The Bieudron Hydroelectric Power Station is a hydroelectric power plant located in the Swiss Alps in the Canton of Valais in Switzerland. The power plant is fed with water from the Grande Dixence Dam's reservoir, Lac des Dix and is part of the Cleuson-Dixence Complex. The 1269 MW power plant is operated by Grande Dixence SA. [1]
Production began in 1998, with two world records set upon its completion: the world's most powerful Pelton turbine as well as the highest head used to produce hydro-electric energy. A penstock rupture in 2000 forced the closure of the power plant and it was operational again in 2010.
This facility houses three Pelton turbines, with each turbine rated at 423 MW (~567,000 HP); note that the turbine acceptance testing process reported a maximum turbine output power of 449 MW each (~602,000 HP) due to better than expected efficiency and ideal test conditions. [1]
At the rated power of 423 MW each turbine operates at a head of ~1869 meters (6130 feet) and a flow rate of 25 cubic meters per second, with an efficiency in excess of 92% (~92.23%). The turbine assembly is a five-jet configuration; the stream of each jet is 184.7 mm (7.2716535 inches) in diameter with an exit velocity of 191.5 meters/second (628.28 ft/s). The kinetic energy of each of the 5 streams i.e. 1 from each jet) is approximately 92.16 MW (Q = 5 cubic meters per second, v = 191.5 m/s, H = 1869 m). The assembly rated pressure is 203.2 bars (2944 psi).
The combined flow rate for the three turbines is 75 cubic meters per second. The facility peak power production is ~1269 MW. The turbines and associated valves were designed and developed by VA Tech of Switzerland.
On December 12, 2000, at approximately 20:10, the Cleuson-Dixence penstock, feeding the Pelton turbines at Bieudron, ruptured at ~1234 meters AMSL (under more than 1000 meters of head). The failure appears to have been due to several factors including the poor strength of rock surrounding the penstock at the rupture location. The rupture was approximately 9 m long by 60 cm wide. The flow rate through the rupture was likely well in excess of 150 m3/s (5,300 cu ft/s). The ensuing rapid release of a very large quantity of high pressure water destroyed approximately 100 hectares (1 km²) of pastures, orchards, forest, as well as washing away several chalets and barns around Nendaz and Fey. Three people were killed. [2]
The Bieudron facility was inoperative after the accident; however, it became partially operational in December 2009, and fully operational in January 2010. Much investigation went into the accident resulting in the almost complete redesign of the penstock. Legal action is still in process and the root cause of the rupture is unknown.[ when? ]
However details [3] regarding the redesign are available. The redesign [4] calls for improvements in the pipe's lining as well as the addition of grouting around the penstock to reduce water flow between the penstock and the surrounding rock due to dynamic variation of the pipe diameter during operation (it expands due to water loading during operation then contracts when the load is removed, leaving a gap). The damaged section of the penstock was rerouted around the previous location to where new (undamaged) more stable rock is available. Construction on the redesigned penstock was completed in 2009. [5] Redesign considerations [6] include operational control of maximum agreed design limits under all conditions of assembly, design and service conditions (including water hammer pressure spikes).
The Pelton wheel or Pelton Turbine is an impulse-type water turbine invented by American inventor Lester Allan Pelton in the 1870s. The Pelton wheel extracts energy from the impulse of moving water, as opposed to water's dead weight like the traditional overshot water wheel. Many earlier variations of impulse turbines existed, but they were less efficient than Pelton's design. Water leaving those wheels typically still had high speed, carrying away much of the dynamic energy brought to the wheels. Pelton's paddle geometry was designed so that when the rim ran at half the speed of the water jet, the water left the wheel with very little speed; thus his design extracted almost all of the water's impulse energy—which made for a very efficient turbine.
A water turbine is a rotary machine that converts kinetic energy and potential energy of water into mechanical work.
The Kaplan turbine is a propeller-type water turbine which has adjustable blades. It was developed in 1913 by Austrian professor Viktor Kaplan, who combined automatically adjusted propeller blades with automatically adjusted wicket gates to achieve efficiency over a wide range of flow and water level.
The Grande Dixence Dam is a concrete gravity dam on the Dixence at the head of the Val d'Hérémence in the canton of Valais in Switzerland. At 285 m (935 ft) high, it is the tallest gravity dam in the world, seventh tallest dam overall, and the tallest dam in Europe. It is part of the Cleuson-Dixence Complex. With the primary purpose of hydroelectric power generation, the dam fuels four power stations, totaling the installed capacity to 2,069 MW, generating approximately 2,000 GWh annually, enough to power 400,000 Swiss households.
The Bath County Pumped Storage Station is a pumped storage hydroelectric power plant, which is described as the "largest battery in the world", with a maximum generation capacity of 3,003 MW, an average of 2,772 MW, and a total storage capacity of 24,000 MWh. The station is located in the northern corner of Bath County, Virginia, on the southeast side of the Eastern Continental Divide, which forms this section of the border between Virginia and West Virginia. The station consists of two reservoirs separated by about 1,260 feet (380 m) in elevation. It was the largest pumped-storage power station in the world until 2021, when it was surpassed by the Fengning Pumped Storage Power Station.
Micro hydro is a type of hydroelectric power that typically produces from 5 kW to 100 kW of electricity using the natural flow of water. Installations below 5 kW are called pico hydro. These installations can provide power to an isolated home or small community, or are sometimes connected to electric power networks, particularly where net metering is offered. There are many of these installations around the world, particularly in developing nations as they can provide an economical source of energy without the purchase of fuel. Micro hydro systems complement solar PV power systems because in many areas water flow, and thus available hydro power, is highest in the winter when solar energy is at a minimum. Micro hydro is frequently accomplished with a pelton wheel for high head, low flow water supply. The installation is often just a small dammed pool, at the top of a waterfall, with several hundred feet of pipe leading to a small generator housing. In low head sites, generally water wheels and Archimedes' screws are used.
The Robert-Bourassa generating station, formerly known as La Grande-2 (LG-2), is a hydroelectric power station on the La Grande River that is part of Hydro-Québec's James Bay Project in Canada. The station can generate 5,616 MW and its 16 units were gradually commissioned between 1979 and 1981. Annual generation is in the vicinity of 26500 GWh.
The Temenggor Dam or Temenggor Hydro-Electric Project or Temenggor Power Station is a dam in Gerik, Perak, Malaysia. It is located on Perak River about 200 km northeast of Ipoh. Construction of the dam impounded Temenggor Lake.
Ghazi-Barotha Hydropower Project is a 1,450 MW run-of-the-river hydropower, connected to the Indus River. It is located about 10 km (6.2 mi) west of Attock in the Punjab province and east of Haripur in the Khyber Pakhtunkhwa province of Pakistan. Construction of the project began in 1995. It consists of five generators, each possessing a maximum power generation capacity of 290 MW. The inauguration of the plant took place on 19 August 2003, presided over by the then President General Pervez Musharraf. It also saw the commissioning of the first two of the five generators i.e. Unit 1 and Unit 2. The last generator was commissioned on 6 April, 2004, and the project was completed by December the same year. It costed US$2.1 billion with funding from Pakistan's Water and Power Development Authority, the World Bank, Asian Development Bank, Japan Bank for International Cooperation, Kreditanstalt für Wiederaufbau, European Investment Bank and Islamic Development Bank.
Veresen Inc. was a Calgary, Alberta-based energy infrastructure company with three main lines of business: pipelines, natural gas and power generation. It was a publicly-traded company on the Toronto Stock Exchange, and was known as Fort Chicago Energy Partners L.P. In 2017, it was acquired by Pembina Pipeline for $9.7 billion.
The Salto Osório Hydroelectric Power Plant is a dam and hydroelectric power plant on the Iguazu River near Osório in Paraná, Brazil. It is the second dam upstream of the Iguazu Falls and was completed in 1979. The power station has a 1,078 MW capacity and is supplied with water by a rock-fill embankment dam.
The Salto Santiago Hydroelectric Power Plant is a dam and hydroelectric power plant on the Iguazu River near Santiago in Paraná, Brazil. It is the third dam upstream of the Iguazu Falls and was completed in 1979. The power station has a 1,420 MW capacity and is supplied with water by a rock-fill embankment dam.
The Lochaber hydroelectric scheme is a hydroelectric power generation project constructed in the Lochaber area of the western Scottish Highlands after the First World War. Like its predecessors at Kinlochleven and Foyers, it was designed to provide electricity for aluminium production, this time at Fort William.
The Punchiná Dam is an embankment dam on the Guatapé River 17 kilometres (11 mi) east of San Carlos in Antioquia Department, Colombia. The dam creates Punchiná Reservoir which is part of the 1,240 megawatts (1,660,000 hp) San Carlos Hydroelectric Power Plant. The power plant was completed in two 620 megawatts (830,000 hp) stages, the first was completed in 1984 and the second in 1987. It is the largest power station in Colombia.
Castaic Power Plant, also known as the Castaic Pumped-Storage Plant, is a seven unit pumped-storage hydroelectric plant, operated by the Los Angeles Department of Water and Power, which provides peak load power from the falling water on the West Branch of the California State Aqueduct. It is a cooperative venture between the LADWP and the Department of Water Resources of the State of California. An agreement between the two organizations was signed on September 2, 1966, for construction of the project.
The Bissorte Dam is a gravity dam in the Maurienne Valley, in Savoie, France, about 7 km (4.3 mi) east of Valmeinier. It was built from 1930 to 1935 to supply a hydroelectric plant capable of generating 75 megawatts (MW) of power.
The Snoqualmie Falls Hydroelectric Plant is located just north of Snoqualmie in King County, Washington state, US. It is situated about 22 mi (35 km) east of Seattle. Located just below the Snoqualmie Falls, the power plant consists of two power houses, Plant 1 and Plant 2. Plant 1 was completed in 1899 and is located underground. It is the first completely underground hydroelectric power plant ever built in the world. Plant 2 was built in 1910 and is located along the right bank of the Snoqualmie River. Both plants receive water from a small reservoir created by a weir atop the falls. Plant 1 has an installed capacity of 13.7 MW and Plant 2 a capacity of 40.2 MW for a total installed capacity of 53.9 MW, enough to power 40,000 homes.
The Vorotan Cascade, or the ContourGlobal Hydro Cascade, is a cascade on the Vorotan River in Syunik Province, Armenia. It was built to produce hydroelectric power and provide irrigation water. The Vorotan Cascade consists of three hydroelectric power plants and five reservoirs with a combined installed capacity of 404.2 MW. It is one of the main power generation complexes in Armenia.
The Tapovan Vishnugad Hydropower Plant is a 520 MW run-of-river hydroelectric project being constructed on Dhauliganga River in Chamoli District of Uttarakhand, India. The plant is expected to generate over 2.5 TWh of electricity annually.
The Kinlochleven hydroelectric scheme was built between 1905 and 1909 to supply power for an Aluminium smelter owned by British Aluminium. It was the second in Scotland after the 1896 Falls of Foyers scheme. The smelter and power house were constructed on the south bank of the River Leven in the village of Kinlochleven, in the south-west of the Scottish Highlands.