Project risk management

Last updated

Within project management, risk management refers to activities for minimizing project risks, and thereby ensuring that a project is completed within time and budget, as well as fulfilling its goals.

Contents

Definition of risk and risk management

Risk management activities are applied to project management. Project risk is defined by the Project Management Institute (PMI) as, "an uncertain event or condition that, if it occurs, has a positive or negative effect on a project’s objectives." [1]

Within disciplines such as operational risk, financial risk and underwriting risk management, the concepts of risk, risk management and individual risks are nearly interchangeable; being either personnel or monetary impacts respectively. However, impacts in project risk management are more diverse, overlapping monetary, schedule, capability, quality and engineering disciplines. For this reason it is necessary in project risk management to specify the differences (paraphrased from the U.S. "Department of Defense Risk, Issue, and Opportunity Management Guide for Defense Acquisition Programs"):

An improvement on the PMI's PMBOK definition of risk management is to add a future date to the definition of a risk. [2] Mathematically, this is expressed as a probability multiplied by an impact, with the inclusion of a future impact date and critical dates. This addition of future dates allows predictive approaches.[ citation needed ]

Procedure

Good project risk management depends on supporting organizational factors, having clear roles and responsibilities, and technical analysis.

Chronologically, project risk management may begin in recognizing a threat, or by examining an opportunity. For example, these may be competitor developments or novel products. Due to lack of definition, this is frequently performed qualitatively, or semi-quantitatively, using product or averaging models. This approach is used to prioritize possible solutions, where necessary.

In some instances it is possible to begin an analysis of alternatives, generating cost and development estimates for potential solutions.

Once an approach is selected, more familiar risk management tools and a general project risk management process may be used for the new projects:

Finally, risks must be integrated to provide a complete picture, so projects should be integrated into enterprise wide risk management, to seize opportunities related to the achievement of their objectives.

Project risk management tools

In order to make project management effective, the managers use risk management tools. It is necessary to assume the measures referring to the same risk of the project and accomplishing its objectives.[ clarification needed ][ citation needed ]

The project risk management (PRM) system should be based on the competences of the employees willing to use them to achieve the project’s goal. The system should track down all the processes and their exposure which occur in the project, as well as the circumstances that generate risk and determine their effects. Nowadays, the big data analysis appears an emerging method to create knowledge from the data being generated by different sources in production processes. According to Górecki, big data seems to be the adequate tool for project risk management .[ citation needed ]

See also

Related Research Articles

Earned value management (EVM), earned value project management, or earned value performance management (EVPM) is a project management technique for measuring project performance and progress in an objective manner.

Project management is the process of leading the work of a team to achieve all project goals within the given constraints. This information is usually described in project documentation, created at the beginning of the development process. The primary constraints are scope, time, and budget. The secondary challenge is to optimize the allocation of necessary inputs and apply them to meet pre-defined objectives.

<span class="mw-page-title-main">Risk management</span> Identification, evaluation and control of risks

Risk management is the identification, evaluation, and prioritization of risks followed by coordinated and economical application of resources to minimize, monitor, and control the probability or impact of unfortunate events or to maximize the realization of opportunities.

<span class="mw-page-title-main">Systems engineering</span> Interdisciplinary field of engineering

Systems engineering is an interdisciplinary field of engineering and engineering management that focuses on how to design, integrate, and manage complex systems over their life cycles. At its core, systems engineering utilizes systems thinking principles to organize this body of knowledge. The individual outcome of such efforts, an engineered system, can be defined as a combination of components that work in synergy to collectively perform a useful function.

<span class="mw-page-title-main">Project Management Body of Knowledge</span> Body of knowledge for project management

The Project Management Body of Knowledge (PMBOK) is a set of standard terminology and guidelines for project management. The body of knowledge evolves over time and is presented in A Guide to the Project Management Body of Knowledge, a book whose seventh edition was released in 2021. This document results from work overseen by the Project Management Institute (PMI), which offers the CAPM and PMP certifications.

<span class="mw-page-title-main">Audit</span> Systematic and independent examination of books, accounts, documents and vouchers of an organization

An audit is an "independent examination of financial information of any entity, whether profit oriented or not, irrespective of its size or legal form when such an examination is conducted with a view to express an opinion thereon." Auditing also attempts to ensure that the books of accounts are properly maintained by the concern as required by law. Auditors consider the propositions before them, obtain evidence, roll forward prior year working papers, and evaluate the propositions in their auditing report.

The rational unified process (RUP) is an iterative software development process framework created by the Rational Software Corporation, a division of IBM since 2003. RUP is not a single concrete prescriptive process, but rather an adaptable process framework, intended to be tailored by the development organizations and software project teams that will select the elements of the process that are appropriate for their needs. RUP is a specific implementation of the Unified Process.

<span class="mw-page-title-main">SWOT analysis</span> Business planning and analysis technique

SWOT analysis is a strategic planning and strategic management technique used to help a person or organization identify Strengths, Weaknesses, Opportunities, and Threats related to business competition or project planning. It is sometimes called situational assessment or situational analysis. Additional acronyms using the same components include TOWS and WOTS-UP.

<span class="mw-page-title-main">Requirements analysis</span> Engineering process

In systems engineering and software engineering, requirements analysis focuses on the tasks that determine the needs or conditions to meet the new or altered product or project, taking account of the possibly conflicting requirements of the various stakeholders, analyzing, documenting, validating and managing software or system requirements.

Operational risk is the risk of losses caused by flawed or failed processes, policies, systems or events that disrupt business operations. Employee errors, criminal activity such as fraud, and physical events are among the factors that can trigger operational risk. The process to manage operational risk is known as operational risk management. The definition of operational risk, adopted by the European Solvency II Directive for insurers, is a variation adopted from the Basel II regulations for banks: "The risk of a change in value caused by the fact that actual losses, incurred for inadequate or failed internal processes, people and systems, or from external events, differ from the expected losses". The scope of operational risk is then broad, and can also include other classes of risks, such as fraud, security, privacy protection, legal risks, physical or environmental risks. Operational risks similarly may impact broadly, in that they can affect client satisfaction, reputation and shareholder value, all while increasing business volatility.

The Project Management Institute is a U.S.-based not-for-profit professional organization for project management.

A feasibility study is an assessment of the practicality of a project or system. A feasibility study aims to objectively and rationally uncover the strengths and weaknesses of an existing business or proposed venture, opportunities and threats present in the natural environment, the resources required to carry through, and ultimately the prospects for success. In its simplest terms, the two criteria to judge feasibility are cost required and value to be attained.

An information technology audit, or information systems audit, is an examination of the management controls within an Information technology (IT) infrastructure and business applications. The evaluation of evidence obtained determines if the information systems are safeguarding assets, maintaining data integrity, and operating effectively to achieve the organization's goals or objectives. These reviews may be performed in conjunction with a financial statement audit, internal audit, or other form of attestation engagement.

Business analysis is a professional discipline focused on identifying business needs and determining solutions to business problems. Solutions may include a software-systems development component, process improvements, or organizational changes, and may involve extensive analysis, strategic planning and policy development. A person dedicated to carrying out these tasks within an organization is called a business analyst or BA.

Software project management is the process of planning and leading software projects. It is a sub-discipline of project management in which software projects are planned, implemented, monitored and controlled.

Intellectual property assets such as patents are the core of many organizations and transactions related to technology. Licenses and assignments of intellectual property rights are common operations in the technology markets, as well as the use of these types of assets as loan security. These uses give rise to the growing importance of financial valuation of intellectual property, since knowing the economic value of patents is a critical factor in order to define their trading conditions.

The marketing research process is a six-step process involving the definition of the problem being studied upon, determining what approach to take, formulation of research design, field work entailed, data preparation and analysis, and the generation of reports, how to present these reports, and overall, how the task can be accomplished.

A Risk Breakdown Structure (RBS) within risk management is a hierarchically organised depiction of the identified project risks arranged by category.

<span class="mw-page-title-main">IT risk management</span>

IT risk management is the application of risk management methods to information technology in order to manage IT risk, i.e.:

Benefits Realization Management (BRM) is one of the many ways of managing how time and resources are invested into making desirable changes.