Ravenspurn gas fields

Last updated
Ravenspurn gas fields
CountryUnited Kingdom
RegionNorth Sea
Location/blocks42/30, 42/29, 43/26a,
Offshore/onshoreOffshore
Operatorssee text
Ownersee text
Field history
DiscoverySouth 1983, North 1984
Start of productionSouth 1989, North 1990
Production
Producing formationsSandstones

The Ravenspurn gas fields are two adjacent natural gas fields (Ravenspurn South and Ravenspurn North) located in the UK sector of the southern North Sea about 65 km east of Flambrough Head, Yorkshire.

Contents

Ravenspurn North CPP BP Ravenspurn North offshore installation.jpg
Ravenspurn North CPP

The fields

Ravenspurn South is principally located in Block 42/30 and extends into Blocks 42/29 and 43/26a of the southern North Sea. [1] It is named after the drowned village of Ravenspurn. The gas reservoir is a Permian sandstone and has a porosity of 23% and a permeability of 90 md. [2] The field was discovered in April 1983 and has recoverable reserves of 18.0 billion cubic metres. First gas was produced in October 1989. [1]

Ravenspurn North is located in Block 43/26a of the North Sea and extends into Block 42/30. The reservoir is a Lower Leman sandstone of the Rotliegendes group with a variable porosity and permeability. [3] The field was discovered in October 1984 and the recoverable reserves were 35.1 billion cubic metres. First gas was produced in 1990. [1]

Owners and operators

In 1993 Blocks 42/30 and 42/29 (Ravenspurn South) were both licensed to BP Exploration Operating Co. Ltd. (100 %). [1] Block 43/26a (Ravenspurn South and North) was licensed to: ARCO British Ltd. (25.0%), Enterprise Oil plc (20.0%), Hamilton Oil Great Britain plc (15.0%), LASMO Ltd. (15.0%), Hardy Oil and Gas (UK) Ltd. (10.0%), Hamilton Brothers Petroleum (UK) Ltd. (7.5%), Monument Resources Ltd. (7.5%). [1]

Ravenspurn South was developed by BP which remained operator until 2012, when Perenco assumed operatorship. [4]

Ravenspurn North was developed by Hamilton Brothers [1] which remained the operator until 1998 when BP assumed operatorship. In 2012 Perenco acquired BP’s interest and became the operator. [5]

Development

The Ravenspurn South field was developed by BP through three normally unattended offshore platforms Ravenspurn South A, B and C. [6] [7]

Ravenspurn South Platforms
PlatformBlockCoordinatesTypeWater depth, mFunctionInstalledWellheadsFirst gas
Ravenspurn South A42/3054.035833N 0.975000ESteel jacket48Wellheads and production19896October 1989
Ravenspurn South B42/3054.060000N 0.999278ESteel jacket48Wellheads and production198911October 1989
Ravenspurn South C42/3054.086944N 0.829722ESteel jacket48Wellheads and production19895October 1989

On RA and RB the fluids from the wellheads are combined and routed to a 3-phase separator on each platform. [8] Gas from the Separator is routed to the 16-inch pipeline to Cleeton, together with the condensate from the Separator. Separated water is discharged to the sea. On RC there is no separator, well fluids are routed directly by pipeline to Cleeton. [8] The pipeline has a maximum operating pressure of 248.3 bar. In the first year of peak production (1991) the field produced 1.60 billion cubic metres of gas. [1]

Ravenspurn North was developed by Hamilton Brothers as a main manned complex and two satellite platforms ST2 and ST3. [6] [7]

Ravenspurn North Platforms
PlatformBlockCoordinatesTypeWater depth, mFunctionConfigurationInstalled
Ravenspurn North CPP43/26a54.060111N 0.900167EConcrete gravity base45Production and accommodationBridge linked1990
Ravenspurn WT143/26a54.060111N 0.900167ESteel jacket45Wellheads1990
Ravenspurn ST243/26a54.060111N 0.900167ESteel jacket45Wellheads and productionSatellite1990
Ravenspurn ST342/3054.073333N 0.914722ESteel jacket45Wellheads and productionSatellite1990

The Ravenspurn North Central Production Platform (CPP) is a concrete gravity base structure, the only example in the southern North Sea. [9] It is a three leg structure supporting a production and accommodation topside. It is bridge linked to WT1 wellhead platform. [4]

Ravenspurn North CPP Processing

Well fluids from the wellhead tower are routed to one of two 3-phase Separators depending on the pressure of the fluids. [10] High pressure gas from the high pressure HP Separator is dehydrated by counter current contact with glycol in a contact tower. It is then metered and exported to the Cleeton platform by a 24-inch pipeline. The pipeline has a maximum operating pressure of 149 bar and is 28 km long. [6] Gas from the lower pressure LP Separator is routed to a 2-stage 3-train compression train. Compressed gas is dehydrated in a glycol contact tower and mixed with the HP gas prior to the metering skid. Condensate from the separators is collected in the Condensate Separator and from there to the Condensate Coalescer. It is then metered and pumped into the gas export line. Water from the Separators is routed to the oily water coalescer and then discharged overboard. [10]

Fluids from the satellite platforms (ST2 and ST3) are exported to the central complex. Upon arrival they are routed to a slug catcher, gas is routed to the inlet of the appropriate Glycol Contactor. Liquids are routed to the Condensate Separator and then the Condensate Coalescer prior to export through the gas pipeline. [10]

In the first year of peak production (1992) the field produced 3.50 billion cubic metres of gas. [1]

Ravenspurn North also receives fluid from the subsea Johnston field. Upon arrival at RN fluid flows to a slug catcher, gas is routed to the inlet of the appropriate Glycol Contactor. Liquids are routed to the Condensate Separator and then the Condensate Coalescer. [10]

Production

The gas production profile (in million m3) for Ravernspurn North was as follows. [11] The cumulative gas production from the start until the end of 2014 was 28,245 million m3


The gas production profile (in million m3) for Ravernspurn South was as follows. [11] The cumulative gas production from the start until the end of 2014 was 16,796 million m3 .

See also

Related Research Articles

Wytch Farm Oil Field & Processing Facility in Dorset, UK

Wytch Farm is an oil field and processing facility in the Purbeck district of Dorset, England. It is the largest onshore oil field in western Europe. The facility, taken over by Perenco in 2011, was previously operated by BP. It is located in a coniferous forest on Wytch Heath on the southern shore of Poole Harbour, two miles (3.2 km) north of Corfe Castle. Oil and natural gas (methane) are both exported by pipeline; liquefied petroleum gas is exported by road tanker.

The Ninian Central Platform is an oil platform in the North Sea. When constructed in Loch Kishorn, Scotland in 1978 the 600,000 tonne platform was the world's largest man-made movable object before being towed to its current position and sunk to the sea floor.

Clair oilfield

The Clair oilfield is an offshore oil field in Scottish territorial waters 75 kilometres (47 mi) west of Shetland in water depths of up to 140 metres (460 ft). It extends over an area of some 220 square kilometres (85 sq mi), covering five licence blocks.

Everest gasfield

The Everest gasfield is located in the Central North Sea, 233 kilometres (145 mi) east of Aberdeen, Scotland. It lies in the United Kingdom Continental Shelf blocks 22/9, 22/10a and 22/14a. The gasfield was discovered by Amoco in 1982 with first gas produced in 1993. Until 2009, the field was operated by BP. As a result of assets' swap between BP and BG Group in 2009, BG Group became the largest stakeholder of field with 80.46% interest and it took over operatorship of the field. Other partners beside of BG Group are Amerada Hess, and Total. The 1.0134% interest, which was owned by ConocoPhillips, was acquired by BG Group in 2007. On 1 November 2017 Chrysaor announced they had acquired a 100 per cent equity interest in the Everest Field, together with interests in the Beryl, Buzzard, Elgin-Franklin, Erskine, Armada, J Block, Lomond and Schiehallion fields.

Schiehallion oilfield

The Schiehallion oilfield is a deepwater offshore oilfield approximately 175 kilometres (110 mi) west of the Shetland Islands in the North Atlantic Ocean. The Schiehallion and adjacent Loyal field were jointly developed by BP on behalf of the Schiehallion field partners; BP, Shell, Amerada Hess, Murphy Oil, Statoil and OMV, and the Loyal field partners; BP and Shell.

An oil production plant is a facility which processes production fluids from oil wells in order to separate out key components and prepare them for export. Typical oil well production fluids are a mixture of oil, gas and produced water. An oil production plant is distinct from an oil depot, which does not have processing facilities.

The Eastern Trough Area Project, commonly known as ETAP, is a network of nine smaller oil and gas fields in the Central North Sea covering an area up to 35 km in diameter. There are a total of nine different fields, six operated by BP and another three operated by Shell, and together, they are a rich mix of geology, chemistry, technology and equity arrangements.

Andrew oilfield

The Andrew oilfield is a relatively small hydrocarbon field in the UK sector of the North Sea, 230 kilometres (140 mi) North-East of Aberdeen and it is operated by BP. It is produced from a single platform, which is also the hub of the Kinnoull, Cyrus and Farragon subsea developments.

The Easington Catchment Area is a group of natural gas producing fields in the Southern North Sea. They lie in UK Blocks 42 and 47 between 25 and 30 miles east of the Yorkshire and Lincolnshire coast. The fields are operated by Perenco.

Central Area Transmission System

The Central Area Transmission System is a natural gas transportation and processing system that transports natural gas through a 404 kilometre pipeline from the Central North Sea to a reception and processing terminal at Teesside in the North East of England.

Easington Gas Terminal

The Easington Gas Terminal is one of six main gas terminals in the UK, and is situated on the North Sea coast at Easington, East Riding of Yorkshire and Dimlington. The other main gas terminals are at St Fergus, Aberdeenshire; Bacton, Norfolk; Teesside; Theddlethorpe, Lincolnshire and Rampside gas terminal, Barrow, Cumbria. The whole site consists of four plants: two run by Perenco, one by Centrica and one by Gassco. The Easington Gas Terminals are protected by Ministry of Defence Police officers and are provided with resources by the Centre for the Protection of National Infrastructure.

Bacton Gas Terminal

The Bacton Gas Terminal is a complex of six gas terminals within four sites located on the North Sea coast of North Norfolk in the United Kingdom. The sites are near Paston and between Bacton and Mundesley; the nearest town is North Walsham.

Perenco is an independent Anglo-French oil and gas company with a headquarters in London and Paris. It conducts exploration and production activities in 16 countries around the globe.

Tyra Field

Tyra Field is the largest gas condensate field in the Danish Sector of the North Sea. It was discovered in 1968 and production started in 1984. The field is owned by Dansk Undergrunds Consortium, a partnership between Total, Noreco and Nordsofonden, and operated by Total. The reservoir depth is about 2,000 metres (6,600 ft) and it covers area of 90 kilometres (56 mi) in the water depth of 37–40 metres (121–131 ft).

The Leman gas field is a natural gas field located in the North Sea.The field is 30 miles (48 km) north-east of Great Yarmouth and is named after the Leman Sandbank beneath which it is situated. The gas reservoir is an 800 ft (240 m) thick Rotliegendes sandstone reservoir at a depth of about 6,000 ft (1830 m). It is about 18 miles (29 km) long by 5 miles (8 km) wide. It was discovered in August 1966 and extends across two blocks. Block 49/26 is licensed to Shell and Block 49/27 was originally licensed to the Amoco-Gas Council joint venture, Block 49/27 is now licensed to Perenco UK Ltd. The field was discovered in 1966 and began production in 1968 and produces natural gas and condensates to the Bacton Gas Terminal on the coast of Norfolk via several pipeline systems. The total proven reserves of the Leman gas field are around 11 trillion cubic feet (316 km³), and production is slated to be around 200 million cubic feet/day (5.7×105m³).

Alwyn North is a major oil and gas field in the United Kingdom sector of the northern North Sea, 160 km west of the Shetland Islands. The field was developed through two bridge-linked offshore platforms and a number of subsea satellite wellheads. Alwyn North has been producing oil and gas since 1987 and is still (2021) in operation.

The Heather oil field is a significant crude oil producing field in the UK sector of the northern North Sea, 458 km north-north-east of Aberdeen. Production of oil started in 1978 and ceased in 2019, the Heather Alpha installation is currently (2021) undergoing decommissioning.

The Clyde oil field is a crude oil producing field in the UK sector of the North Sea, 290 km east-south-east of Aberdeen. Production of oil started in 1987 and the field is still operational (2021).

Esmond, Forbes and Gordon are three adjacent, now depleted, natural gas fields in the southern North Sea, 170 km east of Teesside.

The Morecambe gas fields are two major natural gas producing fields in Morecambe Bay in the Irish Sea, 27 km west of Blackpool.

References

  1. 1 2 3 4 5 6 7 8 Department of Trade and Industry (1994). The Energy Report. London: HMSO. pp. 80–81. ISBN   0115153802.
  2. "Ravenspurn South Field, Blocks 42/29, 42/30, 43/26, UK North Sea". lyellcollection.org. 1991. Retrieved 30 October 2021.
  3. "The Ravenspurn North Field, Blocks 42/30, 43/26a, UK North Sea" . Retrieved 30 October 2021.
  4. 1 2 "Perenco UK SNS- Environmental Statement 2019" (PDF).
  5. "Ravenspurn North Field".
  6. 1 2 3 Southern North Sea Gas Installations Schematic (2005)
  7. 1 2 "OSPAR Offshore Installations Inventory" . Retrieved 30 October 2021.
  8. 1 2 Ravenspurn South Process Flow Diagrams, BP (2001)
  9. "Arup Journal Autumn 1989" (PDF).
  10. 1 2 3 4 Ravenspurn North Simplified Flow Diagrams, BP (2003)
  11. 1 2 "Oil and gas field data" . Retrieved 22 November 2021.