Gorgon Carbon Dioxide Injection Project

Last updated

The Gorgon Carbon Dioxide Injection Project is part of the Gorgon Project, one of the world's largest natural gas projects. [1] The Gorgon Project, located on Barrow Island in Western Australia, includes a liquefied natural gas (LNG) plant, a domestic gas plant, and a Carbon Dioxide Injection Project.

Contents

Carbon dioxide injections commenced in 2019. [2] Once operating at full capacity, the Gorgon Carbon Dioxide Injection Project will be the world's largest CO2 injection plant, with an ability to store up to 4 million tons of CO2 per year – approximately 120 million tons over the project's lifetime, and 40 percent of total Gorgon Project emissions. [3]

Technology

Gas is supplied from two world-class gas fields namely, Gorgon field that contains on average 14% of naturally occurring reservoir CO2, and Jansz-lo field that contains less than 1% CO2. [3] Reservoir CO2 is extracted from natural gas as a part of normal gas-processing operations. During the liquefaction process, natural gas is cooled to -162 °C. CO2 freezes above this temperature, so it needs to be separated from the natural gas stream prior to gas processing and liquefaction. Separation is performed using a basic absorber and stripper system and an amine-based solvent. [3]

The Gorgon Carbon Dioxide Injection Project will compress and pipe separated CO2 to nine injection wells where it will be subsequently injected into the Dupuy Formation. [3] Once the CO2 is injected, it will migrate through the Dupuy Formation until it remains trapped. The top of the Dupuy Formation reservoir is located approximately 2300 m below Barrow Island and is overlain by a thick shale cap-rock seal. [3] The pressure in the reservoir will cause the injected CO2 to behave as a supercritical fluid with behavior of both a liquid and a gas. The reservoir CO2 will become trapped in the reservoir through a combination of residual saturation trapping and by dissolution into the waters in the formation.

Environmental impacts

The carbon dioxide injection plant is located on Barrow Island, a Class A nature reserve. Therefore, the development of the processing plant had to undergo very strict environmental regulations. [4] The Joint Venture established expert panels to protect the biodiversity of the island and surrounding marine environment. To ensure that the Dupuy Formation was suitable for underground injection of reservoir carbon dioxide, the Gorgon Joint Venture undertook additional drilling, well tests, and seismic surveys prior to making the final investment decision. [5] An ongoing monitoring program, including observation wells and seismic surveys, will assist in managing the performance of the injected carbon dioxide in the Dupuy Formation.

History and criticism

This project, led by Chevron, has been designed to capture 3.5 Mt of carbon dioxide per annum from Greater Gorgon gas fields and store it in the Dupuy formation beneath the Barrow Island. Upon completion, the project will be the largest carbon dioxide sequestration operation in the world. [6] Chevron is liable for leaks and other damage during the project's lifetime and for 15 years afterwards, [6] but in 2009 the state and federal governments agreed to indemnify Chevron against liability for the project after that time, [7] with the Commonwealth in 2015 confirming it would adopt 80% of the liability and WA the remaining 20%. [8]

When construction on the project began in 2009, it was expected to be completed by 2014 [9] - including carbon capture and storage. [6] The project ultimately started extracting gas in February 2017 but carbon capture and storage was delayed multiple times. A delay until March 2019 [10] resulted in a further five million tonnes of CO2 to be released, because:

A Chevron report to the State Government released yesterday said start-up checks this year found leaking valves, valves that could corrode and excess water in the pipeline from the LNG plant to the injection wells that could cause the pipeline to corrode. [11]

In May 2018, the WA Environmental Protection Authority announced an investigation into whether Gorgon could meet its storage commitments given the delays. [12] In March 2019, Chevron announced that carbon capture and storage was delayed by another nine months, which would result in the release of a further 7.9 to 11.1 million tonnes of CO2. [13]

WWF claims that the Gorgon geosequestration project is potentially unsafe as the area has over 700 wells drilled in the area, 50 of which reach the area proposed for geosequestration of CO2. Fault lines compound the problems. Barrow Island is also an A class nature reserve of global importance. [14]

Related Research Articles

<span class="mw-page-title-main">Liquefied natural gas</span> Form of natural gas for easier storage and transport

Liquefied natural gas (LNG) is natural gas (predominantly methane, CH4, with some mixture of ethane, C2H6) that has been cooled down to liquid form for ease and safety of non-pressurized storage or transport. It takes up about 1/600th the volume of natural gas in the gaseous state at standard conditions for temperature and pressure.

<span class="mw-page-title-main">Snøhvit</span>

Snøhvit(English: Snow White) is the name of a natural gas field in the Norwegian Sea, situated 140 kilometres (87 mi) northwest of Hammerfest, Norway. The northern part of the Norwegian Sea is often described as the Barents Sea by offshore petroleum companies. Snøhvit is also the name of a development of Snøhvit and the two neighbouring natural gas fields Albatross and Askeladden. Estimated recoverable reserves are 193 billion cubic metres of natural gas, 113 million barrels of condensate, and 5.1 million tonnes of natural gas liquids (NGL). The development comprises 21 wells. The Snøhvit development is operated by Equinor on behalf of six gas companies owning licenses:

<span class="mw-page-title-main">Coal pollution mitigation</span>

Coal pollution mitigation, sometimes labeled as clean coal, is a series of systems and technologies that seek to mitigate health and environmental impact of burning coal for energy. Burning coal releases harmful substances that contribute to air pollution, acid rain, and greenhouse gas emissions. Mitigation includes precombustion approaches, such as cleaning coal, and post combustion approaches, include flue-gas desulfurization, selective catalytic reduction, electrostatic precipitators, and fly ash reduction. These measures aim to reduce coal's impact on human health and the environment.

<span class="mw-page-title-main">Carbon capture and storage</span> Collecting carbon dioxide from industrial emissions

Carbon capture and storage (CCS) is a process in which a relatively pure stream of carbon dioxide (CO2) from industrial sources is separated, treated and transported to a long-term storage location. For example, the burning of fossil fuels or biomass results in a stream of CO2 that could be captured and stored by CCS. Usually the CO2 is captured from large point sources, such as a chemical plant or a bioenergy plant, and then stored in a suitable geological formation. The aim is to reduce greenhouse gas emissions and thus mitigate climate change. For example, CCS retrofits for existing power plants can be one of the ways to limit emissions from the electricity sector and meet the Paris Agreement goals.

Enhanced oil recovery, also called tertiary recovery, is the extraction of crude oil from an oil field that cannot be extracted otherwise. Although the primary and secondary recovery techniques rely on the pressure differential between the surface and the underground well, enhanced oil recovery functions by altering the chemical composition of the oil itself in order to make it easier to extract. EOR can extract 30% to 60% or more of a reservoir's oil, compared to 20% to 40% using primary and secondary recovery. According to the US Department of Energy, carbon dioxide and water are injected along with one of three EOR techniques: thermal injection, gas injection, and chemical injection. More advanced, speculative EOR techniques are sometimes called quaternary recovery.

Carbon dioxide (CO2) flooding is a process in which carbon dioxide is injected into an oil reservoir to increase the output when extracting oil. This is most often used in reservoirs where production rates have declined due to depletion.

<span class="mw-page-title-main">Sleipner gas field</span> North Sea off Norway

The Sleipner gas field is a natural gas field in the block 15/9 of the North Sea, about 250 kilometres (160 mi) west of Stavanger, Norway. Two parts of the field are in production, Sleipner West, and Sleipner East (1981). The field produces natural gas and light oil condensates from sandstone structures about 2,500 metres (8,200 ft) below sea level. It is operated by Equinor. The field is named after the steed Sleipnir in Norse mythology.

Carbon capture and storage (CCS) is a technology that can capture carbon dioxide CO2 emissions produced from fossil fuels in electricity, industrial processes which prevents CO2 from entering the atmosphere. Carbon capture and storage is also used to sequester CO2 filtered out of natural gas from certain natural gas fields. While typically the CO2 has no value after being stored, Enhanced Oil Recovery uses CO2 to increase yield from declining oil fields.

<span class="mw-page-title-main">Gorgon gas project</span>

The Gorgon gas project is a multi-decade natural gas project in Western Australia, involving the development of the Greater Gorgon gas fields, subsea gas-gathering infrastructure, and a liquefied natural gas (LNG) plant on Barrow Island. The project also includes a domestic gas component. Construction was completed in 2017.

<span class="mw-page-title-main">Petroleum industry in Western Australia</span> Overview of WA energy sector

The petroleum industry in Western Australia is the largest contributor to the country's petroleum exports. Western Australia's North West Shelf (NWS) is the primary location from which production originates. Oil exports are shipped from Port Hedland.

The milestones for carbon capture and storage show the lack of commercial scale development and implementation of CCS over the years since the first carbon tax was imposed.

<span class="mw-page-title-main">Boundary Dam Power Station</span> Power station in Saskatchewan, Canada

Boundary Dam Power Station is the largest coal fired station owned by SaskPower, located near Estevan, Saskatchewan, Canada.

The Weyburn-Midale Carbon Dioxide Project was, as of 2008, the world's largest carbon capture and storage project. It has since been overtaken in terms of carbon capture capacity by projects such as the Shute Creek project and the Century Plant. It is located in Midale, Saskatchewan, Canada.

Carbfix is an Icelandic company that has developed an approach to capturing and storing CO2 in water, and its injection into subsurface basalts. Once in the subsurface, the injected CO2 reacts with the host rock forming stable carbonate minerals, thus providing storage of the captured gas.

<span class="mw-page-title-main">Petra Nova</span> Discontinued Texas, U.S.A. carbon-capture project

Petra Nova is a carbon capture project designed to reduce carbon emissions from one of the boilers of a coal burning power plant in Thompsons, Texas. It is a multi-million dollar project taken up by NRG Energy and JX Nippon Oil to retrofit one of the boilers at their WA Parish Generating Station with a post-combustion carbon capture treatment system to treat a portion of the atmospheric exhaust emissions from the retrofitted boiler.

Direct deep-sea carbon dioxide injection was a (now abandoned) technology proposal with the aim to remove carbon dioxide from the atmosphere by direct injection into the deep ocean to store it there for centuries. At the ocean bottom, the pressures would be great enough for CO2 to be in its liquid phase. The idea behind ocean injection was to have stable, stationary pools of CO2 at the ocean floor. The ocean could potentially hold over a thousand billion tons of CO2. However, the interest in this avenue of carbon storage has much reduced since about 2001 because of concerns about the unknown impacts on marine life, high costs and concerns about its stability or permanence.

<span class="mw-page-title-main">Carbon capture and utilization</span>

Carbon capture and utilization (CCU) is the process of capturing carbon dioxide (CO2) from industrial processes and transporting it via pipelines to where one intends to use it in industrial processes.

<span class="mw-page-title-main">Direct air capture</span> Method of carbon capture from carbon dioxide in air

Direct air capture (DAC) is the use of chemical or physical processes to extract carbon dioxide directly from the ambient air. If the extracted CO2 is then sequestered in safe long-term storage, the overall process will achieve carbon dioxide removal and be a "negative emissions technology" (NET).

<span class="mw-page-title-main">Carbon storage in the North Sea</span> Storage of carbon dioxide in the North Sea

Carbon storage in the North Sea includes programmes being run by several Northern European countries to capture carbon, and store it under the North Sea in either old oil and gas workings, or within saline aquifers. Whilst there have been some moves to international co-operation, most of the Carbon Capture and Storage (CCS) programmes are governed by the laws of the country that is running them. Because the governments have pledged net zero carbon emissions by 2050, they have to find ways to deal with any remaining CO2 produced, such as by heavy industry. Around 90% of the identified storage geologies for carbon dioxide in Europe are shared between Norway and the United Kingdom; all of the designated sites for storage are located in the North Sea.

References

  1. "Gorgon Project Business Overview". www.chevronaustralia.com. Retrieved 2020-10-27.
  2. "World leading CO2 injection project starts operations". www.minister.industry.gov.au. Retrieved 2020-10-27.
  3. 1 2 3 4 5 "Carbon Dioxide Injection | Environmental Responsibility | Gorgon | Our Businesses | Chevron Australia". www.chevronaustralia.com. Retrieved 2017-04-28.
  4. Treadgold, Tim. "Chevron Pays To Keep Workers Quiet At Its Gorgon LNG Project". Forbes. Retrieved 2017-04-28.
  5. "SITE SELECTION ‐ GORGON CARBON DIOXIDE INJECTION PROJECT" (PDF).
  6. 1 2 3 Kemp, John (2013-09-10). "World's largest carbon capture begins even as Abbott tax repeal looms". The Sydney Morning Herald. Retrieved 2018-06-21.
  7. "WA and Commonwealth to share Gorgon load". WAtoday. 2009-08-17. Retrieved 2018-06-21.
  8. "Barrow Island Amendment Bill 2015: Second reading speech" (PDF).
  9. "The day disaster struck Gorgon". The West Australian. 2017-04-10. Retrieved 2018-06-21.
  10. "How a gas plant could wipe out a year's worth of solar power emissions savings". ABC News. 2018-06-21. Retrieved 2018-06-21.
  11. Mile, Peter (2017-12-19). "Carbon hiccup for Chevron with 5 million-tonne greenhouse gas problem at Gorgon LNG plant". The West Australian. Retrieved 17 April 2018.
  12. "EPA to probe Gorgon's $2.5b LNG emissions storage delay". The West Australian. 2018-05-09. Retrieved 2018-06-21.
  13. Milne, Peter (2019-03-05). "Gorgon's CO2 burial faces more hold-ups". The West Australian. Retrieved 2019-03-07.
  14. Plan to bury Gorgon's greenhouse gas too risky Archived 2008-07-24 at the Wayback Machine . Accessed 27 May 2008.