Mining feasibility study

Last updated

A mining feasibility study is an evaluation of a proposed mining project to determine whether the mineral resource can be mined economically. There are three types of feasibility study used in mining, order of magnitude, preliminary feasibility and detailed feasibility. [1]

Contents

Order of magnitude

Order of magnitude feasibility studies (sometimes referred to as "scoping studies") are an initial financial appraisal of an inferred mineral resource. Depending on the size of the project, an order of magnitude study may be carried out by a single individual. It will involve a preliminary mine plan, and is the basis for determining whether to proceed with an exploration program, and more detailed engineering work. Order-of-magnitude studies are developed by copying plans and factoring known costs from existing projects completed elsewhere and are accurate to within 40–50%. [1]

Preliminary feasibility

Preliminary feasibility studies or "pre-feasibility studies" are more detailed than order of magnitude studies. A preliminary feasibility study is used in due diligence work, determining whether to proceed with a detailed feasibility study and as a "reality check" to determine areas within the project that require more attention. Preliminary feasibility studies are done by factoring known unit costs and by estimating gross dimensions or quantities once conceptual or preliminary engineering and mine design has been completed. Preliminary feasibility studies are completed by a small group of multi-disciplined technical individuals and have an accuracy within 20-30%. [1]

Detailed feasibility

Detailed feasibility studies are the most detailed and will determine definitively whether to proceed with the project. A detailed feasibility study will be the basis for capital appropriation, and will provide the budget figures for the project. Detailed feasibility studies require a significant amount of formal engineering work, are accurate to within 10-15% and can cost between ½-1½% of the total estimated project cost. [1]

Footnotes

  1. 1 2 3 4 De la Vergne, Jackk (2014). Hard Rock Miner's Handbook (PDF). Edmonton, Alberta: Stantec Consulting. pp. 54–65. ISBN   0-9687006-1-6.

Related Research Articles

Mining Extraction of valuable minerals or other geological materials from the Earth

Mining is the extraction of valuable minerals or other geological materials from the Earth, usually from an ore body, lode, vein, seam, reef, or placer deposit. These deposits form a mineralized commodity that is of economic interest to the miner.

Ore Rock with valuable metals, minerals and elements

Ore is natural rock or sediment that contains one or more valuable minerals, typically containing metals, that can be mined, treated and sold at a profit. Ore is extracted from the earth through mining and treated or refined, often via smelting, to extract the valuable metals or minerals. The grade of ore refers to the concentration of the desired material it contains. The value of the metals or minerals a rock contains must be weighed against the cost of extraction to determine whether it is of sufficiently high grade to be worth mining, and is therefore considered an ore.

Valuation (finance)

In finance, valuation is the process of determining the present value (PV) of an asset. Valuations can be done on assets or on liabilities. Valuations are needed for many reasons such as investment analysis, capital budgeting, merger and acquisition transactions, financial reporting, taxable events to determine the proper tax liability.

Mining engineering Engineering discipline that involves the practice, the theory, the science, the technology, and applicatIon of extracting and processing minerals from a naturally occurring environment

Mining in the engineering discipline is the extraction of minerals from underneath, above or on the ground. Mining engineering is associated with many other disciplines, such as mineral processing, exploration, excavation, geology, and metallurgy, geotechnical engineering and surveying. A mining engineer may manage any phase of mining operations, from exploration and discovery of the mineral resources, through feasibility study, mine design, development of plans, production and operations to mine closure.

Systems development life cycle Systems engineering term

In systems engineering, information systems and software engineering, the software development life cycle (SDLC), also referred to as the application development life-cycle, is a process for planning, creating, testing, and deploying an information system. The systems development life cycle concept applies to a range of hardware and software configurations, as a system can be composed of hardware only, software only, or a combination of both. There are usually six stages in this cycle: requirement analysis, design, development and testing, implementation, documentation, and evaluation.

A feasibility study is an assessment of the practicality of a proposed project or system. A feasibility study aims to objectively and rationally uncover the strengths and weaknesses of an existing business or proposed venture, opportunities and threats present in the natural environment, the resources required to carry through, and ultimately the prospects for success. In its simplest terms, the two criteria to judge feasibility are cost required and value to be attained.

Construction management (CM) is a professional service that uses specialized, project management techniques to oversee the planning, design, and construction of a project, from its beginning to its end. The purpose of Construction management is to control a project's time / delivery, cost and quality—sometimes referred to as a project management triangle or "triple constraints." CM is compatible with all project delivery systems, including design-bid-build, design-build, CM At-Risk and Public Private Partnerships. Professional construction managers may be reserved for lengthy, large-scale, high budget undertakings, called capital projects.

Mineral resource classification is the classification of mineral resources based on an increasing level of geological knowledge and confidence. In an effort to achieve a standard set the classifications, representative bodies from Australia, Canada, South Africa, the USA and the UK reached a provisional agreement in 1997 on the definitions of each of the various mineral classifications. This was followed in 1998 to have these definitions incorporated into the International Framework Classification for Reserves and Resources - Solid Fuels and Mineral Commodities, developed by the United Nations Economic Commission for Europe(UN-ECE).

A cost estimate is the approximation of the cost of a program, project, or operation. The cost estimate is the product of the cost estimating process. The cost estimate has a single total value and may have identifiable component values.

The engineering design process is a common series of steps that engineers use in creating functional products and processes. The process is highly iterative - parts of the process often need to be repeated many times before another can be entered - though the part(s) that get iterated and the number of such cycles in any given project may vary.

For the application of engineering economics in the practice of civil engineering see Engineering economics.

Front-end loading (FEL), also referred to as pre-project planning (PPP), front-end engineering design (FEED), feasibility analysis, conceptual planning, programming/schematic design and early project planning, is the process for conceptual development of projects in processing industries such as upstream oil and gas, petrochemical, natural gas refining, extractive metallurgy, Waste to Energy, and pharmaceuticals. This involves developing sufficient strategic information with which owners can address risk and make decisions to commit resources in order to maximize the potential for success.

Orocobre Limited is a mineral resource company based in Brisbane, Australia. The company's present focus is on lithium and borax mining operations within Argentina. Since 2007 Orocobre Ltd. is registered at the Australian Securities Exchange ASX and as of 2010 listed on the TSX. The company is included in the S&P/ASX 300 Index.

The value of work done (VOWD) is a project management technique for measuring and estimating the project cost at a point in time. It is mainly used in project environments of the Petroleum industry and is defined as the value of goods and services progressed, regardless of whether or not they have been paid for or received. The primary purpose of determining VOWD is to get an accurate and comprehensive as possible estimate of cost for a project at a point in time. This is used in overall project management including reporting and cost control.

Front-End Engineering (FEE), or Front-End Engineering Design (FEED), is an engineering design approach used to control project expenses and thoroughly plan a project before a fix bid quote is submitted. It may also be referred to as Pre-project planning (PPP), front-end loading (FEL), feasibility analysis, or early project planning.

Peak minerals marks the point in time when the largest production of a mineral will occur in an area, with production declining in subsequent years. While most mineral resources will not be exhausted in the near future, global extraction and production is becoming more challenging. Miners have found ways over time to extract deeper and lower grade ores with lower production costs. More than anything else, declining average ore grades are indicative of ongoing technological shifts that have enabled inclusion of more 'complex' processing – in social and environmental terms as well as economic – and structural changes in the minerals exploration industry and these have been accompanied by significant increases in identified Mineral Reserves.

Orex Exploration

Orex Exploration is a former Canadian gold mining company that conducted exploration work on mining properties it owned in the Goldboro and Guysborough County areas of Nova Scotia. The properties owned by Orex were the sites of the former Boston Richardson Mine, Dolliver Mountain Mine, West Goldbrook Mine, and East Goldbrook Mine which operated between 1892 and 1912. Headquartered in Rouyn-Noranda, Quebec, the company was founded in 1987 and raised funds for exploration work, in part, by issuing stocks traded on the Montreal Stock Exchange and then the TSX Venture Exchange. It became a subsidiary of Anaconda Mining Inc. after Anaconda acquired the company in a stock swap deal in 2017.

Seabridge Gold is a Canadian company that is pursuing the development of the Kerr Sulphurets Mitchell ("KSM") gold-silver-molybdenum-copper mine in northwest British Columbia. Headquartered in Toronto, the company is listed on the Toronto Stock Exchange and the New York Stock Exchange. The company was founded in 1979 as a mining company but, in 1999, re-organized to pursue exploration and development of gold deposits with a new board of directors and new management team. Of the mineral properties acquired between 2000 and 2002, the KSM project emerged as its core asset. The project advanced through its preliminary feasibility study, and received its environmental assessment approval in 2014. The Company has completed new development plans and is actively looking for a partner to co-develop the project. KSM is one of the world’s largest gold/copper projects as measured by mineral reserves and resources. Seabridge also owns several other mineral properties, including the Courageous Lake project in Northwest Territories, the Iskut project in northwest BC, the Snowstorm project in Nevada and the 3 Aces project in Canada’s Yukon.

The Toroparu mine is estimated to be one of the largest gold mining projects in Guyana. The mine is located in the north-west of the country in Cuyuni-Mazaruni. The mine has estimated reserves of 6 million oz of gold.

Mineral resource estimation is used to determine and define the ore tonnage and grade of a geological deposit, from the developed block model. There are different estimation methods used for different scenarios dependent upon the ore boundaries, geological deposit geometry, grade variability and the amount of time and money available. A typical resource estimation involves the construction of a geological and resource model with data from various sources. Depending on the nature of the information and whether the data is hard copy or computerized, the principal steps of computer resource estimation are:

  1. Creation, standardization and validation of the database.
  2. Section plotting and interactive geological modeling.
  3. Geostatistical analysis.
  4. Block modeling and block estimation.