in comparative law. The word tort stems from Old French via the Norman Conquest and Latin via the Roman Empire. The word 'tort' was first used in a legal context in the 1580s, although different words were used for similar concepts prior to this time.
Breach of contract is a legal cause of action and a type of civil wrong, in which a binding agreement or bargained-for exchange is not honored by one or more of the parties to the contract by non-performance or interference with the other party's performance. Breach occurs when a party to a contract fails to fulfill its(s), whether partially or wholly, as described in the contract, or communicates an intent to fail the obligation or otherwise appears not to be able to perform its obligation under the contract. Where there is breach of contract, the resulting damages will have to be paid by the party breaching the contract to the aggrieved party.
Quantum meruit is a Latin phrase meaning "what one has earned". In the context of contract law, it means something along the lines of "reasonable value of services".
A legal remedy, also referred to as judicial relief or a judicial remedy, is the means with which a court of law, usually in the exercise of civil law jurisdiction, enforces a right, imposes a penalty, or makes another court order to impose its will in order to compensate for the harm of a wrongful act inflicted upon an individual.
In common law jurisdictions, a misrepresentation is an untrue or misleading statement of fact made during negotiations by one party to another, the statement then inducing that other party to enter into a contract. The misled party may normally rescind the contract, and sometimes may be awarded damages as well.
Tortious interference, also known as intentional interference with contractual relations, in the common law of torts, occurs when one person intentionally damages someone else's contractual or business relationships with a third party, causing economic harm. As an example, someone could use blackmail to induce a contractor into breaking a contract; they could threaten a supplier to prevent them from supplying goods or services to another party; or they could obstruct someone's ability to honor a contract with a client by deliberately refusing to deliver necessary goods.
Ex turpi causa non oritur actio is a legal doctrine which states that a plaintiff will be unable to pursue legal relief and damages if it arises in connection with their own tortious act. Particularly relevant in the law of contract, tort and trusts, ex turpi causa is also known as the illegality defence, since a defendant may plead that even though, for instance, he broke a contract, conducted himself negligently or broke an equitable duty, nevertheless a claimant by reason of his own illegality cannot sue. The UK Supreme Court provided a thorough reconsideration of the doctrine in 2016 in Patel v Mirza.
An adequate remedy or adequate remedy at law is part of a legal remedy which the court deems satisfactory, without recourse to an equitable remedy This consideration expresses to the court whether money should be awarded or a court order should be decreed.. Adequate remedy at law refers to the sufficient compensation for the loss or damages caused by the defendant with a proper monetary award. The court must grant the adequacy of remedy that will lead to a "meaningful hearing". Whether legal damages or equitable relief are requested depends largely on,whether or not the remedy can be valued. Both two elements, compensation and the meaningfulness of hearing, provide a proper way to have an adequate remedy. The word "meaningfulness" of hearing in the law process is the assumption that the defendant compensated must be meaningful for the injured party where the defendant made a fully covered compensation for all the losses. Hence, the hearing in which cannot give any right amount of compensation award or settlement is not "meaningful", and the unavailability of the compensation will lead to an inadequate remedy. The adequate remedy at law is the legal remedies by meaning it is satisfactory compensation by way of monetary damages without granting equitable remedies.
Peevyhouse v. Garland Coal & Mining Co., 382 P.2d 109, is a US contract law case decided by the Supreme Court of Oklahoma. It concerns the question of when specific performance of a contractual obligation will be granted and the measure of expectation damages.
Torquay Hotel Co Ltd v Cousins [1968] EWCA Civ 2 (BAILII) is a UK labour law case concerning the liability of a union when its members take industrial action.
Daulia Ltd v Four Millbank Nominees Ltd [1977] is an English contract law case, concerning unilateral contracts, and when embarking on the performance of an act for which an offer is open, at what point the offer may be withdrawn. In particular, Goff LJ observed that there would be a duty to not prevent full performance of terms in a unilateral offer, once performance had begun.
Attorney General v Blake[2000] UKHL 45, [2001] 1 AC 268 is a leading English contract law case on damages for breach of contract. It established that in some circumstances, where ordinary remedies are inadequate, restitutionary damages may be awarded.
Baltic Shipping Company v Dillon, the Mikhail Lermontov case, is a leading Australian contract law case, on the incorporation of exclusion clauses and damages for breach of contract or restitution for unjust enrichment.
Addis v Gramophone Co Ltd [1909] AC 488 is an old English contract law and UK labour law case, which used to restrict damages for non-pecuniary losses for breach of contract.
Parsons (Livestock) Ltd v Uttley Ingham & Co Ltd [1978] QB 791 is an English contract law case, concerning remoteness of damage. In it, the majority held that losses for breach of contract are recoverable if the type or kind of loss is a likely result of the breach of contract. Lord Denning MR, dissenting on the reasoning, held that a distinction should be drawn between losses for physical damage and economic losses.
Mitigation in law is the principle that a party who has suffered loss has to take reasonable action to minimize the amount of the loss suffered. As stated by the Canadian Federal Court of Appeal in Redpath Industries Ltd. v. Cisco (The), "It is well established that a party who suffers damages as a result of a breach of contract has a duty to mitigate those damages, that is to say that the wrongdoer cannot be called upon to pay for avoidable losses which would result in an increase in the quantum of damages payable to the injured party." The onus on showing a failure to mitigate damages is on the defendant. In the UK, Lord Leggatt describes the "function of the doctrine of mitigation" as enabling the law
to distinguish between effects on the claimant's financial position which are to be regarded as caused by the defendant's breach of contract and for which damages can therefore be recovered and effects which are attributed to the claimant's own action or inaction in response to the breach and for which the defendant is not liable.
Cooper Manufacturing Co. v. Ferguson, 113 U.S. 727 (1885), was a suit regarding the legitimacy of a sale of a steam engine and other machinery in the State of Ohio.
Kingston v Preston (1773) 2 Doug KB 689 is an English contract law case, concerning the right to withhold performance for a contract.