Huangdeng Dam

Last updated
Huangdeng dam
Huangdeng Hydropower Station under construction.jpg
Huangdeng During Construction
CountryChina
LocationYunnan Province
Coordinates 26°33′33″N99°06′56″E / 26.55917°N 99.11556°E / 26.55917; 99.11556 Coordinates: 26°33′33″N99°06′56″E / 26.55917°N 99.11556°E / 26.55917; 99.11556
PurposePower, irrigation, recreation
StatusOperational
Construction beganJanuary 2010
Opening dateJune 2019
Owner(s)Yunnan Huaneng Lancang River Hydropower Co., Ltd.
Dam and spillways
ImpoundsLancang (upper Mekong)
Height (thalweg)203 m
Length464 m
Dam volume3,678,000 m3
Reservoir
Total capacity1,613,000,000 m3
Power Station
Commission date2019
Installed capacity 1,900 MW

The Huangdeng Dam is a gravity dam recently completed on the Lancang (Mekong) River in Lanping Bai and Pumi Autonomous County of Yunnan Province, China. The fact that work on the dam was begun without formal approval from the central government was a subject of some controversy. [1]

Construction on the dam began in 2010 and its 1,900 MW hydroelectric power station was initially planned to be operational in 2016, with the entire project complete in 2018. [2] [3] The first unit was put into operation in July 2018 [4] and the dam was fully commissioned in January 2019. [5]

See also

Related Research Articles

Xiluodu Dam Dam in Xiluodu Town, Yongshan County, Yunnan/Leibo County Sichuan, China

The Xiluodu Dam is an arch dam on the Jinsha River, i.e. the upper course of the Yangtze in China. It is located near the town of Xiluodu in Yongshan County of Yunnan Province but the dam straddles into Leibo County of Sichuan Province on the opposite side of the river. The primary purpose of the dam is hydroelectric power generation and its power station has an installed capacity of 13,860 MW. Additionally, the dam provides for flood control, silt control and its regulated water releases are intended to improve navigation downstream. Construction on the dam and power station began in 2005 and the first generator was commissioned in 2013, the last in 2014. It is operated by China Yangtze Power and is currently the third-largest power station with the fourth-tallest dam in the world.

Nuozhadu Dam Dam in Puer, Yunnan Province

Nuozhadu Dam is an embankment dam on the Lancang (Mekong) River in Yunnan Province, southwest China. The dam is 261.5 m (858 ft) tall, and creates a reservoir with a normal capacity of 21,749,000,000 m3 (17,632,000 acre⋅ft) at a level of 812 m (2,664 ft) asl. The purpose of the dam is hydroelectric power production along with flood control and navigation. The dam supports a power station with nine generators, each with generating capacity of 650 MW. The total generating capacity of the power station is 5,850 MW. Construction on the project began in 2004; the dam's first generator went online 6 September 2012 and the last generator was commissioned in June 2014. The construction and management of the project was implemented by Huaneng Power International Ltd., which has a concession to build, own and operate hydroelectric dams on China's stretch of the Mekong River.

Xiaowan Dam

The Xiaowan Dam is an arch dam on the Lancang (Mekong) River in Nanjian County, Yunnan Province, southwest China. The primary purpose of the dam is hydroelectric power generation and it supports a 4,200 MW power station. Constructed between 2002 and 2010 by Huaneng Power International at a cost of ¥32 billion, it is the world's second highest arch dam at 292 m (958 ft). It is also third highest among dams of all types behind Jinping-I and Nurek and the third largest hydroelectric power station in China.

Wudongde Dam Dam in China

The Wudongde Dam is a large hydroelectric dam on the Jinsha River, an upper stretch of Yangtze River in Sichuan and Yunnan provinces, southwest China.

Shuangjiangkou Dam Dam in Border of Maerkang County and Jinchuan County within Ngawa Tibetan and Qiang Autonomous Prefecture, Sichuan Province

The Shuangjiangkou Dam, also referred to as Shuang Jiang Kou, is an embankment dam currently being constructed in a gorge on the Dadu River in Sichuan Province, China. When completed, the 312 m-tall (1,024 ft) dam will be the tallest dam in the world. Preliminary construction began in 2008 and the entire project was expected to be complete in 2018. By April 2011, over 200,000,000 m3 (261,590,124 cu yd) of material had been excavated from the construction site. In March 2013, China's Ministry of Environmental Protection approved construction on the dam's superstructure and associated facilities. The government acknowledged that the dam would have negative impacts on the environment but that developers were working to mitigate them. The dam is being built by the Guodian Group at a cost of US$4.02 billion. The entire construction period is expected to last 10 years. All turbines are expected to be commissioned by 2023.

Dachaoshan Dam Dam in Yunnan Province

The Dachaoshan Dam is a gravity dam on the Lancang (Mekong) River in Yunnan Province, China. The sole purpose of the dam is hydroelectric power production as it supplies water to a power station containing six 225 MW generators for a total installed capacity of 1,350 MW.

Jinghong Dam Dam in Jinghong, Yunnan Province

The Jinghong Dam is a gravity dam composed of roller-compacted concrete on the Lancang (Mekong) River near Jinghong in Yunnan Province, China. The main purpose of the dam is hydroelectric power production and it has an associated 1,750 MW power station. Part of the power generated is sold to Thailand under an agreement with China.

Ludila Dam

The Ludila Dam(鲁地拉水电站 in Chinese) is a gravity dam on the Jinsha River near Lijiang in Yunnan province, China. The primary purpose of the dam is hydroelectric power generation and it will support a 2,160 MW power station. Construction on the dam began in 2007 and was briefly halted in June 2009 by the Ministry of Environmental Protection after it was being constructed without approval. On 13 June 2013 the dam's first generator became operational. In May 2014 reports surfaced that the dam and been damaged or was structurally unsound, forcing engineers to draw down the reservoir level and leaving the power station inoperable. An estimated 16,900 people were relocated after its construction.

Longkaikou Dam

The Longkaikou Dam is a gravity dam on the Jinsha River in Dali Bai Autonomous Prefecture, Yunnan province, China. The dam has a height of 119 m (390 ft) and was constructed with roller-compacted concrete. Construction on the dam began in 2007, the river was diverted in January 2009 but construction was briefly halted in June 2009 by the Ministry of Environmental Protection after it was being constructed without approval. On 25 November 2012 the reservoir was impounded and the first of five 360 MW Francis turbine-generators was commissioned on 21 May 2013. The last was commissioned on 29 November 2013. The dam was expected to displace 2,000 people. The dam also supports a fish proliferation system.

Jinping-I Dam Dam in Yanyuan County and Muli Tibetan Autonomous County, Liangshan Prefecture, Sichuan, China

The Jinping-I Dam also known as the Jinping-I Hydropower Station or Jinping 1st Cascade, is a tall arch dam on the Jinping Bend of the Yalong River in Liangshan, Sichuan, China. Construction on the project began in 2005 and was completed in 2014. Its power station has a 3,600 MW capacity to produce between 16 and 18 TW·h annually. Supplying the power station is a reservoir created by the 305-meter-tall arch dam, the tallest in the world. The project's objective is to supply energy for expanding industrialization and urbanization, improve flood protection, and prevent erosion.

Miaowei Dam Dam in Yunlong County, Dali Bai Autonomous Prefecture, Yunnan

The Miaowei Dam is a rock-filled embankment dam on the Lancang (Mekong) River in Yunlong County of Yunnan Province, China. Construction on the dam began in 2010. The four turbines of 1,400 MW hydroelectric power station were commissioned in 2017 and 2018.

Wunonglong Dam Dam in Weixi Lisu Autonomous County, Dêqên Tibetan Autonomous Prefecture, Yunnan

The Wunonglong Dam is a gravity dam currently under construction on the Lancang (Mekong) River in Weixi Lisu Autonomous County, Yunnan of Yunnan Province, China. The primary purpose of the dam is hydroelectric power production. Construction on the dam began in 2010 and the river was diverted around the foundation in November 2014. Its 990 MW hydroelectric power station is expected to be operational in 2018 with the entire project complete in 2019.

Dahuaqiao Dam Dam in Lanping Bai and Pumi Autonomous County, Nujiang Lisu Autonomous Prefecture, Yunnan

The Dahuaqiao Dam is a gravity dam on the Lancang River in Lanping Bai and Pumi Autonomous County of Yunnan Province, China. The primary purpose of the dam is hydroelectric power generation. Construction began in 2010 and its 900 MW hydroelectric power station was fully operational as of 2019.

Gongguoqiao Dam Dam in Yunlong County, Dali Bai Autonomous Prefecture, Yunnan

The Gongguoqiao Dam is a gravity dam on the Lancang (Mekong) River in Yunlong County of Yunnan Province, China. The primary purpose of the dam is hydroelectric power generation. Construction began in 2008 and the river was diverted around the dam site in 2009. The next year concrete placement began and in 2011 the first generator was commissioned. The 900 MW power station was fully operational on 21 June 2012.

Longjiang Dam Dam in Mangshi, Dehong Prefecture, Yunnan Province

The Longjiang Dam is an arch dam on the Long River near Mangshi in Dehong Prefecture of Yunnan Province, China. It is a multiple-purpose project aimed at flood control, irrigation and hydroelectric power generation. Its reservoir has a storage capacity of 1,217,000,000 m3 (986,638 acre⋅ft), of which 679,000,000 m3 (550,474 acre⋅ft) is reserved for river these purposes. The dam's power station is located on its left bank and contains three 80 MW Francis turbine-generators for a total installed capacity if 240 MW. Construction on the project began on 28 November 2006 and all generators were commissioned in 2010.

Madushan Dam Dam in Gejiu City and Jinping County, Honghe Prefecture, Yunnan Province

The Madushan Dam is a gravity dam on the Honghe (Red) River in Honghe Hani and Yi Autonomous Prefecture of Yunnan Province.

Tianhuaban Dam Dam in Ludian/Qiaojia Counties, Zhaotong, Yunnan Province

The Tianhuaban Dam is an arch dam on the Niulan River, a tributary of the Jinsha River. It straddles the border of Ludian and Qiaojia Counties in Yunnan Province, China. The primary purpose of the dam is hydroelectric power generation and it supports a 180 MW power station. In September 2006, construction on the dam's river diversion tunnels commenced. The first two of 90 MW Francis turbine-generator sets was commissioned in February 2011, the second in March of the same year. Water from the reservoir is diverted to a power station about 2.5 km (1.6 mi) downstream on the right bank of the river.

References

  1. "China gives environmental approval to country's biggest hydro dam". Reuters. 15 May 2013. Retrieved 2017-12-20.
  2. "Huang Teng Hydropower Project in Yunnan Province in mid-November closure (云南黄登水电站工程计划于11月中旬截流)" (in Chinese). Polaris Power Network News. 30 September 2013. Retrieved 17 June 2014.
  3. "Testing the waters: Hydropower engineers pioneer fish lift in China | WLE Mekong".
  4. "The First Unit of Huang Deng Hydropower Plant Generated Power". Kunming Engineering Corporation Limited. Retrieved 6 January 2020.
  5. "8th International Symposium on RCC dams" . Retrieved 7 January 2020.