Sumpter v Hedges

Last updated

Sumpter v Hedges
MuensterRathausRatsstall1900.jpg
CourtCourt of Appeal
Decided18 March 1898
Citation[1898] 1 QB 673, 67 LJQB 545, 46 WR 454, 42 Sol Jo 362, 78 LT 378
Case opinions
AL Smith LJ, Chitty LJ and Collins LJ
Keywords
quantum meruit, entire obligation, restitution for unjust enrichment, substantial performance

Sumpter v Hedges [1898] 1 QB 673 is an English contract law case concerning substantial performance of a contract and restitution for unjust enrichment.

Contents

Facts

Mr Sumpter was a builder. He had a contract to build two houses and stables for Mr Hedges for £560. He did work valued at £333 and said he had to stop because he had no more money. Substantial payments on account have in fact been made to the builder. Hedges finished the building, using materials which Sumpter had left behind. Sumpter sued for the outstanding money.

Bruce J found that Mr Sumpter had abandoned the contract, and said he could obtain money for the value of the materials but nothing for the work.

Judgment

The Court of Appeal found that Mr Sumpter had abandoned the building work and emphasised that it left Mr Hedges without any choice of whether to adopt the work. It held that Mr Hedges had to pay for the building materials that he used, but did not need to reimburse Mr Sumpter for the half-built structures. AL Smith LJ gave the leading judgment:

In this case the plaintiff, a builder, entered into a contract to build two houses and stables on the defendant's land for a lump sum. When the buildings were still in an unfinished state the plaintiff informed the defendant that he had no money, and was not going on with the work any more. The learned judge has found as a fact that he abandoned the contract. Under such circumstances, what is a building owner to do? He cannot keep the buildings on his land in an unfinished state for ever. The law is that, where there is a contract to do work for a lump sum, until the work is completed the price of it cannot be recovered. Therefore the plaintiff could not recover on the original contract. It is suggested however that the plaintiff was entitled to recover for the work he did on a quantum meruit . But, so that may be, there must be evidence of a fresh contract to pay for the work already done. With regard to that, the case of Munro v Butt [1] appears to be exactly in point. That case decides that, unless the building owner does something from which a new contract can be inferred to pay for the work already done, the plaintiff in such a case as this cannot recover on a quantum meruit. In the case of Lysaght v Pearson , [2] to which we have been referred, the case of Munro v Butt [3] does not appear to have been referred to. There the plaintiff had contracted to erect on the defendant's land two corrugated iron roofs. When he had completed one of them, he does not seem to have said that he abandoned the contract, but merely that he would not go on unless the defendant paid him for what he had already done. The defendant thereupon proceeded to erect for himself the second roof. The Court of Appeal held that there was in that case something from which a new contract might be inferred to pay for the work done by the plaintiff. That is not this case. In the case of Whitaker v Dunn [4] there was a contract to erect a laundry on defendant's land, and the laundry erected was not in accordance with the contract, but the official referee held that the plaintiff could recover on a quantum meruit. The case came before a Divisional Court, consisting of Lord Coleridge CJ and myself, and we said that the decision in Munro v Butt [5] applied, and there being no circumstances to justify an inference of a fresh contract the plaintiff must fail. My brother Collins thinks that that case went to the Court of Appeal, and that he argued it there, and the Court affirmed the decision of the Queen's Bench Division. I think the appeal must be dismissed.

Chitty LJ concurred.

I am of the same opinion. The plaintiff had contracted to erect certain buildings for a lump sum. When the work was only partly done, the plaintiff said that he could not go on with it, and the judge has found that he abandoned the contract. The position therefore was that the defendant found his land with unfinished buildings upon it, and he thereupon completed the work. That is no evidence from which the inference can be drawn that he entered into a fresh contract to pay for the work done by the plaintiff. If we held that the plaintiff could recover, we should in my opinion be overruling Cutter v Powell , [6] and a long series of cases in which it has been decided that there must in such a case be some evidence of a new contract to enable the plaintiff to recover on a quantum meruit . There was nothing new in the decision in Pattinson v Luckley , [7] but Bramwell B. there pointed out with his usual clearness that in the case of a building erected upon land the mere fact that the defendant remains in possession of his land is no evidence upon which an inference of a new contract can be founded. He says: “In the case of goods sold and delivered, it is easy to shew a contract from the retention of the goods; but that is not so where work is done on real property.” I think the learned judge was quite right in holding that in this case there was no evidence from which a fresh contract to pay for the work done could be inferred.

Collins LJ concurred.

I agree. I think the case is really concluded by the finding of the learned judge to the effect that the plaintiff had abandoned the contract. If the plaintiff had merely broken his contract in some way so as not to give the defendant the right to treat him as having abandoned the contract, and the defendant had then proceeded to finish the work himself, the plaintiff might perhaps have been entitled to sue on a quantum meruit on the ground that the defendant had taken the benefit of the work done. But that is not the present case. There are cases in which, though the plaintiff has abandoned the performance of a contract, it is possible for him to raise the inference of a new contract to pay for the work done on a quantum meruit from the defendant's having taken the benefit of that work, but, so that may be done, the circumstances must be such as to give an option to the defendant to take or not to take the benefit of the work done. It is only where the circumstances are such as to give that option that there is any evidence on which to ground the inference of a new contract. Where, as in the case of work done on land, the circumstances are such as to give the defendant no option whether he will take the benefit of the work or not, then one must look to other facts than the mere taking the benefit of the work to ground the inference of a new contract. In this case I see no other facts on which such an inference can be founded. The mere fact that a defendant is in possession of what he cannot help keeping, or even has done work upon it, affords no ground for such an inference. He is not bound to keep unfinished a building which in an incomplete state would be a nuisance on his land. I am therefore of opinion that the plaintiff was not entitled to recover for the work which he had done. I feel clear that the case of Whitaker v Dunn , [8] to which reference has been made, was the case which as counsel I argued in the Court of Appeal, and in which the Court dismissed the appeal on the ground that the case was concluded by Munro v Butt . [9]

See also

Related Research Articles

A quasi-contract is a fictional contract recognised by a court. The notion of a quasi-contract can be traced to Roman law and is still a concept used in some modern legal systems. Quasi contract laws have been deduced from the Latin statement "Nemo debet locupletari ex aliena iactura", which proclaims that no one should grow rich out of another person's loss. It was one of the central doctrines of Roman law.

<i>Quantum meruit</i> Latin Phrase

Quantum meruit is a Latin phrase meaning "what one has earned". In the context of contract law, it means something along the lines of "reasonable value of services".

Restitution and unjust enrichment is the field of law relating to gains-based recovery. In contrast with damages, restitution is a claim or remedy requiring a defendant to give up benefits wrongfully obtained. Liability for restitution is primarily governed by the "principle of unjust enrichment": A person who has been unjustly enriched at the expense of another is required to make restitution.

Assumpsit, or more fully, action in assumpsit, was a form of action at common law used to enforce what are now called obligations arising in tort and contract; and in some common law jurisdictions, unjust enrichment. The origins of the action can be traced to the 14th century, when litigants seeking justice in the royal courts turned from the writs of covenant and debt to the trespass on the case.

Damages for breach of contract is a common law remedy, available as of right. It is designed to compensate the victim for their actual loss as a result of the wrongdoer’s breach rather than to punish the wrongdoer. If no loss has been occasioned by the plaintiff, only nominal damages will be awarded.

Peevyhouse v. Garland Coal & Mining Co., 382 P.2d 109, is a US contract law case decided by the Supreme Court of Oklahoma. It concerns the question of when specific performance of a contractual obligation will be granted and the measure of expectation damages.

The English law of unjust enrichment is part of the English law of obligations, along with the law of contract, tort, and trusts. The law of unjust enrichment deals with circumstances in which one person is required to make restitution of a benefit acquired at the expense of another in circumstances which are unjust.

<span class="mw-page-title-main">Baltic Shipping Company v Dillon</span> Judgement of the High Court of Australia

Baltic Shipping Company v Dillon, the Mikhail Lermontov case, is a leading Australian contract law case, on the incorporation of exclusion clauses and damages for breach of contract or restitution for unjust enrichment.

<i>Cutter v Powell</i> English contract law case

Cutter v Powell (1795) 101 ER 573 is an English contract law case, concerning substantial performance of a contract.

<i>Addis v Gramophone Co Ltd</i>

Addis v Gramophone Co Ltd [1909] AC 488 is an old English contract law and UK labour law case, which used to restrict damages for non-pecuniary losses for breach of contract.

<i>Wilson v Racher</i> UK labour law case concerning constructive dismissal

Wilson v Racher [1974] ICR 428 is a UK labour law case concerning constructive dismissal. It serves as an example of an employer being found to have wrongfully dismissed an employee, because of the employer's own bad behaviour. Edmund-Davies LJ also made an important statement about the modern employment relationship,

What would today be regarded as almost an attitude of Czar-serf, which is to be found in some of the older cases where a dismissed employee failed to recover damages, would, I venture to think, be decided differently today. We have by now come to realise that a contract of service imposes upon the parties a duty of mutual respect.

<i>Williams v Natural Life Health Foods Ltd</i>

Williams v Natural Life Health Foods Ltd[1998] UKHL 17 is an important English tort law, company law and contract law case. It held that for there to be an effective assumption of responsibility, there must be some direct or indirect conveyance that a director had done so, and that a claimant had relied on the information. Otherwise only a company itself, as a separate legal person, would be liable for negligent information.

<i>Guinness plc v Saunders</i>

Guinness plc v Saunders [1989] UKHL 2 is a UK company law case, regarding the power of the company to pay directors. It required that whatever rules exist for payment in the company's articles, they must be strictly observed.

BP Exploration Co (Libya) v Hunt [1983] 2 AC 352 is an English contract and unjust enrichment case, concerning the frustration of an agreement.

British Steel Corp v Cleveland Bridge and Engineering Co Ltd [1984] 1 All ER 504 is an English contract law case concerning agreement.

<i>Pavey & Matthews Pty Ltd v Paul</i> Judgement of the High Court of Australia

Pavey & Matthews Pty Ltd v Paul, is a leading Australian case concerning unjust enrichment, and an award for restitution based on quantum meruit.

<i>Benedetti v Sawiris</i>

Benedetti v Sawiris[2013] UKSC 50 is an English unjust enrichment law case, concerning the method for determining the amount of a quantum meruit claim. It was decided by the United Kingdom Supreme Court.

Quantum valebant is a Latin phrase meaning "as much as they were worth". It is sometimes used in its singular form, quantum valebat, meaning “as much as it was worth". It is a common count at law very similar to quantum meruit. The two legal actions differ only in that quantum meruit is used to recover the reasonable value of services rendered, while quantum valebant is used to recover the reasonable value of goods sold and delivered. This count is considered a type of assumpsit.

<i>Miles v Wakefield Metropolitan District Council</i>

Miles v Wakefield Metropolitan District Council[1987] UKHL 15 is a UK labour law case, concerning the theory of partial performance and strike action. Its authority has been questioned since.

Nash v Inman was a 1908 court case heard in the King's Bench. It concerned a minor's capacity to make contracts under English law.

References

  1. 8 E&B 738
  2. Not reported, except in the Times Newspaper of March 3, 1879
  3. 8 E&B 738
  4. 3 Times LR 602
  5. 8 E&B 738
  6. (1795) 6 TR 320
  7. (1875) LR 10 Ex 330
  8. 3 Times LR 602
  9. 8 E&B 738