Mercury Energy

Last updated

Mercury
Company type Public
NZX: MCY
ASX:  MCY
Industry Electric power generation
Predecessor ECNZ, Mighty River Power
Founded1 April 1999 (1999-04-01)
Headquarters,
Key people
Vince Hawksworth (CEO)
Products Electric power
Services Electricity retailing
RevenueIncrease2.svg NZ$2,188M (2022) [1]
Increase2.svg NZ$581M (2022) [1]
Increase2.svg NZ$469M (2022) [1]
Total assets Increase2.svg NZ$9,660M (2022) [1]
Total equity Increase2.svg NZ$4,752M (2022) [1]
Owner New Zealand Government (51.15%)
Number of employees
1335 [1]  (2022)
Subsidiaries GLOBUG (prepay power)
Website www.mercury.co.nz

Mercury NZ Limited is a New Zealand electricity generation and multi-product utility retailer of electricity, gas, broadband and mobile telephone services. All the company's electricity generation is renewable. Mercury has a pre-paid electricity product sub-brand GLOBUG. Mercury Energy is also the largest electricity retailer in New Zealand.

Contents

Mercury generates most of its energy from nine hydro stations on the Waikato River and five geothermal plants in the central north island as well as a number of wind farms. [2] [3] As of June 2021, Mercury had generated 3,611GWh of electricity through hydro generation and 2,594GWh through geothermal generation. [4]

Mercury also service industrial and wholesale market customers offering electricity and natural gas products. Since 2022 it has also offered internet fibre broadband services as a bundle for its residential electricity customers. [5] Mercury has offices in Auckland, Tauranga, Hamilton, Rotorua, Palmerston North, Wellington and Oamaru.

History

In the 1980s, the New Zealand Electricity Department (NZED) (a government department) controlled and operated almost all New Zealand electricity generation and operated the electricity transmission grid. The first phase of deregulation saw the New Zealand Government corporatisze the NZED and form the state-owned enterprise Electricity Corporation of New Zealand (ECNZ).

In 1994 Mercury NZ Limited was formed by the Auckland Energy Consumer Trust to own and operate the electricity supply business previously operated by the community-owned local authority, Auckland Electric Power Board (AEPB).

Also in 1994, Transpower New Zealand was separated from ECNZ and created as a State Owned Enterprise (SOE) to own and operate the national grid.

In 1996, ECNZ split into two SOEs, ECNZ and Contact Energy.

Logo of the former Mighty River Power MightyRiverPower-logo.svg
Logo of the former Mighty River Power

In 1998, law changes obligated AEPB to sell the electricity retailing and generation part of the business.

On 1 April 1999, ECNZ was split into three – Genesis Energy, Meridian Energy and Mighty River Power. Mercury's electricity retailing division was sold to Mighty River Power, who continued the trading name Mercury Energy. The electricity distribution business Mercury Energy Limited changed its name to Vector Limited and continued the distribution and transmission operation.

Mighty River Power took over the ownership and operation of the nine hydroelectric power stations on the Waikato River, New Zealand's longest river, and inherited assets of two largely decommissioned oil-fired power stations at Marsden Point, near Whangārei and its share in the Southdown Power Station (in conjunction with the Natural Gas Corporation).

In 2000, Mighty River Power acquired the Rotokawa geothermal power station, to operate and maintain the station, and own the geothermal turbines in a joint venture with the Tauhara North No.2 Trust. Also, that year, Mighty River Power commissioned the Mōkai geothermal power station geothermal power station in a joint venture with the Tuaropaki Trust.

In September 2002, Mighty River Power gained 100 percent ownership of the Southdown power station.

In 2004, Mighty River Power announced plans to refurbish the Marsden B plant to fire it on coal to increase supply security north of Auckland. Marsden B had been mothballed since it was completed in 1978 due to rising oil prices following the 1973 oil crisis and there being cheaper alternatives available. Greenpeace staged a nine-day occupation of the site in 2005, and after the Northland Regional Council granted consent, appealed to both the Environment Court and High Court, eventually overturning the consent. Mighty River Power appealed the High Court decision to the Court of Appeal, but in March 2007 dropped the proposal.

In 2008, Mighty River Power increased its generating capacity by opening the 100 MW Kawerau geothermal power station, increasing supply security to the eastern Bay of Plenty, a large timber processing area. In 2010, it opened the 140 MW Nga Awa Purua geothermal station near Taupō with the largest single-shaft geothermal turbine in the world. The commissioning of Nga Awa Purua increased Mighty River's geothermal capacity to 385 MW making it the nation's largest geothermal electricity generator with 52.7 percent of all installed geothermal capacity.

In 2009, Mighty River Power sold the Marsden B plant for $20 million to an Indian company, United Telecom. [6] Resource consents for dismantling the plant were granted in June 2011, and the 20,000 tonnes of plant and equipment was dismantled later in 2011.

In Dec 2011, the National Government announced plans to reduce its shareholding in the four state-owned energy companies, Contact Energy, Genesis Energy, Meridian Energy and Mighty River Power (Mercury) from 100 percent to 51 percent and to sell off the remaining 49 percent as part of its controversial "mixed-ownership model" plan. Mighty River Power was to be the first company to be partially sold in September 2012, pursuant to legislative changes and market conditions. [7] However, threatened legal action and unfavourable market conditions saw the Government delay any sale until March 2013 at the earliest. [8]

On 5 March 2012, the Government began taking registrations of interest from the public in Mighty River Power shares. [9] More than 35,000 people tried to register in the first six hours causing the registration website to crash for much of the day. [10] By midnight, more than 90,000 people had registered. [11]

In April 2013, State Owned Enterprises Minister Tony Ryall, in anticipation of the sale, said director fees would be increasing from $49,000 a year to $85,000, and the chair's fees from $98,000 to $150,000, despite still being majority-owned by taxpayers.

On 2 April 2013, The Financial Markets Authority approved the sale of Mighty River Power with the IPO (Initial Public Offering) on 15 April. However, the IPO was temporarily suspended on 22 April while a supplementary disclosure was issued, after the Labour and Green parties in opposition announced plans to reform the electricity market if elected to government at the 2014 election. At the close of the IPO on 5 May, there were 113,000 shareholders, and on 8 May the opening share price was set at $2.50, raising $1.7 billion. The Government was slightly disappointed, blaming the Labour-Green policy for putting off many more potential shareholders, with the Finance Minister indicating before the policy was announced that the price would be in the $2.70 to $2.80 range [12] The government retained 51.78 percent of the shareholding, with another 1.02 percent owned by other Crown interests (mainly the New Zealand Superannuation Fund). [13]

By September, shares had slumped to $2.16, well below the float price [14] and in October the company announced it would be buying back up to $50 million in shares. [15]

Logo of the former Mercury Energy Mercury Energy logo.jpg
Logo of the former Mercury Energy

In December 2015, the gas fired Southdown Power Station, a 170 MW combined cycle power station in south Auckland was closed.

On 29 July 2016, after merging its retail and generation businesses the company changed its name to Mercury NZ Limited. [16] The company also launched a new brand logo, moving from the Roman god Mercury, to a bee. Market research showed New Zealand had a stronger connection to the bee as a symbol. [17]

In August 2021, Mercury acquired five operating wind farms and several wind farm development options from Tilt Renewables. [18] At the same time, the first power from the newly built wind farm at Turitea was generated [19] – adding to the existing portfolio of nine hydro stations [20] on the Waikato River and five geothermal plants [21] located in the central North Island.

In August 2021, Mercury acquired five operating wind farms and several wind farm development options. [22] At the same time, the first power from the newly built wind farm at Turitea was generated. [23]

In May 2022, Mercury acquired the retail business of Trustpower, [24] including the retail customer base and Trustpower brand. The generation business of Trustpower changed its name to Manawa Energy Limited.

In June 2023, Mercury brought the two brands Mercury and Trustpower together under singular brand of Mercury. [25]

Power stations

Mercury operates 17 generation sites; 8 Hydroelectric Powerstations, 5 Geothermal, and 4 Wind Farms.

In total, the company has 2155 MW of generating capacity – 1096 MW hydroelectric, 475 MW geothermal and 584 MW wind.

NameTypeLocationCapacity
(MW)
Annual generation
(average GWh) [26]
CommissionedNotes
Arapuni Hydroelectric Waikato River 198805First 4 machines 1929; further 2 in 1938; another 2 in 1946
Aratiatia HydroelectricWaikato River78331March - May 1964
Ātiamuri HydroelectricWaikato River74305First 3 machines - Nov 1958; 4th machine April 1962
Karāpiro HydroelectricWaikato River96490Machine 1 - May 1947; Machine 2 - Sept 1947; Machine3 - May 1948Refurbishment project underway (expected completion 2025) once fully refurbished capacity will increase to 112.5MW with expected annual average generation of 537GW
Kawerau Geothermal Kawerau, Bay of Plenty 1068482008
Mahinerangi Wind Farm WindOtago682452011Acquired from Tilt Renewables August 2021
Maraetai HydroelectricWaikato River360878Maraetai 1 - 1952; Maraetai 2 - 1970
Mōkai GeothermalNorth-west of Taupō 1128902000Joint venture with Tuaropaki Trust
Ngā Awa Pūrua GeothermalNorth of Taupō 13911402010Joint venture with Tauhara North No.2 Trust
World's largest geothermal turbine (147 MW rated)
Ngā Tamariki GeothermalNorth of Taupō 857052013
Ōhakuri HydroelectricWaikato River1124051961
Rotokawa GeothermalNorth of Taupō 332701997Joint venture with Tauhara North No.2 Trust
Tararua Wind Farm Wind Tararua Ranges 161563Stage 1: 1991 Stage 2: 2004 Stage 3: 2007Acquired from Tilt Renewables August 2021
Turitea Wind Farm Wind Tararua Ranges 2228402023Turitea is currently NZ's largest wind farm
Waipipi Wind Farm WindSouth Taranaki1334552021Acquired from Tilt Renewables August 2021
Waipāpa HydroelectricWaikato River542381961
Whakamaru HydroelectricWaikato River1244971956

Generation developments

NameTypeLocationPlanned
capacity (MW)
Status
Puketoi Wind Puketoi Ranges Consent application lodged August 2011, [27] granted June 2012 [28]
Tararua I & II repoweringWindManawatu140 vs 68 existingDevelopment option acquired from Tilt Renewables August 2021 [29]
KaiwaikaweWindNorthland70Development option acquired from Tilt Renewables August 2021
Mahinerangi IIWindOtago160Development option acquired from Tilt Renewables August 2021
Kaiwera DownsWindSouthlandStage 1 43; Stage 2 to bring total to 240Stage 1 scheduled to commence Oct 2022 [30]

Subsidiaries

In addition to its generation assets, Mercury also incorporates or has major shareholdings in:

See also

Related Research Articles

The New Zealand electricity market (NZEM) is a decentralised electricity market regulated by the Electricity Industry Participation Code administered by the Electricity Authority (EA). The authority was established in November 2010 to replace the Electricity Commission.

<span class="mw-page-title-main">Genesis Energy Limited</span> New Zealand electricity generating and retailing company

Genesis Energy Limited, formerly Genesis Power Limited is a New Zealand publicly listed electricity generation and electricity, natural gas and LPG retailing company. It was formed as part of the 1998–99 reform of the New Zealand electricity sector, taking its generation capacity from the breakup of the Electricity Corporation of New Zealand (ECNZ) and taking retail customers from three local power boards in the Lower North Island. The New Zealand Government owns a 51% share of the company.

Meridian Energy Limited is a New Zealand electricity generator and retailer. The company generates the largest proportion of New Zealand's electricity, generating 35 percent of the country's electricity in the year ending December 2014, and is the fourth largest retailer, with 14 percent of market share in terms of customers as of December 2015.

<span class="mw-page-title-main">Manawa Energy</span> New Zealand electricity generation and retailing company

Manawa Energy limited is a New Zealand electricity generation company that offers bespoke electricity products to commercial and industrial customers across New Zealand. Manawa energy currently operate 26 power schemes from the Bay of Plenty in the north, to Otago in the south.

<span class="mw-page-title-main">Contact Energy</span> New Zealand electricity generating and retailing company

Contact Energy Limited is a New Zealand electricity generator, a wholesaler of natural gas, and a retailer of electricity, natural gas, broadband and LPG.

<span class="mw-page-title-main">Kawerau Power Station</span>

The Kawerau Power Station is a 100-megawatt geothermal power plant located just outside the town of Kawerau in the Bay of Plenty Region of New Zealand. The power station is situated within the Kawerau geothermal field, which is part of the Taupo Volcanic Zone. Completed in July 2008 by Mighty River Power at a cost of NZ$300 million, the plant's capacity proved greater than expected. The station is the largest single-generator geothermal plant in New Zealand.

<span class="mw-page-title-main">Wind power in New Zealand</span> Overview of wind power in New Zealand

Wind power constitutes a small but growing proportion of New Zealand's electricity. As of December 2020, wind power accounts for 690 MW of installed capacity and over 5 percent of electricity generated in the country.

The electricity sector in New Zealand uses mainly renewable energy, such as hydropower, geothermal power and increasingly wind energy. As of 2019, 82% of electricity is generated from renewable sources, making New Zealand one of the countries with the lowest carbon dioxide emissions from electricity generation. Electricity demand grew by an average of 2.1% per year from 1974 to 2010 but decreased by 1.2% from 2010 to 2013.

<span class="mw-page-title-main">Otahuhu Power Station</span>

The Ōtāhuhu power station was a power station site located in Ōtara, Auckland, New Zealand. Two plants operated on the site: Ōtāhuhu A and Ōtāhuhu B. A proposed third station, Ōtāhuhu C, was never built. The stations were owned by Contact Energy.

Turitea Wind Farm is a 222-megawatt wind farm near Turitea, Palmerston North, New Zealand. The farm is owned and operated by Mercury Energy.

The Awhitu Wind Farm is a renewable energy project in New Zealand initially planned by Tilt Renewables. The development is proposed to be located on the Awhitu Peninsula near Waiuku on the west coast south of Auckland. As of 2016 the project was being privately pursued.

The Poihipi Power Station is a geothermal power station owned and operated by Contact Energy. It is located on Poihipi Road near Taupō in New Zealand.

<span class="mw-page-title-main">Southdown Power Station</span>

Southdown Power Station was a natural gas-fired combined cycle gas turbine cogeneration power station in Southdown, a suburb in southern Auckland, New Zealand. When operational, it was New Zealand's northernmost power station with a capacity exceeding 50 MW.

<span class="mw-page-title-main">Whakamaru Dam</span> Dam in Lake Whakamaru

Whakamaru Power Station is a hydroelectric power station on the Waikato River, in the North Island of New Zealand. It is the fourth hydroelectric power station on the Waikato River.

Ngatamariki is a geothermal power station commissioned in 2013 and operated by Mercury Energy. It is located approximately 17 km north east of Taupō and was constructed well under the budget of $475 million.

<span class="mw-page-title-main">Solar power in New Zealand</span> Overview of solar power in New Zealand

Solar power in New Zealand is increasing in capacity, despite no government subsidies or interventions being available. As at the end of December 2023, New Zealand has 365 MW of grid-connected photovoltaic (PV) solar power installed, of which 105 MW (29%) was installed that year. In the 12 months to September 2023, 333 gigawatt-hours of electricity was estimated to have been generated by grid-connected solar, 0.77% of all electricity generated in the country.

The Mokai Power Station is a geothermal power station owned by the Tuaropaki Power Company and operated by Mercury NZ Limited. It is located approximately 30 km north west of Taupō in New Zealand. The station uses a binary cycle manufactured by Ormat Industries.

The Waipipi Wind Farm is a wind powered electricity generation project in New Zealand owned and operated by Mercury NZ Ltd. This site is located between Patea and Waverley in South Taranaki. The wind farm consists of 31 wind turbines over 980 hectares, generating up to 133 MW at a cost of approximately $277 million. The 4.3 MW machines are the largest wind turbines installed in New Zealand.

<span class="mw-page-title-main">Tilt Renewables</span> Australian utilities company

Tilt Renewables Pty Ltd is an Australian electricity generation company. It was previously dual listed on the New Zealand stock exchange and Australian stock exchange. As of 2022, the Powering Australian Renewables has merged with Tilt Renewables following a complex acquisition and merger, making it the largest private developer and generator of renewable electricity in Australia.

References

  1. 1 2 3 4 5 6 "Annual Report 2022". Mercury Energy. 16 August 2022.
  2. "News Release – first power produced at Turitea Wind Farm". Mercury. Retrieved 24 July 2022.
  3. "Geothermal". Mercury. Retrieved 24 July 2022.{{cite web}}: Check |url= value (help)
  4. "2021 Annual Report". Mercury. Mercury NZ. Retrieved 25 July 2022.
  5. "News Release Mercury launches unlimited fibre broadband offers". Mercury. Retrieved 24 July 2022.
  6. "Marsden B plant set to be shipped to India after $20m sale". The Northern Advocate. Retrieved 1 October 2022 via nzherald.co.nz.
  7. "Mighty River Power first SOE to go". The New Zealand Herald. 15 December 2011. Retrieved 12 January 2012.
  8. Tracy, Watkins (3 September 2012). "Sale of Mighty River Power delayed". Stuff. Dominion Post. Retrieved 15 October 2012.
  9. Grant, Bradley (4 March 2013). "Market may take a hit as Mighty River sale attracts 'huge interest". The New Zealand Herald. Retrieved 15 August 2022.
  10. "Mighty River share site crashes". The New Zealand Herald. 5 March 2013. Retrieved 15 August 2022.
  11. Rutherford, Hamish (6 March 2013). "Mighty River share registration high". Stuff. Retrieved 15 August 2022.
  12. "Mighty River $2.50 price hit by power policy". The New Zealand Herald. 9 May 2013. Retrieved 15 August 2022.
  13. Parker, Tamsyn (17 May 2013). "Stock Takes: Mighty nervous". The New Zealand Herald. Retrieved 15 August 2022.
  14. "Mighty River Power pair snap up shares".
  15. "Mighty River Power to buy back shares".
  16. "Mercury inspired by new energy future". Mercury.
  17. Venuto, Damien (29 July 2016). "Mercury buzzes in with new look, champions renewable energy". StopPress. Retrieved 15 August 2022.
  18. "News Release Mercury acquires Tilt Renewables' New Zealand operations". Mercury. Retrieved 24 July 2022.
  19. "News Release – first power produced at Turitea Wind Farm". Mercury. Retrieved 24 July 2022.
  20. "Hydro Generation". Mercury. Retrieved 24 July 2022.
  21. "Geothermal". Mercury. Retrieved 24 July 2022.
  22. "Mercury acquires Tilt Renewables' New Zealand opertaions". Mercury. Retrieved 15 August 2022.
  23. "First power produced at Turitea Wind Farm". Mercury. Retrieved 15 August 2022.
  24. "Mercury's acquisition of Trustpower's retail business now unconditional". Mercury. Retrieved 15 August 2022.
  25. "Trustpower is now Mercury". Mercury. Mercury.
  26. "Operating Statistics – Mercury NZ" . Retrieved 20 July 2017.
  27. "Mighty River Power lodges application for wind development at Puketoi" (Press release). Mighty River Power. 3 August 2011. Archived from the original on 4 October 2011.
  28. "Mighty River gains consents for Puketoi wind farm" (Press release). Mighty River Power. 25 June 2012. Retrieved 25 June 2012.
  29. "Mercury (ASX:MCY) acquires Tilt Renewables' NZ operations". Finance News Network. 3 August 2021.
  30. "Construction on new wind farm near Gore will begin in October". Stuff. 12 September 2022.
  31. "Starship Children's Health | Supporting Our Community | Mercury".