Buzzard oil field

Last updated
Buzzard Oil Field
Buzzard - North Sea Oil Rig sails (geograph 1832631).jpg
An oil platform departing Hartlepool for the Buzzard field in 2010
Country United Kingdom
Region North Sea
Offshore/onshoreoffshore
Operator CNOOC - 43%,
Partners Suncor Energy - 30%, BG Group - 22%, Edinburgh Oil & Gas - 5%
Field history
Discovery2001
Start of production2007
Peak year2009
Production
Current production of oil85,500 barrels per day (~4.26×10^6 t/a)
Year of current production of oil2020
Estimated oil in place1,500 million barrels (~2.0×10^8 t)

The Buzzard Oil Field is an oil field located in the North Sea Blocks 19/10, 19/5a, 20/6 and 20/1s. [1] It was discovered in 2001 by PanCanadian, and developed initially by PanCanadian's successor EnCana and then by Nexen. The oil field was initially operated and owned by Nexen which is now a subsidiary of China's CNOOC.

Contents

The field

The total proven reserves of the Buzzard oil field are 240 million cubic metres (1.5 billion barrels), and production will be centered on 28,670 cubic metres (180,300 bbl) per day. [2]

The Buzzard reservoir has a low gas/oil ratio and requires pressure maintenance through water injection. Buzzard’s oil consists of medium sour crude: 32.6° API, 1.4% sulphur. [3]

Infrastructure

The Buzzard field development comprises four bridge-linked steel platforms: the wellhead facilities (W) for up to 27 production wells, production facilities (P), a platform supporting accommodation and utilities (UQ) and an oil stripper platform (PS). [3]

Processing

The oil processing facilities comprise a 3-phase (oil/vapour/water) Production Separator. Oil from the separator flows to the 3-phase Second Stage Separartor. Oil from the latter is 'spiked' with Natural Gas Liquids (NGL) from the gas dewpointing plant, then injected with a hydrogen sulphide (H2S) scavenger chemical prior to metering and export. [4]

Produced water from the Second Stage Separator is recycled to the Production Separator, and from there to the produced water treatment facilities using hydrocyclones before overboard disposal. [4]

Vapour from the two Separators is compressed in an Offgas Compressor and a LP/HP compressor. Compressed gas passes through a Mercury Removal Bed and an Acid Gas Removal system, which uses a counter-current flow of amine solvent, and then through a Mercaptans Removal Bed. The gas is dehydrated in a gas dehydration system which uses a counter-current flow of glycol. After dehydration the gas is cooled and passes through a Joule-Thomson valve to reduce its pressure and hence its temperature to remove liquids and achieve a gas hydrocarbon dewpoint. Natural Gas Liquids are separated and co-mingled with the export oil stream. Gas is compressed in the HP Compressors, some is used as gas lift on the production wells, some as fuel gas, and the remainder is exported. [4]    

Export

Oil is exported from Buzzard via an 18 inch pipeline from the Buzzard processing platform to the nearest point in the Forties to Cruden Bay System, approximately 28 km away. Oil flows to Cruden Bay and then onto the Kinneil Terminal. First oil was produced in December 2006. [3]

Gas is exported via a 250 millimetres (10 in) pipeline from Buzzard to the Captain ‘T’ point on the UK Frigg pipeline 29 km away. From there the gas is transported to the St Fergus Gas Terminal. Fuel gas can also be imported onto Buzzard from the Frigg pipeline. [2]

Production history

Buzzard was the largest discovery in UK waters for 20 years when it was found in 2001 and went on to become the largest-producing field in the region after starting up in 2007.

Once at a peak of more than 35,000 cubic metres (220,000 barrels ) of oil equivalent per day in 2009, production has decreased to 13,590 cubic metres (85,500 barrels) of oil equivalent per day as of May 2020, according to Oil and Gas Authority (OGA) figures. [5]

Buzzard was temporarily shutdown twice in late 2019 for repairs to topside pipework. [6] [7]

Expansion

Buzzard Phase 2 is a bid to go after additional reserves to the north of the main field with a subsea development tied-back to it, with expected peak production of 5,900 cubic metres (37,000 barrels) of oil equivalent per day.

The first stage includes installation of a subsea manifold, a new processing module for the platform and drilling of four production wells. First oil from Buzzard Phase 2 was expected in late 2020 but as of August 2020, CNOOC postponed the project to 2021. Chrysaor stated that the drilling results for Buzzard Phase 2 was "towards the lower end of expectations," with the project now expected to come on stream in December 2021. [8]

Related Research Articles

Platform Name - Tern Alpha.

The Ninian Central Platform is an oil platform in the North Sea. When constructed in Loch Kishorn, Scotland in 1978 the 600,000 tonne platform was the world's largest man-made movable object before being towed to its current position and sunk to the sea floor.

The Clair oilfield is an offshore oil field in Scottish territorial waters 75 kilometres (47 mi) west of Shetland in water depths of up to 140 metres (460 ft). The field is the largest oilfield on the UK Continental Shelf with an estimated 8 billion barrels of oil-in-place, according to the BP Plc’s website. It extends over an area of some 220 square kilometres (85 sq mi), covering five licence blocks.

The Harding oilfield is a small oil field operated by TAQA, in the North Sea block 9/23b, approximately 200 miles (320 km) North-East of Aberdeen and in 110 metres (360 ft) of water.

The Everest gasfield is located in the Central North Sea, 233 kilometres (145 mi) east of Aberdeen, Scotland. It lies in the United Kingdom Continental Shelf blocks 22/9, 22/10a and 22/14a. The gasfield was discovered by Amoco in 1982 with first gas produced in 1993.

<span class="mw-page-title-main">Schiehallion oilfield</span>

The Schiehallion oilfield is a deepwater offshore oilfield approximately 175 kilometres (110 mi) west of the Shetland Islands in the North Atlantic Ocean. The Schiehallion and adjacent Loyal field were jointly developed by BP on behalf of the Schiehallion field partners; BP, Shell, Amerada Hess, Murphy Oil, Statoil and OMV, and the Loyal field partners; BP and Shell.

An oil production plant is a facility which processes production fluids from oil wells in order to separate out key components and prepare them for export. Typical oil well production fluids are a mixture of oil, gas and produced water. An oil production plant is distinct from an oil depot, which does not have processing facilities.

<span class="mw-page-title-main">Douglas Complex</span>

The Douglas Complex is a 54-metre (177 ft) high system of three linked platforms in the Irish Sea, 24 kilometres (15 mi) off the North Wales coast. The Douglas oil field was discovered in 1990, and production commenced in 1996. Now operated by Eni, the complex consists of the wellhead platform, which drills into the seabed, a processing platform, which separates oil, gas and water, and thirdly an accommodation platform, which is composed of living quarters for the crew. This accommodation module was formerly the Morecambe Flame jack-up drilling rig.

<span class="mw-page-title-main">Central Area Transmission System</span> Gas terminal in Seal Sands, Middlesbrough

The Central Area Transmission System is a natural gas transportation and processing system that transports natural gas through a 404 kilometre pipeline from the Central North Sea to a reception and processing terminal at Teesside in the North East of England.

<span class="mw-page-title-main">Bacton Gas Terminal</span> Gas terminal in Bacton

The Bacton Gas Terminal is a complex of six gas terminals within four sites located on the North Sea coast of North Norfolk in the United Kingdom. The sites are near Paston and between Bacton and Mundesley; the nearest town is North Walsham.

The Hutton oil field, located on the UK continental shelf, was the location for the first ever production Tension Leg Platform (TLP).

<span class="mw-page-title-main">Tyra Field</span>

Tyra Field is the largest gas condensate field in the Danish Sector of the North Sea. It was discovered in 1968 and production started in 1984. The field is owned by Dansk Undergrunds Consortium, a partnership between Total, Noreco and Nordsofonden, and operated by Total. The reservoir depth is about 2,000 metres (6,600 ft) and it covers area of 90 kilometres (56 mi) in the water depth of 37–40 metres (121–131 ft).

Gannet is an oil and gas field located in the United Kingdom's continental shelf in the North Sea. It is 180 km (110 mi) east of Aberdeen, and the water depth at the Gannet offshore installation is 95 m (312 ft). The field is located in Blocks 22/21, 22/25, 22/26 and 21/30. It is half-owned by Royal Dutch Shell (50%) and partly by ExxonMobil (50%) and has been operated by Shell UK Ltd since ‘first oil’ in November 1993. The Gannet A installation is the host platform for subsea tiebacks designated Gannet B to G. Like most Shell fields in the central and northern North Sea the field is named after a sea bird the gannet.

The Claymore oil field is located in Block 14/19 on the United Kingdom's Continental Shelf. It is 161 km (100 mi) northeast of Aberdeen in the Central North Sea. The field is named after a double-edged broadsword used by Highland Scots. Recoverable oil reserves were estimated to be 511 million barrels from an initial oil in place of 1452.9 million barrels. The field was developed through a large steel jacket platform standing in 110 m of water. A separate accommodation platform was installed in 1995. Fluid production was supported by gas lift and significant water injection. The production platform also supports production from the Scapa field, the Golden Eagle field and the Tartan field. Oil is exported to the Flotta terminal.

Alwyn North is a major oil and gas field in the United Kingdom sector of the northern North Sea, 160 km east of the Shetland Islands. The field was developed through two bridge-linked offshore platforms and a number of subsea satellite wellheads. Alwyn North has been producing oil and gas since 1987 and is still (2023) in operation.

The Beryl oil field is a major crude oil production field in the UK sector of the northern North Sea, 335 km north east of Aberdeen. Production of oil started in 1976 and the field is still producing oil and gas (2021).

The Clyde oil field is a crude oil producing field in the UK sector of the North Sea, 290 km east-south-east of Aberdeen. Production of oil started in 1987 and the field is still operational (2021).

<span class="mw-page-title-main">Ravenspurn gas fields</span>

The Ravenspurn gas fields are two adjacent natural gas fields located in the UK sector of the southern North Sea about 65 km east of Flambrough Head, Yorkshire.

The Lincolnshire Offshore Gas Gathering System (LOGGS) was a major natural gas collection, processing and transportation complex in the UK sector of the southern North Sea. It comprised five bridge-linked platforms about 118 km east of the Lincolnshire coast, which operated from 1988 to 2018. 

The Cleeton gas field and hub is a natural gas production, gathering, compression, treatment and transportation facility in the southern North Sea, 54 km east of Flamborough Head, Yorkshire. It has been producing and transmitting gas since 1988.

References

  1. "Offshore Oil and Gas Activity". Oil and Gas Authority. Archived from the original on 2019-01-26. Retrieved 25 November 2019.
  2. 1 2 "Hebron". nalcorenergy.com. 2012. Retrieved 2013-05-29.
  3. 1 2 3 "Offshore Technology - Buzzard Field". Offshore Technology. Archived from the original on 2004-11-03. Retrieved 24 November 2019.
  4. 1 2 3 Process Sketch Oil and Gas export (2006)
  5. "Updated: CNOOC postpones Buzzard Phase 2 project to extend life of North Sea mega-field - News for the Energy Sector". 25 August 2020.
  6. "Buzzard Oil Field shutdown for repairs". Energy Voice. 4 October 2019. Archived from the original on 2020-08-05. Retrieved 25 November 2019.
  7. "Buzzard oil field shutdown again as repairs compromised". Energy Voice. 21 October 2019. Archived from the original on 2019-10-22. Retrieved 25 November 2019.
  8. "North Sea producer Chrysaor eyes 2021 output drop, muted Buzzard production | S&P Global Platts". 16 December 2020.