Bull bridge accident

Last updated

The Bull Bridge accident was a failure of a cast-iron bridge at Bullbridge, near Ambergate in Derbyshire on 26 September 1860. As a goods train was passing over the bridge at Bullbridge, the structure failed suddenly, causing the derailment of the majority of the wagons. There were no serious casualties, but it was a warning of the fundamental weakness of many such bridges on the British rail network.

Contents

The accident

The accident happened on the Midland Railway between Derby and Chesterfield, on the night of 26 September 1860. With visibility only about 10 yards (9.1 m) due to fog, the train was proceeding northwards at only 14 mph (23 km/h). It was a long train, with twenty-seven wagons loaded with salt, two loaded goods vans, and a brake van, hauled by a tender locomotive. The heavy load caused some slippage of the engine's driving wheels on the rail. Half a mile (800 m) beyond Ambergate station, the driver suddenly noticed that the engine's rear wheels were no longer on the rails. He shut off steam, stopped the engine and went to investigate. His tender was attached to only two wagons, and they were all off the rails too. There were two more wagons about 10 yards (9.1 m) behind, close to Bull bridge, a small viaduct over a local road. The next nine wagons behind were piled in a heap about 25 feet (7.6 m) high from the bottom of the road, reaching up to the telegraph wires by the side of the track. The guard in the brake van had been thrown headfirst against the front panel when the accident occurred but was not seriously hurt. All the wagons behind the bridge were still on the line.

Investigation

Section of broken girder Bull bridge1.jpg
Section of broken girder

When examined by the driver and fireman, one of the cast-iron girders of the bridge was found to have fractured, unusually, near to one of the abutments rather than at the centre of the beam. The track was supported by a pair of identical girders with Barlow rails cut to length laid across the inner flange, with asphalted ballast on top, just below the sleepers. When Captain Henry Whatley Tyler of the Railway Inspectorate examined the fracture surface, he found it rusted over, but the evidence of those who had seen it first showed just what had happened. The cast iron girder had broken vertically from an enormous defect in the web and flanges, where there was a complete gap between the sides. The girder was completely defective here, but why no one had spotted it before the accident remains a mystery. Tyler suggests that it may have grown from an internal void with time simply because such a defect would surely have been discovered either by the foundry or the builders. The girder had been installed 23 years before, in 1837, and should have supported a central load of 90 long tons (91,000 kg) if in good condition. The pair of girders should have supported a total load of 360 long tons (370,000 kg) distributed over all the structure, and Tyler stated that the girder was much bigger than was needed for the job. The engine weighed 31 long tons (31,000 kg) and the tender 18 long tons (18,000 kg).

The source of the defect remains unknown but may have been caused initially by a "cold shut," where the molten metal does not fuse during metal casting. It often occurs when two waves of fast cooling cast iron meet, but why it should have occurred only about 10 feet (3.0 m) from one end remains unknown. It could have grown with repeated loading from passing traffic, and Tyler thought it lucky that it had failed when a goods train passed, rather than a passenger train, when casualties would have been inevitable. So it is possible that fatigue had caused the failure by the steady growth of a brittle crack from the initial defect.

Implications

Together with the Wootton bridge collapse the following year in 1861, there should have been some concern within the railway companies about the number of cast-iron girders used as underbridges on railway lines. Engineers would also have been aware of the problems of cast iron in railway bridges after the failure of the Dee bridge in 1847. Whether or not such structures were inspected is unknown; it seems not, as several more collapses occurred some years later, at the Inverythan crash and the Norwood Junction rail accident in 1891. Thereafter, the vast majority of cast-iron underbridges on the rail network were eventually replaced by wrought iron or steel structures, although some cast-iron underbridges remain today, e.g. Robert Stephenson's High Level Bridge in Newcastle.

Related Research Articles

<span class="mw-page-title-main">Wagonway</span> Railway using horses to pull goods wagons

Wagonways, also known as horse-drawn railways and horse-drawn railroad consisted of the horses, equipment and tracks used for hauling wagons, which preceded steam-powered railways. The terms plateway, tramway, dramway, were used. The advantage of wagonways was that far bigger loads could be transported with the same power.

<span class="mw-page-title-main">Tay Bridge</span> Railway bridge across the River Tay, Scotland

The Tay Bridge carries rail traffic across the Firth of Tay in Scotland between Dundee and the suburb of Wormit in Fife. Its span is 2.75 miles. It is the second bridge to occupy the site.

<span class="mw-page-title-main">History of the railway track</span>

The railway track or permanent way is the elements of railway lines: generally the pairs of rails typically laid on the sleepers or ties embedded in ballast, intended to carry the ordinary trains of a railway. It is described as a permanent way because, in the earlier days of railway construction, contractors often laid a temporary track to transport spoil and materials about the site; when this work was substantially completed, the temporary track was taken up and the permanent way installed.

<span class="mw-page-title-main">High Level Bridge, River Tyne</span> Road-rail bridge in Tyneside, England

The High Level Bridge is a road and railway bridge spanning the River Tyne between Newcastle upon Tyne and Gateshead in North East England. It was built by the Hawks family from 5,050 tons of iron. George Hawks, Mayor of Gateshead, drove in the last key of the structure on 7 June 1849, and the bridge was officially opened by Queen Victoria later that year.

<span class="mw-page-title-main">Meigs Elevated Railway</span>

The Meigs Elevated Railway was an experimental but unsuccessful 19th century elevated steam-powered urban rapid transit system, often described as a monorail but technically pre-electric third rail. It was invented in the US by Josiah Vincent Meigs, of Lowell, Massachusetts, and was demonstrated from 1886 to 1894 in a suburb of Boston called East Cambridge.

<span class="mw-page-title-main">Little Eaton Gangway</span> British narrow gauge industrial wagonway (1795-1908)

The Little Eaton Gangway, officially the Derby Canal Railway, was a narrow gauge industrial wagonway serving the Derby Canal, in England, at Little Eaton in Derbyshire.

<span class="mw-page-title-main">Dee Bridge disaster</span> Railway accident

The Dee Bridge disaster was a rail accident that occurred on 24 May 1847 in Chester, England, that resulted in five fatalities. It revealed the weakness of cast iron beam bridges reinforced by wrought iron tie bars, and brought criticism of its designer, Robert Stephenson, the son of George Stephenson.

The Norwood Junction railway crash occurred on 1 May 1891, when a cast-iron underbridge over Portland Road, 60 yards (55 m) north-east of Norwood Junction railway station, fractured under the weight of an express train from Brighton to London Bridge.

<span class="mw-page-title-main">Wootton bridge collapse</span>

The Wootton bridge collapse occurred on 11 June 1861, when the rail bridge over the road between Leek Wootton and Hill Wootton in Warwickshire collapsed under the weight of a passing goods train on the line between Leamington Spa and Kenilworth owned by the London and North Western Railway Company. The train had passed over the bridge safely in the morning with a full load of coal, and was returning to Kenilworth with the empty wagons at 7 am. The 30 ton locomotive fell through the deck of the bridge onto the road below, and the tender crashed into the cab, killing both driver and fireman instantly. Many of the empty wagons behind were dragged into the gap to form a pile almost up to the height of nearby telegraph poles.

<span class="mw-page-title-main">Tay Bridge disaster</span> Bridge collapse and train wreck

The Tay Bridge disaster occurred during a violent European windstorm on Sunday 28 December 1879, when the first Tay Rail Bridge collapsed as a North British Railway (NBR) passenger train on the Edinburgh to Aberdeen Line from Burntisland bound for its final destination of Dundee passed over it, killing everybody on board. The bridge—designed by Sir Thomas Bouch—used lattice girders supported by iron piers, with cast iron columns and wrought iron cross-bracing. The piers were narrower and their cross-bracing was less extensive and robust than on previous similar designs by Bouch.

<span class="mw-page-title-main">Inverythan rail accident</span>

The Inverythan rail accident occurred when a faulty girder collapsed on a 39 by 15 ft single-track railway underbridge between Auchterless and Fyvie. The engine of the freight/passenger train crossed safely, but most of the train fell into the gap onto a road below.

<span class="mw-page-title-main">Howden rail accident</span>

The Howden rail accident in Yorkshire on 7 August 1840 killed five passengers. It occurred when a large piece of cargo, cast iron, fell from a wagon and derailed the following carriages. It happened on the Hull and Selby Railway as the train was travelling from Leeds to Hull. The crash was one of the first railway accidents to be investigated by the Railway Inspectorate. One of the worst accidents to have occurred on the new UK rail network, it was also a new phenomenon for the public; shipwrecks and coal mining accidents were more frequent.

A derailment of a night mail train from Scotland to London occurred on the North Eastern Railway when a tender axle suddenly fractured on 28 December 1869 near Dalton Junction, south of Darlington, England. There were only slight injuries among the staff, but the accident was a warning of the problem of premature axle failure.

<span class="mw-page-title-main">Rail profile</span> Cross sectional shape of a railway rail

The rail profile is the cross sectional shape of a railway rail, perpendicular to its length.

<span class="mw-page-title-main">Baulk road</span> Railway track on undergirding timber bearings

Baulk road is the name given to a type of railway track or 'rail road' that is formed using rails carried on continuous timber bearings, as opposed to the more familiar 'cross-sleeper' track that uses closely spaced sleepers or ties to give intermittent support to stronger rails.

The St. Neots Derailment 1895 occurred near to St. Neots railway station on 10 November 1895 when a Great Northern Railway Scottish express from Kings Cross encountered a broken rail.

<span class="mw-page-title-main">Merthyr Tramroad</span> Early Welsh railway line

The Merthyr Tramroad was a 9.75-mile-long (15.69 km) line that opened in 1802, connecting the private lines belonging to the Dowlais and Penydarren Ironworks with the Glamorganshire Canal at Abercynon, also serving the Plymouth Ironworks along the way. It is famous as the line, on which Richard Trevithick's experimental locomotive hauled the first train to carry a load. It was largely superseded when the Taff Vale Railway opened in 1841, and sections gradually went out of use over two decades, from about 1851.

<span class="mw-page-title-main">Surtees Rail Bridge</span> Rail-bridge over the River Tees, Northern England

The Surtees Rail Bridge is a rail bridge on the Tees Valley Line over the River Tees in the Borough of Stockton-on-Tees. The bridge is south of Stockton-on-Tees town centre and just north of the adjacent Surtees Bridge which carries the A66 road. The bridge is built on the site of a series of Tees Bridges alternating between two adjacent crossing sites.

<span class="mw-page-title-main">Murray River railway bridge, Albury–Wodonga</span> Bridge in New South Wales, Australia

The Murray River railway bridge is a heritage-listed Australian railway bridge over the Murray River on the Main Southern line south of Albury in the City of Albury, New South Wales, and on the North Eastern line north of Wodonga in Victoria. The bridge was designed by John Whitton and built from 1883 to 1884 by J. S. Bennett, with iron work supplied by Westwood, Baillie, England. It is also known as the Rail Bridge over Murray River, Albury–Wodonga and the Albury Lattice Railway Bridge and Murray River Underbridge. The bridge is owned by RailCorp, and maintained by the Australian Rail Track Corporation as part of its lease of the line. It was added to the New South Wales State Heritage Register on 2 April 1999, and added to the Register of the National Estate on 18 April 1989.

<span class="mw-page-title-main">Ultimo Road railway underbridge</span> Bridge in New South Wales, Australia

The Ultimo Road railway underbridge is a heritage-listed former railway bridge located on the former Darling Harbour goods railway line in the inner city Sydney suburb of Ultimo in the City of Sydney local government area of New South Wales, Australia. It was designed by engineering staff in the Existing Lines branch of the New South Wales Public Works Department and built in 1879. The property is owned by Transport Asset Holding Entity, an agency of the Government of New South Wales. It was added to the New South Wales State Heritage Register on 2 April 1999.