Morecambe South gas field | |
---|---|
Country | United Kingdom |
Region | Irish Sea |
Location/blocks | UK Block 110/2a and extends into Blocks 110/3a, 110/8a, 110/7a |
Offshore/onshore | offshore |
Coordinates | 53°50′48″N3°34′51″W / 53.84667°N 3.58083°W |
Operators | Hydrocarbons GB Limited, British Gas E & P Ltd, Centrica plc, Spirit Energy |
Owner | Hydrocarbons GB Limited, British Gas E & P Ltd, Centrica plc, Spirit Energy |
Service contractors | see text |
Field history | |
Discovery | September 1974 |
Start of production | January 1985 |
Production | |
Estimated gas in place | 150×10 9 m3 (5.3×10 12 cu ft) |
Producing formations | Triassic sandstone |
The Morecambe gas fields are two major natural gas producing fields in the Irish Sea, 27 km west of Blackpool and Morecambe Bay.
The Morecambe South field is in UK Block 110/2a and extends into Blocks 110/3a, 110/8a, 110/7a; Morecambe North is in Block 110/2a. The fields were discovered in September 1974 and February 1976 respectively. [1] [2] The fields are named after a light-ship station, they are sometimes erroneously called Morecambe Bay. [2]
The gas reservoir is a Triassic sandstone and has the following characteristics. [3] [4]
Reservoir depth, feet | 2,200 to 3,750 |
Gas column, feet | 1,650 |
Porosity, % | 12-15 |
Nitrogen content, % | 7-8 |
Pressure at depth | 1,875 psi @ 3,750 feet |
Recoverable reserves, trillion cubic feet (1985) | 5. 2 |
Recoverable reserves South billion cubic metres (1994) | 150.0 / 5.2 Tcf |
Recoverable reserves North billion cubic metres (1994) | 35.0 / 1.2 Tcf |
In 1985 the sole licensee of the field and the operator was Hydrocarbons GB Limited. [3] This had become British Gas E & P Ltd by 1994, then Centrica plc in 1997. In 2017, Centrica launched Spirit Energy a joint venture with German energy and infrastructure company Stadtwerke München (SWM). Spirit Energy assumed ownership of the Morecambe gas fields. [5]
The Morecambe gas fields development was to provide peak UK demand for gas in the winter. Morecambe South was developed around a central drilling, production and accommodation complex. This comprised three bridge linked platforms plus a bridge-linked flare tower. Details of the platforms are as shown. [3]
Platform | CPP1 | AP1 | DP1 |
---|---|---|---|
Type | Steel jacket | Steel jacket | Steel jacket |
Function | Central processing | Accommodation for 176 | Wellhead drilling |
Coordinates | 53°50’48”N 03°34’51”W | 53.846667N 3.580556W | 53.846861N 3.580556W |
Water depth, metres | 26 | 26 | 26 |
Design contractors | Matthew Hall Eng. | Matthew Hall Eng. | Worley-Atkins |
Topsides fabrication | Wm Press, Wallsend | ||
Topside installation | March 1984 | June 1984 | 1985 |
Jacket fabrication | RGC Offshore, Methil | RGC Offshore, Methil | McDermott, Ardesier |
Jacket weight, tonnes | 11,754 | 4,100 | 5,500 |
Jacket installation | October 1983 | March 1984 | April 1984 |
Legs | 8 | 4 | 4 |
Piles | 32 | 12 | |
Wells | – | – | 16 (5-8 planned) |
Startup | January 1984 | – | 1985 |
Export to | Barrow, 39 km 36-inch pipeline | – | CPP1 via bridge |
The central complex Flare tower (53.846667N 3.580556W) is linked by a bridge to the CPP1 platform. It is supported by a 3-leg jacket.
In addition to the central DP1 drilling and wellhead platform, four other wellhead platforms were installed in the field, each producing well fluids to the CPP1 platform. [3]
Platform | DP3 | DP4 | DP6 | DP8 |
---|---|---|---|---|
Type | Steel jacket | Steel jacket | Steel jacket | Steel jacket |
Function | Wellhead drilling | Wellhead drilling | Wellhead drilling | Wellhead drilling |
Coordinates | 53°49’00”N 03°33’37”W | 53°52’34”N 03°39’39”W | 53.867278N 3.616650W | 53.891872N 3.622833W |
Water depth, metres | 30 | 30 | 32 | 32 |
Accommodation | 6 | 6 | ||
Design contractors | Worley-Atkins | Worley-Atkins | ||
Topsides weight, tonnes | 5,200 | 5,200 | ||
Topside installation | September 1983 | July 1984 | ||
Jacket fabrication | McDermott, Ardesier | Howard Doris, Kishorm | ||
Jacket weight, tonnes | 5,500 | 5,500 | ||
Jacket installation | July 1983 | July 1984 | ||
Legs | 4 | 4 | ||
Wells | 16 (5-8 planned) | 16 (5-8 planned) | ||
Startup | 1985 | 1985 | 1985 | 1985 |
Export to | CPP1, 3.5 km 24-inch pipeline | CPP1, 3.5 km 24-inch pipeline | CPP1, 3.2 km 24-inch pipeline | CPP1, 5.8km 24-inch pipeline |
Because the gas reservoir is shallow, and to avoid a large deviation of the wells, slant drilling is used. Two jack up drilling rigs were built to undertake 30 degree slant drilling. The rigs were Morecambe Flame and Bay Driller.
In 1984 a single drilling and production platform was installed in the Morecambe North field. [5] [6]
Platform | Block | Coordinates | Water depth | Operational | Export |
---|---|---|---|---|---|
Morecambe North | 110/2a | 53.960578N 3.670694W | 29 metres | October 1994 | 37 km pipeline to Barrow |
The Bains field was developed in 2002 by a single subsea wellhead producing well fluids to DP1 via a 8.3 km 8-inch pipeline. [5]
The Bains field was developed in 2002 by a single subsea wellhead producing well fluids to DP1 via a 8.3 km 8-inch pipeline. [5]
Field | Block | Coordinates | Water depth | Operational |
---|---|---|---|---|
Bains | 110/3c | 53.875833N 3.465556W | 18 metres | 2002 |
The North Morecambe platform was modified to tie in the Millom East / West and Dalton fields, and in 2013 the addition of the Rhyl field. [5]
Well fluids from the wellhead platforms are piped to the CPP1 platform. Three phase separation into gas, condensate and water is undertaken. The gas is dehydrated using tri-ethylene glycol. Dry gas together with condensate is piped ashore. [3]
Initial production from Morecambe South field in the winter of 1984-5 was 120 million standard cubic feet of gas per day (MMSCFD). This increased to 450 MMSCFD in the winter of 1985-6 and ultimately to 1,200 MMSCFD. [3] The first year of peak production was 1993 when the South field produced 8.6 billion cubic metres per year. [1]
The first year of peak production for the Morecambe North field was 1995 when the field produced 3.1 billion cubic metres of gas per year. [1]
The decommissioning of the DP3 and DP4 platforms is currently (2021) underway. [6] [7]
Morecambe Bay is an estuary in north-west England, just to the south of the Lake District National Park. It is the largest expanse of intertidal mudflats and sand in the United Kingdom, covering a total area of 120 sq mi (310 km2). In 1974, the second largest gas field in the UK was discovered 25 mi (40 km) west of Blackpool, with original reserves of over 7 trillion cubic feet (tcf). At its peak, 15% of Britain's gas supply came from the bay but production is now in decline. Morecambe Bay is also an important wildlife site, with abundant birdlife and varied marine habitats.
Platform Name - Tern Alpha.
The Everest gasfield is located in the Central North Sea, 233 kilometres (145 mi) east of Aberdeen, Scotland. It lies in the United Kingdom Continental Shelf blocks 22/9, 22/10a and 22/14a. The gasfield was discovered by Amoco in 1982 with first gas produced in 1993.
Amethyst is a natural gas field in the Southern North Sea, about 30 miles (48 km) east of the Yorkshire coast. Gas lies in a Permian sandstone reservoir around 2,700 metres (8,900 ft) below the seabed. The gasfield is operated by BP.
The Eastern Trough Area Project, commonly known as ETAP, is a network of nine smaller oil and gas fields in the Central North Sea covering an area up to 35 km in diameter. There are a total of nine different fields, six operated by BP and another three operated by Shell, and together, they are a rich mix of geology, chemistry, technology and equity arrangements.
The Andrew oilfield is a relatively small hydrocarbon field in the UK sector of the North Sea, 230 kilometres (140 mi) North-East of Aberdeen and it is operated by BP. It is produced from a single platform, which is also the hub of the Kinnoull, Cyrus and Farragon subsea developments.
The Bouri Offshore Field is part of Block NC-41, which is located 120 kilometers (75 mi) north of the Libyan coast in the Mediterranean Sea. It was first discovered in 1976 at a depth of 8,700 feet (2,700 m) and is estimated to contain 4.5 billion barrels (720,000,000 m3) in proven recoverable crude oil reserves and 3.5 trillion cubic feet (99 km3) of associated natural gas with an annual production potential of 6 billion m³. Bouri is considered the largest producing oilfield in the Mediterranean.
Theddlethorpe Gas Terminal (TGT) is a former gas terminal on the Lincolnshire coast on Mablethorpe Road at Theddlethorpe St Helen close to Mablethorpe in East Lindsey in England. It is just off the A1031 and next door to a holiday camp and Mablethorpe Seal Sanctuary and Wildlife Centre.
The Bacton Gas Terminal is a complex of six gas terminals within four sites located on the North Sea coast of North Norfolk in the United Kingdom. The sites are near Paston and between Bacton and Mundesley; the nearest town is North Walsham.
Rampside Gas Terminal is a gas terminal situated in Barrow-in-Furness, Cumbria on the Irish Sea coast. It connects to gas fields in Morecambe Bay. It is situated adjacent to the former Roosecote Power Station.
Vale is an offshore gas field in the North Sea located 16 kilometres (9.9 mi) north of the Heimdal gas field. The depth of the water in the field area is 115 metres (377 ft). Vale is considered a satellite to Heimdal field and is connected to it by a pipeline. Estimated reserves at Vale stand at 2.5 billion cubic metres of natural gas and 21 million barrels (3,300,000 m3) of gas condensate. Vale gas field is expected to produce 1.6 million cubic metres per day of natural gas and 2,600 barrels per day (410 m3/d) of condensate.
Tyra Field is the largest gas condensate field in the Danish Sector of the North Sea. It was discovered in 1968 and production started in 1984. The field is owned by Dansk Undergrunds Consortium, a partnership between Total, BlueNord and Nordsofonden, and operated by Total. The reservoir depth is about 2,000 metres (6,600 ft) and it covers area of 90 kilometres (56 mi) in the water depth of 37–40 metres (121–131 ft). The Tyra field has a number of satellite fields, including Roar, Svend and Tyra Southeast fields.
The L4-L7 gas fields are significant natural gas producing fields in the Netherlands sectors L4 and L7 of the North Sea. They are operationally one complex which started producing gas from the L7 main platform hub in 1977 and was still partly operational in 2021.
Alwyn North is a major oil and gas field in the United Kingdom sector of the northern North Sea, 160 km east of the Shetland Islands. The field was developed through two bridge-linked offshore platforms and a number of subsea satellite wellheads. Alwyn North has been producing oil and gas since 1987 and is still (2023) in operation.
The Beryl oil field is a major crude oil production field in the UK sector of the northern North Sea, 335 km north east of Aberdeen. Production of oil started in 1976 and the field is still producing oil and gas (2021).
The Tartan oil field is a significant crude oil producing field in the UK sector of the North Sea, 187 km north-east of Aberdeen. Production of oil started in 1981 and ceased in 2020, the Tartan Alpha installation is currently (2021) undergoing decommissioning.
The Ravenspurn gas fields are two adjacent natural gas fields located in the UK sector of the southern North Sea about 65 km east of Flambrough Head, Yorkshire.
The Lincolnshire Offshore Gas Gathering System (LOGGS) was a major natural gas collection, processing and transportation complex in the UK sector of the southern North Sea. It comprised five bridge-linked platforms about 118 km east of the Lincolnshire coast, which operated from 1988 to 2018.
The Pickerill and Juliet gas fields are decommissioned natural gas producing facilities in the UK sector of the southern North Sea. The fields are located about 66 km (41 mi) east of Spurn Head, Lincolnshire. Pickerill was in operation from 1992 until 2018 and Juliet from 2014 to 2018.
The Greater Markham Area gas fields are natural gas reservoirs and gas production facilities that straddled, or are close to, the UK and Netherlands median line of the southern North Sea. The UK field production facilities, which export gas to the Netherlands, began operation in 1992.