Lump sum contract

Last updated
Typical Lump Sum Contract Structure LumpSum1.png
Typical Lump Sum Contract Structure

A lump sum contract in construction is one type of construction contract, sometimes referred to as stipulated-sum, where a single price is quoted for an entire project based on plans and specifications and covers the entire project and the owner knows exactly how much the work will cost in advance. [1] This type of contract requires a full and complete set of plans and specifications and includes all the indirect costs plus the profit and the contractor will receive progress payments each month minus retention. The flexibility of this contract is very minimal and changes in design or deviation from the original plans would require a change order paid by the owner. [2] In this contract the payment is made according to the percentage of work completed. [3] The lump sum contract is different from guaranteed maximum price in a sense that the contractor is responsible for additional costs beyond the agreed price, however, if the final price is less than the agreed price then the contractor will gain and benefit from the savings. [4]

Contents

There are some factors that make for a successful execution of a lump sum contract on a project such as experience and confidence, management skills, communication skills, having a clear work plan, proper list of deliverables, contingency, and dividing the responsibility among the project team. [5]

According to Associated General Contractors of America (AGC),

In a lump sum contract, the owner has essentially assigned all the risk to the contractor, who in turn can be expected to ask for a higher markup in order to take care of unforeseen contingencies. A Contractor under a lump sum agreement will be responsible for the proper job execution and will provide its own means and methods to complete the work. [6]

With a lump sum contract or fixed-price contract, the contractor assesses the value of work as per the documents available, primarily the specifications and the drawings. At pre-tender stage the contractor evaluates the cost to execute the project (based on the above documents such as drawings, specifications, schedules, tender instruction and any clarification received in response to queries) and quotes a fixed inclusive price. [7]

Advantages

Disadvantages

Variations to lump sum contracts

Variations occur due to fluctuation in prices and inflation, provisional items, statutory fees, relevant events such as failure of the owner to deliver goods, etc. [8] [9] Where the cost of a specific activity is identified as a "provisional sum", a variation in actual cost may be accepted by the employer.

Variations are typically broken down into two categories, beneficial and detrimental, where the former is for improvement of work quality, cost and schedule reduction, and the latter is a negative change in performance or quality of work due to client's financial difficulties. There are many reasons for variations to occur but main causes are normally due to omission in design, inadequate design, changes in specifications and scope, and lack of coordination and communication among the stakeholders. [11]

Case law

Related Research Articles

<span class="mw-page-title-main">Architect</span> Person who designs buildings and oversees construction

An architect is a person who plans, designs, and oversees the construction of buildings. To practice architecture means to provide services in connection with the design of buildings and the space within the site surrounding the buildings that have human occupancy or use as their principal purpose. Etymologically, the term architect derives from the Latinarchitectus, which derives from the Greek, i.e., chief builder.

Build–operate–transfer (BOT) or build–own–operate–transfer (BOOT) is a form of project delivery method, usually for large-scale infrastructure projects, wherein a private entity receives a concession from the public sector to finance, design, construct, own, and operate a facility stated in the concession contract. The private entity will have the right to operate it for a set period of time. This enables the project proponent to recover its investment and operating and maintenance expenses in the project.

Design–build, also known as alternative delivery, is a project delivery system used in the construction industry. It is a method to deliver a project in which the design and construction services are contracted by a single entity known as the design–builder or design–build contractor. It can be subdivided into architect-led design–build and contractor-led design–build.

Project delivery methods defines the characteristics of how a construction project is designed and built and the responsibilities of the parties involved in the construction. They are used by a construction manager who is working as an agent to the owner or by the owner itself to carry-out a construction project while mitigating the risks to the scope of work, time, budget, quality and safety of the project. These risks ranges from cost overruns, time delays and conflict among the various parties.

Design–bid–build, also known as Design–tender, traditional method, or hardbid, is a project delivery method in which the agency or owner contracts with separate entities for the design and construction of a project.

A general contractor, main contractor, prime contractor, builder (UK/AUS), or contractor is responsible for the day-to-day oversight of a construction site, management of vendors and trades, and the communication of information to all involved parties throughout the course of a building project. In the USA a builder may be a sole proprietor managing a project and performing labor or carpentry work, have a small staff, or may be a very large company managing billion dollar projects. Some builders build new homes, some are remodelers, some are developers.

Time and materials (T&M) is a standard phrase in a contract for construction, product development or any other piece of work in which the employer agrees to pay the contractor based upon the time spent by the contractor's employees and subcontractors employees to perform the work, and for materials used in the construction, no matter how much work is required to complete construction. Time and materials is generally used in projects in which it is not possible to accurately estimate the size of the project, or when it is expected that the project requirements would most likely change.

Construction management (CM) aims to control the quality of a project's scope, time, and cost to maximize the project owner's satisfaction. It uses project management techniques and software to oversee the planning, design, construction and closeout of a construction project safely, on time, on budget and within specifications.

A management contract is an arrangement under which operational control of an enterprise is vested by contract in a separate enterprise that performs the necessary managerial functions in return for a fee. Management contracts involve not just selling a method of doing things but actually doing them. A management contract can involve a wide range of functions such as technical operation of a production facility, management of personnel, accounting, marketing services, and training.

A bill of quantities is a document used in tendering in the construction industry in which materials, parts, and labor are itemized. It also (ideally) details the terms and conditions of the construction or repair contract and itemizes all work to enable a contractor to price the work for which he or she is bidding. The quantities may be measured in number, area, volume, weight or time. Preparing a bill of quantities requires that the design is complete and a specification has been prepared.

A guaranteed maximum price contract is a cost-type contract such that the contractor is compensated for actual costs incurred plus a fixed fee, limited to a maximum price. The contractor is responsible for cost overruns greater than the guaranteed maximum price, unless the GMP has been increased by a formal change order. Savings resulting from unexpectedly low costs are returned to the client.

Construction bidding is the process of submitting a proposal (tender) to undertake, or manage the undertaking of a construction project. The process starts with a cost estimate from blueprints and material take offs.

Engineering, procurement, and construction (EPC) contracts are a form of contract used to undertake construction works by the private sector on large-scale and complex infrastructure projects.

Lump sum turnkey (LSTK) is a combination of the business-contract concepts of lump sum and turnkey. Lump sum is a noun which means a complete payment consisting of a single sum of money while turnkey is an adjective of a product or service which means product or service will be ready to use upon delivery.

EPCI stands for Engineering, Procurement, Construction and Installation, a common form of contracting arrangement within offshore construction. The acronym EPIC for Engineering, Procurement, Installation & Commissioning is also used.

Fast-track building construction is construction industry jargon for a project delivery strategy to start construction before the design is complete. The purpose is to shorten the time to completion.

Pre-construction services are services that are offered to support owners, architects, and engineers in making decisions. They are used in planning a construction project before the actual construction begins. The stage where these services are offered is called pre-construction or "pre-con".

A fixed-price contract is a type of contract for the supply of goods or services, such that the agreed payment amount will not subsequently be adjusted to reflect the resources used, costs incurred or time expended by the contractor. This contract type may be contrasted with a cost-plus contract, which is intended to cover the costs incurred by the contractor plus an additional amount for profit, and with time-and-materials contracts and labor-hour contracts. Fixed-price contracts are one of the main options available when contracting for supplies to governments.

Australian Construction Contracts govern how the parties to a construction contract behave and how the project manager and the contract manager administer the relationship between the parties. There are several popular standard forms of construction contracts that are currently used in Australia.

A construction contract is a mutual or legally binding agreement between two parties based on policies and conditions recorded in document form. The two parties involved are one or more property owners and one or more contractors. The owner, often referred to as the 'employer' or the 'client', has full authority to decide what type of contract should be used for a specific development to be constructed and to set out the legally-binding terms and conditions in a contractual agreement. A construction contract is an important document as it outlines the scope of work, risks, duration, duties, deliverables and legal rights of both the contractor and the owner.

References

  1. The project resource manual : CSI manual of practice. New York: McGraw-Hill; Construction Specifications Institute. 2005. ISBN   0071370048. OCLC   56191871.
  2. Halpin, Daniel W. (2006). Construction management (3rd ed.). Hoboken, NJ: Wiley. ISBN   0471661732. OCLC   61425134.
  3. "The Pros and Cons of Pricing Options in Construction Contracts". Bell Davis Pitt. 2017-06-20. Retrieved 2019-07-04.
  4. "Fixed price construction contract - Designing Buildings Wiki". www.designingbuildings.co.uk. Retrieved 2019-07-04.
  5. "Managing Design under Lump-Sum Contract | Journal of Management in Engineering | Vol 11, No 2". ascelibrary.org. doi:10.1061/(asce)0742-597x(1995)11:2(21) . Retrieved 2019-07-04.
  6. "Associated General Contractors". www.agc.org. Retrieved 2019-07-04.
  7. "5 pros & cons of Lump sum Contracts/Fixed price Contracts (with video explain)". Quantitysurveyor.blog.
  8. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 "Lump Sum Construction Contract - Advantages and Disadvantages". The Constructor. 2016-12-09. Retrieved 2019-07-04.
  9. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 "Lump sum contract - pros and cons - Designing Buildings Wiki". www.designingbuildings.co.uk. Retrieved 2019-07-04.
  10. 1 2 3 4 5 6 7 8 "Lump Sum Contract Advantages and Disadvantages in Construction". Construction Tuts. 2017-02-05. Retrieved 2019-07-04.
  11. Khalid, Zul Khafiz Mohd; Sahamir, Shaza Rina; Rahman, Nurul Asra Abd; Zainordin, Zainab Mohmad (2019). "Methods of Valuing Construction Variation in Lump Sum Contract from the Public Client's Perspective". MATEC Web of Conferences. 266: 03023. doi: 10.1051/matecconf/201926603023 . ISSN   2261-236X.
  12. Fenwick Elliott, Harvey Shopfitters Limited -v- ADI Limited, published 13 November 2003, accessed 16 December 2022