The Logical Framework Approach (LFA) is a methodology mainly used for designing, monitoring, and evaluating international development projects. Variations of this tool are known as Goal Oriented Project Planning (GOPP) or Objectives Oriented Project Planning (OOPP).
The Logical Framework Approach was developed in 1969 for the U.S. Agency for International Development (USAID). It is based on a worldwide study by Leon J. Rosenberg, a principal of Fry Consultants Inc. [1] In 1970 and 1971, USAID implemented the method in 30 country assistance programs under the guidance of Practical Concepts Incorporated, founded by Rosenberg. [2]
It has been widely used by multilateral donor organizations, such as AECID, GIZ, SIDA, NORAD, DFID, SDC, UNDP, EC and the Inter-American Development Bank. Some non-governmental organizations offer LFA training to ground-level field staff. [3] It has also gained popularity in the private sector, for example, in health care. [4]
The Logical Framework Approach takes the form of a four-by-four project table, often referred to as a "Logframe".
The rows represent types of events that take place as a project is implemented: Activities, Outputs, Purpose and Goal (from bottom to top on the left hand side — see EC web site under external links).
The columns represent types of information about the events: a Narrative description, Objectively Verifiable Indicators (OVIs) of these events taking place, Means of Verification (MoV) where information will be available on the OVIs, and Assumptions. Assumptions are external factors that could have an influence, whether positive or negative, on the events described in the narrative column.
The list of assumptions should include the factors that may impact the project's success but cannot be directly controlled by the project or program managers. In some cases, these include what could be killer assumptions, which if invalid will have major negative consequences for the project. A good project design should be able to substantiate its assumptions, especially those with a high potential to have a negative impact.
The core of the Logical Framework is the "temporal logic model" that runs through the matrix. This takes the form of a series of connected propositions:
These are viewed as a hierarchy of hypotheses, with the project or program manager sharing responsibility with higher management for the validity of hypotheses beyond the output level. Thus, Rosenberg brought the essence of scientific method to non-scientific endeavors.
The "Assumptions" column is important in clarifying the extent to which the project or program objectives depend on external factors, and greatly clarify "force majeure" which are out of control of the project delivery partners — an area that was of particular interest when the Canadian International Development Agency (CIDA) at least briefly used the LFA as the essence of contracts.
The LFA is also used in other contexts, both personal and corporate. When developed within an organization, it can articulate a common interpretation of the objectives of a project and how they will be achieved. The indicators and means of verification force clarifications as one would for a scientific endeavor, as in "you haven't defined it until you say how you will measure it." Tracking progress against carefully defined output indicators provides a clear basis for monitoring progress; verifying purpose and goal level progress then simplifies evaluation. Given a well constructed logical framework, an informed skeptic and a project advocate should be able to agree on exactly what the project attempts to accomplish, and how likely it is to succeed—in terms of programmatic (goal-level) as well as project (purpose-level) objective.
One of its purposes in its early uses was to identify the span of control of 'project management'. In some countries with less than perfect governance and managerial systems, it became an excuse for failure. Externally sourced technical assistance managers were able to say that all activities foreseen have been implemented and all required outputs produced, but because of the sub-optimal systems in the country, which are beyond the control of the project's management, the purpose(s) have not been achieved and so the goal has not been attained. [5]
The Logical Framework Approach, Handbook for objectives-oriented planning, Fourth edition, NORAD, 1999, ISBN 82-7548-160-0.
Strategic Project Management Made Simple: Solution Tools for Leaders and Teams, by Terry Schmidt. (Wiley, 2021) ISBN 978-1-119-71817-8
Project management is the process of leading the work of a team to achieve all project goals within the given constraints. This information is usually described in project documentation, created at the beginning of the development process. The primary constraints are scope, time, and budget. The secondary challenge is to optimize the allocation of necessary inputs and apply them to meet pre-defined objectives.
In common usage, evaluation is a systematic determination and assessment of a subject's merit, worth and significance, using criteria governed by a set of standards. It can assist an organization, program, design, project or any other intervention or initiative to assess any aim, realisable concept/proposal, or any alternative, to help in decision-making; or to ascertain the degree of achievement or value in regard to the aim and objectives and results of any such action that has been completed.
ISO 14000 is a family of ‘standards’ - the standard (14001) + guidelines - related to environmental management that exists to help organizations (a) minimize how their operations negatively affect the environment ; (b) comply with applicable laws, regulations, and other environmentally oriented requirements; and (c) continually improve in the above.
Program evaluation is a systematic method for collecting, analyzing, and using information to answer questions about projects, policies and programs, particularly about their effectiveness and efficiency.
A performance indicator or key performance indicator (KPI) is a type of performance measurement. KPIs evaluate the success of an organization or of a particular activity in which it engages. KPIs provide a focus for strategic and operational improvement, create an analytical basis for decision making and help focus attention on what matters most.
Adaptive management, also known as adaptive resource management or adaptive environmental assessment and management, is a structured, iterative process of robust decision making in the face of uncertainty, with an aim to reducing uncertainty over time via system monitoring. In this way, decision making simultaneously meets one or more resource management objectives and, either passively or actively, accrues information needed to improve future management. Adaptive management is a tool which should be used not only to change a system, but also to learn about the system. Because adaptive management is based on a learning process, it improves long-run management outcomes. The challenge in using the adaptive management approach lies in finding the correct balance between gaining knowledge to improve management in the future and achieving the best short-term outcome based on current knowledge. This approach has more recently been employed in implementing international development programs.
COBIT is a framework created by ISACA for information technology (IT) management and IT governance.
The Committee of Sponsoring Organizations of the Treadway Commission (COSO) is an organization that develops guidelines for businesses to evaluate internal controls, risk management, and fraud deterrence. In 1992 (and subsequently re-released in 2013), COSO published the Internal Control - Integrated Framework, commonly used by businesses in the United States to design, implement, and conduct systems of internal control over financial reporting and assessing their effectiveness.
Capacity building is the improvement in an individual's or organization's facility "to produce, perform or deploy". The terms capacity building and capacity development have often been used interchangeably, although a publication by OECD-DAC stated in 2006 that capacity development was the preferable term. Since the 1950s, international organizations, governments, non-governmental organizations (NGOs) and communities use the concept of capacity building as part of "social and economic development" in national and subnational plans. The United Nations Development Programme defines itself by "capacity development" in the sense of "'how UNDP works" to fulfill its mission. The UN system applies it in almost every sector, including several of the Sustainable Development Goals to be achieved by 2030. For example, the Sustainable Development Goal 17 advocates for enhanced international support for capacity building in developing countries to support national plans to implement the 2030 Agenda.
Organizational effectiveness is a concept organizations use to gauge how effective they are at reaching intended outcomes. Organizational effectiveness is both a powerful and problematic term. The strength of it is that it may be used to critically evaluate and improve organisational activities. It's problematic since it means various things to different individuals. And there are other alternative methods for measuring organizational performance. Organizational effectiveness embodies the degree to which firms achieve the goals they have decided upon, a question that draws on several different factors. Among those are talent management, leadership development, organization design and structure, design of measurements and scorecards, implementation of change and transformation, deploying smart processes and smart technology to manage the firms' human capital and the formulation of the broader Human Resources agenda.
Logic models are hypothesized descriptions of the chain of causes and effects leading to an outcome of interest. While they can be in a narrative form, logic model usually take form in a graphical depiction of the "if-then" (causal) relationships between the various elements leading to the outcome. However, the logic model is more than the graphical depiction: it is also the theories, scientific evidences, assumptions and beliefs that support it and the various processes behind it.
The Triad is an approach by the United States Environmental Protection Agency to decision-making for hazardous-waste site cleanup. During the late 1990s, technology advocates from the environmental sector in the United States developed the approach by combining innovations in management and technology with ideas from hazardous-waste site cleanup experience.
Participatory impact pathways analysis (PIPA) is a project management approach in which the participants in a project, including project staff, key stakeholders, and the ultimate beneficiaries, together co-construct their program theory.
GQM+Strategies is a method that provides concepts and actionable steps for creating the link between goals and strategies across an organization and allows for measurement-based decision-making. It was developed by Victor Basili, Jens Heidrich, Mikael Lindvall, Jürgen Münch, Myrna Regardie, Carolyn B. Seaman, and Adam Trendowicz. The method was originally developed for organizations having a strong focus on IT and the development of software systems, but the method's popularity has grown to other domains and can be applied to any organization. The book Aligning Organizations through Measurement gives a comprehensive overview of the method, provides actionable guidance, case studies, and practical applications.
Theory of Change (ToC) is a methodology or a criterion for planning, participation, adaptive management, and evaluation that is used in companies, philanthropy, not-for-profit, international development, research, and government sectors to promote social change. Theory of Change defines long-term goals and then maps backward to identify necessary preconditions.
Small-scale project management is the specific type of project management of small-scale projects. These projects are characterised by factors such as short duration; low person hours; small team; size of the budget and the balance between the time committed to delivering the project itself and the time committed to managing the project. They are otherwise unique, time delineated and require the delivery of a final output in the same way as large-scale projects.
Ghana's Ministry of Food and Agriculture (MOFA) is the government agency responsible for the development and growth of agriculture in the country. The jurisdiction does not cover the cocoa, coffee or forestry sectors.
Results-based management (RBM) is a tool for monitoring and managing the implementation of strategy. It in many respects is similar to the logical framework approach, a strategy implementation tool used extensively by Non-governmental organizations.
Monitoring and Evaluation (M&E) is a combined term for the processes set up by organizations such as companies, government agencies, international organisations and NGOs, with the goal of improving their management of outputs, outcomes and impact. Monitoring includes the continuous assessment of programmes based on early detailed information on the progress or delay of the ongoing assessed activities. Evaluation involves the examination of the relevance, effectiveness, efficiency and impact of activities in the light of specified objectives.
Monitoring Education for Sustainable Development (ESD) refers to measuring progress in ESD learning compared to policy commitments, provision, institutional support, resources and others. Monitoring and evaluation (M&E) of Education for Sustainable Development is widely discussed in literature on ESD, including debates regarding methodology and strategies for interpreting the data.