Railway reconstruction in Taiwan

Last updated

Since the 1980s, ground level railway facilities in urban areas have been seen as obstacles to road traffic and local development. [1] In 1983, the Executive Yuan tasked the Taipei Railway Underground Project Organisation (TRUPO) [2] with the project to rebuild railway facilities in greater Taipei, completed in 2011. [1] The office would later become the Railway Reconstruction Bureau, [3] then Railway Bureau, responsible for reconstruction in other urban areas. Completed or partially complete reconstruction projects include those for Yuanlin, Pingtung, Taichung and Kaohsiung, with more planned or under construction for Tainan, Taoyuan, Chiayi, Changhua and more.

Contents

Greater Taipei

The last train operating on surface trackage in Taipei City before the cut-over to underground trackage built during the Undergroundization Project: Taroko Express No. 1074 on September 20, 2008. 1074 in Songshan at 920.JPG
The last train operating on surface trackage in Taipei City before the cut-over to underground trackage built during the Undergroundization Project: Taroko Express No. 1074 on September 20, 2008.
Civic Boulevard Expressway (a second phase project) is an elevated expressway built above underground railway tracks. TaipeiCivicBlvdExpressway.jpg
Civic Boulevard Expressway (a second phase project) is an elevated expressway built above underground railway tracks.

In Taipei, a NT$17.792 billion project aimed to move a 4.42 km (2.75 mi) section of railway between Huashan and Wanhua underground. [4] Work began on the project in July 1983 and was completed by September 1989, eliminating 13 railroad crossings. [4] An extension of the project was approved by the Executive Yuan on July 20, 1988. The 5.33 km (3.31 mi) project constructed a double-track tunnel (for both conventional rail and high-speed rail) extending east towards Songshan. [5] The NT$27.48 billion project was completed in June 1994.

The "Wanhua-Banciao Project" was another underground railway project in Taipei aimed at the Wanhua and Banqiao areas. [6] The 15.38 km (9.56 mi) project included the construction of new Banqiao and Wanhua stations. [6] Construction began in September 1992, with underground railway operations beginning in July 1999 and tunnel construction for Taiwan High Speed Rail completed in April 2003. [6] The whole project was completed in 2004. The project also included the construction of a coach yard at Shulin, covering 14.3 ha (143,000 m2) and servicing both diesel multiple units and electric multiple units. [6]

Second phase

In the nineties, the tunnel was extended both eastward and westward, and with separate double track north and south tunnels, preparation was made for Taiwan High Speed Rail, the planned high-speed line to Kaohsiung. The eastward extension, the Songshan Project, added 5.33 km (3.31 mi) to Songshan. [7] The project cost NT$27.48 billion, and was in construction from July 1989 until June 1994. [7] On the surface, the space gained was used for the construction of the elevated Civic Blvd Expressway, which opened in September 1997. [7]

Surface facilities of the new Banqiao Station Banciao Station 01.jpg
Surface facilities of the new Banqiao Station

The westward extension, the Wanhua–Banqiao Project, added 7.18 km (4.46 mi) to the four-track tunnel section, on a new alignment with the newly built Wanhua Station and the rebuilt Banqiao Station along it. [8] The total project length was 15.38 km (9.56 mi), which included the upgrade of TRA's surface tracks, and a new Shulin Coach Yard at the end of the upgraded section, built to maintain TRA's electric multiple unit (EMU) and diesel multiple unit (DMU) fleet. [8] Work started in September 1992, and TRA began to use the underground tracks in the north tunnel in July 1999. [8]

The extensions also include emergency stations, where passengers can be evacuated in case of fire. The stations and emergency stations were fitted with a smoke suppression system that was tested with simulations and a live evacuation trial in Wanhua Station. [9]

The first 14 km (8.7 mi) [10] of the south tunnel and its exit forms an altogether 15.8 km (9.8 mi) section of the THSR. [11] Civil works were the responsibility of TRUPO. [2]

When work started on the south tunnel, TRA's management was concerned that TRA's capacity would be limited during construction. [11] TRA was to give up the tracks and some station platforms without receiving compensation or rent. [12] The rail unions argued that this arrangement would result in a reduction of TRA services by more than a fourth, and a loss of income and jobs; the union organised a protest rally in March 2002, after which the Ministry of Transport agreed to re-negotiate the TRA–THSRC contract. [12] The cancellation of some TRA train services resulting from the final station platform lease agreement led to another union protest and threat of strike action in February 2003. [13] Unions continued to protest the TRA–THSRC agreement, accusing the government of having favoured THSRC. [14] Civil works in the south tunnel were completed in April 2003. [8]

After the completion of track construction, the western end of the south tunnel went into service on 5 January 2007, when THSRC's high-speed trains began to run between Taipei and Kaohsiung with Banqiao as the Taipei terminus. [15] The service was extended to Taipei Main Station on 2 March 2007. [16] The end of the completed 4.9 km (3.0 mi) track section east of Taipei was put into use as the Songshan Temporary Facility, for servicing the trains. [17]

Third phase

The new Nangang Station was one of the third phase projects. Nangang Station Building face to Zhongxiao East Road 20160723b.jpg
The new Nangang Station was one of the third phase projects.

The NT$83.069 billion Nangang Project completes the Taipei Railway Underground Project with a 5.4 km (3.4 mi) eastward extension of the tunnel, including the rebuilt Songshan and Nangang Stations. [18] East of Nangang along TRA's Western Line, the project also includes a short mountain tunnel and a 5 km (3.1 mi) elevated section. [18] Wudu Freight Yard, near Wudu Station, and Qidu Marshalling Yard, next to Qidu Station, replaces facilities dissolved at Songshan Station. [18] The entire length of the TRA part of the Nangang Project is 19.585 km (12.170 mi) between Songshan and Qidu, and was to be completed in August 2011. [18] Construction was officially completed on 23 October 2011 and began service the following day on 24 October 2011. [19] As a separate NT$10 billion project, in March 2009, TRA also began building a new depot at Fugang, Taoyuan County (now Taoyuan City), to replace its Songshan Depot, which was reached crossing THSRC's tracks. [20]

The "Nangang Project", expected to be completed by August 2011, includes the construction of two 5.4 km (3.4 mi) tunnels between Keelung Road and the Dakeng River (for the TRA and THSR), reconstructing Songshan and Nangang stations as underground stations, construction of a 2 km (1.2 mi) mountain tunnel/ramp for the TRA, construction of a 5 km (3.1 mi) elevated railway, and the construction of the Cidu Marshalling Yard and Wudu Freight Yard. [21] At an estimated cost of NT$83.069 billion, the project is expected to eliminate 15 level crossings and boost the development of the Nangang District. [21] A project to expand the railway tracks between Nangang and Qidu from a double-track to triple-track system is expected to be completed by December 2012, decreasing the interval between trains during peak hours. [22]

Approaching Nangang Station from the west, THSRC's south tunnel swings above TRA's north tunnel, to connect to different levels of Nangang Station. [18] East of Nangang Station, THSR tracks swing to the right, [18] towards THSRC's planned Xizhi Depot. [17] The THSR level of Nangang Station was opened to passengers on 20 September 2016. [23]

With the railroad moved underground in the Songshan-Nangang area, a new 4.7 km (2.9 mi) road was created aboveground running from Keelung Road to Nangang Station. [24] An online ballot was created to let citizens vote on the name of the new road, scheduled to open in October 2011.

Kaohsiung

Since the opening of the new Xinzuoying Station in Zuoying, Kaohsiung, traffic problems have plagued the area. [25] The "Zuoying Extension Plan of the Kaohsiung Railway Underground Project" aims to construct a 4.13 km (2.57 mi)-long single hold, double-tracked tunnel between Xinzuoying and TRA's Zuoying Station. [25] Neiwei Station will also be redeveloped as part of this project. [25]

The "Kaohsiung Project" aims to move railroad lines in Kaohsiung underground as well as the construction of six commuter rail stations. [26] Estimated to cost NT$71.582 billion, the 9.75 km (6.06 mi) tunnel will eliminate six level crossings and fourteen grade separated crossings and remove the railway barrier along the current route. [26] While planning for the project began in 1998, several pre-construction projects have been completed including the movement of the old Kaohsiung Station and the construction of the Jhongbo temporary elevated bridge. [26] The project is expected to be completed by December 2018, and will also include the construction of a new Kaohsiung Station by 2023. [26]

Shalun

The "Shalun Project" was approved on November 5, 2004 and links the TRA and THSR lines around Tainan. [27] The 6.5 km (4.0 mi)-long branch line involved the construction of two brand-new elevated stations: Shalun Station and Chang Jung Christian University Station as well as an elevated Zhongzhou Station. [27] It opened on January 2, 2011. [28]

Neiwan

Similar to the Shalun Project, the Neiwan line was approved on September 27, 2004 to connect THSR Hsinchu Station with Hsinchu City. [29] The project will eliminate eight railway crossings between Hsinchu and Zhuzhong. [29] The line totals 11.1 km (6.9 mi) and was completed in 2011. [29] The Liujia line opened and the Neiwan line reopened on November 11, 2011. [30]

Related Research Articles

<span class="mw-page-title-main">Taiwan High Speed Rail</span> High-speed railway in Taiwan

Taiwan High Speed Rail (THSR) is the high-speed railway of Taiwan consisting of one line that runs approximately 350 km (217 mi) along the west coast, from the capital Taipei to the southern city of Kaohsiung. With construction and operations managed by a private company, Taiwan High Speed Rail Corporation (THSRC), which also operates the line, the total cost of the project was NT$513.3 billion in 1998. At the time it was built, this was one of the world's largest privately funded rail construction schemes. The system's technology is based primarily on Japan's Shinkansen.

<span class="mw-page-title-main">THSR 700T</span> High speed train type operated in Taiwan

The THSR 700T is the high-speed electric multiple unit trainset derived from the Japanese Shinkansen family for Taiwan High Speed Rail (THSR), Taiwan's high-speed rail line. The THSR 700T is based primarily on the 700 Series Shinkansen that currently operates on the San'yō Shinkansen line and formerly on the Tokaido Shinkansen line in Japan, with the "T" referring to Taiwan. The trains were manufactured in Japan by Kawasaki Heavy Industries, Nippon Sharyo, and Hitachi, Ltd., marking the first time Japanese Shinkansen trains have been exported overseas. 30 trains were delivered to THSR operator Taiwan High Speed Rail Corporation (THSRC), and are in regular service with a top speed of 300 kilometres per hour (186 mph) since the line's opening on January 5, 2007.

<span class="mw-page-title-main">Taiwan Railways Administration</span> Railway operator in Taiwan

Taiwan railway Railways Administration (TRA) is a railway operator in Taiwan. It is an agency of the Ministry of Transportation and Communications, responsible for managing, maintaining, and running conventional passenger and freight railway services on 1,097 km (682 mi) of track in Taiwan.

<span class="mw-page-title-main">Kaohsiung Metro</span> Transit system in Kaohsiung, Taiwan

Kaohsiung Metro is a rapid transit and light rail system covering the metropolitan area of Kaohsiung, Taiwan. Its rapid transit network is known as Kaohsiung Mass Rapid Transit or Kaohsiung MRT. Construction of the MRT started in October 2001. The MRT opened in 2008 and the Circular light rail in 2015. Kaohsiung Metro is operated by the Kaohsiung Rapid Transit Corporation under a BOT contract the company signed with the Kaohsiung City Government.

<span class="mw-page-title-main">Taipei Main Station</span> Major railway station in Taiwan

Taipei Main Station is a major metro and railway station in the capital Taipei, Taiwan. It is served by Taipei Metro, the Taiwan High Speed Rail, and the Taiwan Railways Administration. It is also connected through underground passageways to the terminal station of Taoyuan Airport MRT and the Taipei Bus Station. It is the busiest station in Taiwan and one of the busiest stations in Asia, with more than 5,000 trains arriving and departing daily; on average, more than 600,000 people use Taipei Main Station every day.

<span class="mw-page-title-main">Taoyuan Airport MRT</span> Airport rail link of Taoyuan Airport, operated by Taoyuan Metro

Taiwan Taoyuan International Airport MRT, commonly known as the Airport MRT, is a rapid transit line of Taoyuan Metro that connects the municipalities of the capital Taipei, Taoyuan, and New Taipei with Taoyuan International Airport. The 51.33 km (31.89 mi) line, from Taipei Main Station to Huanbei, has 22 stations and began commercial service on 2 March 2017.

<span class="mw-page-title-main">Civic Boulevard</span> Highway in Taipei

The Civic Boulevard is a 4 to 6-lane highway located in Taipei, Taiwan. It was completed in 1997 as part of a multi-modal reconstruction project to improve transportation networks in congested central Taipei. The highway begins at the MacArthur Bridges in the east (connecting the Neihu district, and Keelung Road, heads west to an interchange with the Zhongxiao Bridge and the HuanHe Expressway, providing direct access to Taipei Main Station, which is just south of the Civic Blvd. Expressway in the Zhongzheng district. Since Civic Blvd. is elevated, there is also a surface-level frontage road system below the highway, connecting intersecting arterials with highway ramps. As part of the larger project, the elevated Civic Blvd. Expressway was constructed to provide a new, east–west highway through Taipei, moving the Taipei railway railroad tracks underground to reduce congestion at surface railroad crossings, and providing new underground parking options. Other additions to this project constructed new underground shopping malls in the vicinity of Taipei Main Station and provisions for utilities. In the future, tracks for the Taiwan High Speed Rail system will be added under existing tracks for the THSR's extension to Nangang in 2012.

<span class="mw-page-title-main">Nangang station</span> Railway station located in Taipei, Taiwan

Nangang is a railway and metro station in Taipei, Taiwan served by Taiwan High Speed Rail, Taiwan Railways Administration and Taipei Metro. The station is served by the fastest HSR express services of the 1 series.

<span class="mw-page-title-main">Bannan line</span> A MRT Route in Great Taipei Metropolitan

The Bannan or Blue line is a metro line of Taipei Metro in Taipei, Taiwan, with a total of 23 stations serving the districts of Nangang, Xinyi, Daan, Zhongshan, Wanhua, Banqiao and Tucheng. The line's name is a portmanteau of Banqiao and Nangang.

<span class="mw-page-title-main">Transportation in Taiwan</span>

The Ministry of Transportation and Communications governs transportation in Taiwan.

<span class="mw-page-title-main">Songshan station</span> Railway station located in Taipei, Taiwan

Songshan is a railway and metro station in Taipei, Taiwan, served by Taiwan Railways and Taipei Metro. This station connects to the shopping centre at basement 1 and level 1. The station is a planned transfer for the Circular line.

<span class="mw-page-title-main">Taoyuan HSR station</span> Railway station in Taoyuan, Taiwan

Taoyuan HSR is a high-speed rail and metro station in Zhongli District, Taoyuan, Taiwan, served by Taiwan High Speed Rail and Taoyuan Airport MRT, and is also known as Qingpu Station.

<span class="mw-page-title-main">Hsinchu HSR station</span> Railway station in Hsinchu, Taiwan

Hsinchu is a railway station in Hsinchu County, Taiwan served by Taiwan High Speed Rail. It opened for service in 2006. The station was designed by Taiwanese architect Kris Yao. Transfers to TRA Liujia station can be made at this station, which links to the Hsinchu TRA station located In Hsinchu City. Hsinchu HSR station is 11 km away from Hsinchu TRA station.

<span class="mw-page-title-main">Tainan HSR station</span> Railway station in Tainan, Taiwan

Tainan is a railway station in Tainan, Taiwan served by Taiwan High Speed Rail, and is connected to Shalun station for TRA services. Tainan HSR station is about 17 km away from Tainan railway station.

<span class="mw-page-title-main">Zuoying HSR station</span> Railway station located in Kaohsiung, Taiwan.

Zuoying is a metro and railway station in Kaohsiung, Taiwan served by Kaohsiung MRT, Taiwan High Speed Rail, and Taiwan Railways, where it is known as Xinzuoying. The station is served by the fastest HSR express services of the 1 series.

<span class="mw-page-title-main">Tainan railway station</span> Railway station located in Tainan, Taiwan.

Tainan is a railway station in Tainan, Taiwan served by Taiwan Railways Administration. Situated in centre of the old town square of Tainan, Tainan Station is the main station of the city and also one of the major stations along the western trunk line in Taiwan. The Shalun line, opened in 2011, allows through services to link the station with THSR Tainan Station.

<span class="mw-page-title-main">Continental Engineering Corporation</span>

Continental Engineering Corporation is a large Taiwanese construction company.

<span class="mw-page-title-main">Banqiao station</span> Railway station in New Taipei, Taiwan

Banqiao is a railway and metro station in New Taipei, Taiwan served by Taiwan High Speed Rail, TRA and Taipei Metro. With the exception of the Circular Line, all other tracks and platforms in the station are located underground. The station is served by the fastest HSR express services of the 1 series.

<span class="mw-page-title-main">Shalun line</span>

The Shalun Line is a branch line of the Taiwan Railways Administration (TRA) West Coast line in Tainan, Taiwan. It was built to link the Western Line to the Taiwan High Speed Rail (THSR) Tainan Station, speeding up transit times between downtown Tainan and the THSR station, with services running from Nanke railway station or Tainan TRA station to Shalun Station, next to the THSR station. The line opened on January 2, 2011.

References

  1. 1 2 "Taipei Main Station Project". Railway Reconstruction Bureau, Ministry of Transportation and Communications. Archived from the original on 2013-12-09. Retrieved 2011-02-23.
  2. 1 2 Saleem, Amair (May 2006). "Taiwan's High Speed Rail: Technical Challenges". PB Network. Parsons Brinckerhoff. XXI (63). Retrieved 2010-10-06.
  3. "Organization & Duties". Railway Reconstruction Bureau. Retrieved 6 November 2018.
  4. 1 2 "Taipei Main Station Project". Railway Reconstruction Bureau. Retrieved 2011-01-21.
  5. "Songshan Project". Railway Reconstruction Bureau. Retrieved 2011-01-21.
  6. 1 2 3 4 "Wanhua-Banciao Project". Railway Reconstruction Bureau. Retrieved 2011-01-21.
  7. 1 2 3 "Songshan Project". Railway Reconstruction Bureau, Ministry of Transportation and Communications. Retrieved 2011-02-23.
  8. 1 2 3 4 "Wanhua-Banqiao Project". Railway Reconstruction Bureau, Ministry of Transportation and Communications. Retrieved 2011-02-23.
  9. Yang, K.H.; Yeh, T.C. (2004). "Experimental Validation of the Taipei Underground Railway System under Emergency Operation Modes" (PDF). International Rail Safety Conference. Archived from the original (PDF) on 2006-05-15. Retrieved 2011-02-23.{{cite journal}}: Cite journal requires |journal= (help)
  10. "Taiwan High-Speed Line On Course To Open In 2005 - High Speed: Far East". International Railway Journal . October 2002. Retrieved 2010-10-09.
  11. 1 2 "THSRC starts major work this month". Railway Gazette International. 2001-03-01. Retrieved 2010-10-09.
  12. 1 2 "Rail workers get their way". Taipei Times . 2002-03-27. Retrieved 2011-02-02.
  13. "Railway union plans big strike". Taipei Times. 2003-02-26. Retrieved 2011-02-02.
  14. "Railway workers plan protest". Taipei Times. 2003-06-13. Retrieved 2011-02-02.
  15. "High speed rail commences operations". Taipei Times. 2007-01-06. Retrieved 2010-09-28.
  16. "Taiwan Quick Take/Taipei HSR station opens". Taipei Times. 2007-03-02. Retrieved 2010-09-28.
  17. 1 2 Shima, Takashi (August 2007). "Taiwan High Speed Rail" (PDF). Japan Railway & Transport Review (48): 40–46. Archived from the original (PDF) on 2011-06-13. Retrieved 2011-01-13.
  18. 1 2 3 4 5 6 "Nangang Project". Railway Reconstruction Bureau, Ministry of Transportation and Communications. Retrieved 2011-02-23.
  19. "市民大道南港段 24日通車". 中央通訊社. 2011-10-23. Retrieved 2011-10-23.
  20. "TRA holds groundbreaking ceremony for new depot". Taipei Times. 2009-04-01. Retrieved 2011-02-26.
  21. 1 2 "Nangang Project". Railway Reconstruction Bureau. Retrieved 2011-01-22.
  22. Shan, Shelley (2011-08-19). "Triple-track system to allow faster train service". Taipei Times . Retrieved 2011-08-18.
  23. "Four stations to be added to Taiwan high speed rail". Focus Taiwan (CNA). 2010-04-26. Retrieved 2010-10-06.
  24. "Road-naming ballot in Taipei to run through Aug. 8". Focus Taiwan News Channel. 2011-07-25. Retrieved 2011-07-25.
  25. 1 2 3 "Zuoying Project". Railway Reconstruction Bureau. Retrieved 2011-01-22.
  26. 1 2 3 4 "Kaohsiung Project". Railway Reconstruction Bureau. Retrieved 2011-01-22.
  27. 1 2 "Shalun Project". Railway Reconstruction Bureau. Retrieved 2011-01-22.
  28. "Shalun Branch line cuts travel time for Tainan commuters". Taipei Times . 2011-01-03. Retrieved 2013-11-27.
  29. 1 2 3 "Neiwan Project". Railway Reconstruction Bureau. Retrieved 2011-01-20.
  30. Shan, Shelley (2011-11-09). "Hsinchu's Lioujia railway line set to open on Friday". Taipei Times . Retrieved 2013-11-27.