The Warwickslade Cutting Railway was a light railway temporarily built to fill in the Warwickslade Cutting, a straight drainage ditch dug circa 1850 in the New Forest of south-east England, with imported gravel and clay. In 2009, the Forestry Commission decided to obliterate it and replace it by a more natural meandering stream. [1]
The reason for the works was that Warwickslade Lawn Site of Special Scientific Interest (SSSI) was "in an unfavourable declining condition because the artificially deepened cutting meant that there was no seasonal inundation of the grassland and woodland habitats". [2] Surprisingly, much of the course of the original, pre-1850s, stream could still be seen on the ground. The aim of the works was to reinstate the original stream as closely as possible, whilst filling in the Cutting. It was necessary to bring in 10,000 tonnes of hoggin to fill in the cutting, plus some clay to make plugs to ensure that water followed the desired course. [3]
The contractors were Alaska Environmental Contracting. [4] They used 8, 13 and 18 tonne hydraulic excavators, 10 tonne rubber tracked dumper trucks and an innovative light railway.
To bring in 10,000 tonnes of hoggin would have required 1,000 round trips for a Morooka MST-2200vd tracked dumper truck. [5] The contractors Alaska designed and built an experimental light railway from a forest track to the cutting. By this they reduced the compaction of the soil of the forest by eliminating heavy dumper movements. This allowed work to continue even in wet weather. It also resulted in lower fuel consumption and less noise and pollution. [6] The project cost of £214,500 included plant hire and labour (£106,500) and infill materials (£108,000). [7]
The track laying began on 2 September 2009 along a wide, grassy forest track. The track consisted of circular steel pipe of about 6mm wall thickness, welded to steel cross members which were in turn bolted to wooden sleepers. One side was fitted with a steel spike to engage with the next section. Thus, it fitted together very much like a toy railway, using preassembled track sections which are either straight or of fixed curvature. [1] The track laying operation looked a bit like a child’s train set on a large scale. The rails, with sleepers ready attached, came in sections - straight or curved to suit their position. The tube and pin joints fitted together exactly as do the rail sections of the toy set. [6]
The purpose of the railway was to reduce the environmental impact of bringing so much material on site. The Morooka dumper truck has an engine of 250 HP whereas Alaska thought that they could shift the same 10 tonnes of gravel in a train powered by a Boxer 532DX mini-skid, a tracked vehicle running on the rails, which has a 32 HP engine. Thus the emissions savings would be substantial. There ought also to be less surface damage. [1] The railtrack had a calculated ground pressure, when loaded by a train carrying a load of 10 tonnes, of under 3 psi, to avoid the sleepers sinking into the occasionally very wet ground. [8] Therefore, no ballast was needed.
The bolts securing the rail to its sleepers have pulled out of the wood occasionally, especially where the Boxer had derailed. This was caused by the weight of the tracked Boxer locomotive pushing down upon the sleepers at a point where they were not well supported. Some of the weight of the Boxer is normally borne by the rails, via its rear steel wheels. [9] Some sleepers disintegrated during the use and some sections needed to be supported by broken branches rammed into cavities under the track. However, as the trains moved slowly, nobody was hurt in occasional derailments and little damage was done. [6] At the conclusion of the drain in-filling, the rail tracks were removed. [10] The project was successfully completed on 19 November 2009. [11]
Two trains consisted of white-painted trucks each coupled together. Each 10 tonne train consisted of 10 trucks each taking 1 tonne. [12] The locomotive was the modified Boxer 532DX mini-skid upon which the driver stood, either pushing or pulling the coupled trucks. The trucks had plastic wheels designed either to ride along the cylindrical track or along a flat surface. The wheels had needle roller bearings. The Boxer obtained traction by means of its rubber track bearing upon the sleepers, but at the rear it had two wheels riding upon the track, the height of which could be adjusted hydraulically. They could also be raised to free the Boxer from the track whilst it was negotiating points.
The two trains operated from a newly constructed depot in Vinney Ridge, where points allowed the diversion of one train into a siding. There it was loaded while the other travelled up to a mile southwards towards Brockenhurst where the track runs parallel to the stream. Then a heavy excavator lifted the containers from the bogies, tipped their content into the ditch and placed them back empty onto the train with virtually no sideways movement. [6]
A bogie is a chassis or framework that carries a wheelset, attached to a vehicle—a modular subassembly of wheels and axles. Bogies take various forms in various modes of transport. A bogie may remain normally attached or be quickly detachable ; it may contain a suspension within it, or be solid and in turn be suspended ; it may be mounted on a swivel, as traditionally on a railway carriage or locomotive, additionally jointed and sprung, or held in place by other means.
Wagonways consisted of the horses, equipment and tracks used for hauling wagons, which preceded steam-powered railways. The terms plateway, tramway and dramway were used. The advantage of wagonways was that far bigger loads could be transported with the same power.
A railroad switch (AE), turnout, or [set of] points (BE) is a mechanical installation enabling railway trains to be guided from one track to another, such as at a railway junction or where a spur or siding branches off.
A railway track or railroad track, also known as permanent way or simply track, is the structure on a railway or railroad consisting of the rails, fasteners, railroad ties and ballast, plus the underlying subgrade. It enables trains to move by providing a dependable surface for their wheels to roll upon. Tracks where electric trains or electric trams run are equipped with an electrification system such as an overhead electrical power line or an additional electrified rail. Early tracks were constructed with wooden or cast iron rails, and wooden or stone sleepers; since the 1870s, rails have almost universally been made from steel.
The railway track or permanent way is the elements of railway lines: generally the pairs of rails typically laid on the sleepers or ties embedded in ballast, intended to carry the ordinary trains of a railway. It is described as permanent way because in the earlier days of railway construction, contractors often laid a temporary track to transport spoil and materials about the site; when this work was substantially completed, the temporary track was taken up and the permanent way installed.
A loader is a heavy equipment machine used in construction to move or load materials such as soil, rock, sand, demolition debris, etc. into or onto another type of machinery.
In railroading, a derailment occurs when a rail vehicle such as a train comes off its rails. Although many derailments are minor, all result in temporary disruption of the proper operation of the railway system and they are a potentially serious hazard.
The axle load of a wheeled vehicle is the total weight bearing on the roadway for all wheels connected to a given axle. Axle load is an important design consideration in the engineering of roadways and railways, as both are designed to tolerate a maximum weight-per-axle ; exceeding the maximum rated axle load will cause damage to the roadway or rail tracks.
The Peak Forest Tramway was an early horse- and gravity-powered industrial railway system in Derbyshire, England. Opened for trade on 31 August 1796, it remained in operation until the 1920s. Much of the route and the structures associated with the line remain. The western section of the line is now the route of the Peak Forest Tramway Trail.
A road–rail vehicle is a dual-mode vehicle which can operate both on rail tracks and a conventional road. They are also called hi-rail, from highway and railway, or variations such as high-rail, HiRail, Hy-rail, etc.
Mighty Machines is a Canadian children's television series about machines and how they work. It was nominated for a Gemini Award in 1996 in the category of Best Children's Program or Series. The series premiered in 1994 before ending its run in 2008, airing 39 episodes over 3 seasons.
Tramway track is used on tramways or light rail operations. Grooved rails are often used to provide a protective flangeway in the trackwork in city streets. Like standard rail tracks, tram tracks consist of two parallel steel rails.
A tamping machine or ballast tamper, informally simply a tamper, is a self-propelled, rail-mounted machine used to pack the track ballast under railway tracks to make the tracks and roadbed more durable and level. Prior to the introduction of mechanical tampers, this task was done by manual labour with the help of beaters. As well as being faster, more accurate, more efficient and less labour-intensive, tamping machines are essential for the use of concrete sleepers since they are too heavy to be lifted by hand.
The rail profile is the cross sectional shape of a railway rail, perpendicular to its length.
A concrete sleeper or concrete tie is a type of railway sleeper or railroad tie made out of steel reinforced concrete.
Baulk road is the name given to a type of railway track or 'rail road' that is formed using rails carried on continuous timber bearings, as opposed to the more familiar 'cross-sleeper' track that uses closely spaced sleepers or ties to give intermittent support to stronger rails.
The Research Designs & Standards Organisation (RDSO) is an ISO 9001 research and development organisation under the Ministry of Railways of government of India, which functions as a technical adviser and consultant to the Railway Board, the Zonal Railways, the Railway Production Units, RITES, RailTel and Ircon International in respect of design and standardization of railway equipment and problems related to railway construction, operations and maintenance.
Ladder track is a type of railway track in which the track is laid on longitudinal supports with transverse connectors holding the two rails at the correct gauge distance. Modern ladder track can be considered a development of baulk road, which supported rails on longitudinal wooden sleepers. Synonyms include longitudinal beam track.
The South African Railways Dutton road-rail tractors of 1923 were road-rail steam tractors.
The Spalding railway was a German narrow gauge railway system invented, patented and developed by Heinrich Andreas Spalding in 1884 for forestry and agriculture applications. It was similar to the Decauville railway, which had been invented and patented in France eight years earlier.
Wikimedia Commons has media related to Warwickslade Cutting railway . |