Cost-plus-incentive fee

Last updated

A cost-plus-incentive fee (CPIF) contract is a cost-reimbursement contract which provides for an initially negotiated fee to be adjusted later by a formula based on the relationship of total allowable costs to total target costs. [1]

Contents

Like a cost-plus contract, the price paid by the buyer to the seller changes in relation to costs, in order to reduce the risks assumed by the contractor (seller). Unlike a cost-plus contract, the cost in excess of the target cost is only partially paid according to a buyer/seller ratio, so the seller's profit decreases when exceeding the target cost. Similarly, the seller's profit increases when actual costs are below the target cost defined in the contract.

According to the PMBOK (7th edition) by the Project Management Institute (PMI), CPIF is a "type of cost-reimbursable contract where the buyer reimburses the seller for the seller's allowable cost (allowable costs are defined by the contract), and the seller earns its profit if it meets defined performance criteria". [2]

Formula and Examples

Incentive contracts allow sharing of the risks between the contractor and the client. The contractor is reimbursed all its justifiable costs in addition to a calculated fee. The basic elements of a CPIF contract are:

  • Target Cost: the estimated total contract costs.
  • Actual Cost: constitutes the reasonable costs that the contractor can prove have been incurred.
  • Target Fee: the basic fee to be paid if the Target Cost matches the Actual Cost (target profit). The Target Fee varies between the Minimum Fee and the Maximum Fee according to a formula tied to the Actual Cost (e.g. Target Fee could be 10% of the Actual Cost).
  • Sharing Ratio: the agreed upon cost sharing proportion, normally expressed in percentage (e.g. 85% for the client / 15% for the contractor). It is often different for cost overruns and cost underruns.

Other components of incentive fee contracting include:

  • Maximum Fee: the highest fee that may be earned, usually expressed as a percentage.
  • Minimum Fee: the lowest fee that may be earned, usually expressed as a percentage.

The Final Fee (profit of the contractor) is expressed as follows: Final Fee = Target Fee + (Target Cost - Actual Cost) * Contractor Share. [lower-alpha 1] [3]

The Final Price of the contract is expressed as follows: Final Price = Actual Cost + Final Fee.

Note that if Contractor Share = 1, the contract is a Fixed Price Contract; if Contractor Share = 0, the contract is a cost plus fixed fee (CPFF) contract. [4]

For example, assume a CPIF with:

  • Target Cost = 1,000
  • Target Fee = 100
  • Benefit/Cost Sharing Ratio for cost overruns = 80% Client / 20% Contractor
  • Benefit/Cost Sharing Ratio for cost underruns = 60% Client / 40% Contractor

If the Actual Cost is higher than the Target Cost, say 1,100, the client will pay: 1,100 + 100 + (1,000 - 1,100) * 0.2 = 1,180 (contractor earns 80).

If the Actual Cost is lower than the Target Cost, say 900, the client will pay: 900 + 100 + (1,000 - 900) * 0.4 = 1,040 (contractor earns 140).

Notes

  1. In the formula, an asterisk ("*") is used for multiplication

Related Research Articles

Earned Value Management (EVM), earned value project management, or earned value performance management (EVPM) is a project management technique for measuring project performance and progress in an objective manner.

<span class="mw-page-title-main">Mergers and acquisitions</span> Type of corporate transaction

Mergers and acquisitions (M&A) are business transactions in which the ownership of companies, business organizations, or their operating units are transferred to or consolidated with another company or business organization. As an aspect of strategic management, M&A can allow enterprises to grow or downsize, and change the nature of their business or competitive position.

In finance, a put or put option is a derivative instrument in financial markets that gives the holder the right to sell an asset, at a specified price, by a specified date to the writer of the put. The purchase of a put option is interpreted as a negative sentiment about the future value of the underlying stock. The term "put" comes from the fact that the owner has the right to "put up for sale" the stock or index.

<span class="mw-page-title-main">Price</span> Amount of money given in order to purchase a thing or service

A price is the quantity of payment or compensation expected, required, or given by one party to another in return for goods or services. In some situations, the price of production has a different name. If the product is a "good" in the commercial exchange, the payment for this product will likely be called its "price". However, if the product is "service", there will be other possible names for this product's name. For example, the graph on the bottom will show some situations A good's price is influenced by production costs, supply of the desired item, and demand for the product. A price may be determined by a monopolist or may be imposed on the firm by market conditions.

Cost-plus pricing is a pricing strategy by which the selling price of a product is determined by adding a specific fixed percentage to the product's unit cost. Essentially, the markup percentage is a method of generating a particular desired rate of return. An alternative pricing method is value-based pricing.

Build–operate–transfer (BOT) or build–own–operate–transfer (BOOT) is a form of project delivery method, usually for large-scale infrastructure projects, wherein a private entity receives a concession from the public sector to finance, design, construct, own, and operate a facility stated in the concession contract. The private entity will have the right to operate it for a set period of time. This enables the project proponent to recover its investment and operating and maintenance expenses in the project.

Target costing is an approach to determine a product's life-cycle cost which should be sufficient to develop specified functionality and quality, while ensuring its desired profit. It involves setting a target cost by subtracting a desired profit margin from a competitive market price. A target cost is the maximum amount of cost that can be incurred on a product, however, the firm can still earn the required profit margin from that product at a particular selling price. Target costing decomposes the target cost from product level to component level. Through this decomposition, target costing spreads the competitive pressure faced by the company to product's designers and suppliers. Target costing consists of cost planning in the design phase of production as well as cost control throughout the resulting product life cycle. The cardinal rule of target costing is to never exceed the target cost. However, the focus of target costing is not to minimize costs, but to achieve a desired level of cost reduction determined by the target costing process.

Construction management (CM) aims to control the quality of a project's scope, time, and cost to maximize the project owner's satisfaction. It uses project management techniques and software to oversee the planning, design, construction and closeout of a construction safely, on time, on budget and within specifications.

A management contract is an arrangement under which operational control of an enterprise is vested by contract in a separate enterprise that performs the necessary managerial functions in return for a fee. Management contracts involve not just selling a method of doing things but actually doing them. A management contract can involve a wide range of functions such as technical operation of a production facility, management of personnel, accounting, marketing services, and training.

<span class="mw-page-title-main">Revenue recognition</span>

The revenue recognition principle is a cornerstone of accrual accounting together with the matching principle. They both determine the accounting period in which revenues and expenses are recognized. According to the principle, revenues are recognized when they are realized or realizable, and are earned, no matter when cash is received. In cash accounting—in contrast—revenues are recognized when cash is received no matter when goods or services are sold.

Closing costs are fees paid at the closing of a real estate transaction. This point in time called the closing is when the title to the property is conveyed (transferred) to the buyer. Closing costs are incurred by either the buyer or the seller.

A cost-plus contract, also termed a cost plus contract, is a contract such that a contractor is paid for all of its allowed expenses, plus additional payment to allow for a profit. Cost-reimbursement contracts contrast with fixed-price contract, in which the contractor is paid a negotiated amount regardless of incurred expenses.

Commissions are a form of variable-pay remuneration for services rendered or products sold. Commissions are a common way to motivate and reward salespeople. Commissions can also be designed to encourage specific sales behaviors. For example, commissions may be reduced when granting large discounts. Or commissions may be increased when selling certain products the organization wants to promote. Commissions are usually implemented within the framework on a sales incentive program, which can include one or multiple commission plans.

A guaranteed maximum price contract is a cost-type contract such that the contractor is compensated for actual costs incurred plus a fixed fee, limited to a maximum price. The contractor is responsible for cost overruns greater than the guaranteed maximum price, unless the GMP has been increased by a formal change order. Savings resulting from unexpectedly low costs are returned to the client.

<span class="mw-page-title-main">Point of total assumption</span>

The point of total assumption (PTA) is a point on the cost line of the profit-cost curve determined by the contract elements associated with a fixed price plus incentive-Firm Target (FPI) contract above which the seller effectively bears all the costs of a cost overrun. The seller bears all of the cost risk at PTA and beyond, due to a dollar for dollar decrease in profit beyond the costs at the PTA. In addition, once the costs on an FPI contract reach PTA, the maximum amount the buyer will pay is the ceiling price. Note, however, that between the cost at PTA and when the cost equals the ceiling price, the seller is still in a profitable position; only after costs exceed the ceiling price is the seller in a loss position.

Construction bidding is the process of submitting a proposal (tender) to undertake, or manage the undertaking of a construction project. The process starts with a cost estimate from blueprints and material take offs.

Budgeted cost of work performed (BCWP) also called earned value (EV), is the budgeted cost of work that has actually been performed in carrying out a scheduled task during a specific time period. The BCWP is the sum of the budgets for completed work packages and completed portions of open work packages, plus the applicable portion of the budgets for level of effort and apportioned effort.

In an open-book contract, the buyer and seller of work/services agree on (1) which costs are remunerable and (2) the margin that the supplier can add to these costs. The project is then invoiced to the customer based on the actual costs incurred plus the agreed margin. It is essentially the same as what is known as a cost-plus contract.

A fixed-price contract is a type of contract such that the payment amount does not depend on resources used or time expended by the contractor. This is opposed to a cost-plus contract, which is intended to cover the costs incurred by the contractor plus an additional amount for profit. Such a scheme is often used by military and government contractors to require vendors to incur the risk of cost overruns, and to control costs. However, historically when such contracts are used for innovative new projects with untested or undeveloped technologies, it often results in failure if costs greatly exceed the ability of the contractor to absorb unexpected cost overruns.

A construction contract is a mutual or legally binding agreement between two parties based on policies and conditions recorded in document form. The two parties involved are one or more property owners and one or more contractors. The owner, often referred to as the 'employer' or the 'client', has full authority to decide what type of contract should be used for a specific development to be constructed and to set out the legally-binding terms and conditions in a contractual agreement. A construction contract is an important document as it outlines the scope of work, risks, duration, duties, deliverables and legal rights of both the contractor and the owner.

References

  1. Federal Acquisition Regulations, 16.3—Cost-Reimbursement Contracts Archived 2009-09-15 at the Wayback Machine
  2. Project Management Institute 2021, Glossary §3 Definitions.
  3. Badenfelt, Ulrika. "The selection of sharing ratios in target cost contracts." Engineering, Construction and Architectural Management 15.1 (2008): 54-65
  4. Stephen Ward, Chris Chapman, Choosing contractor payment terms, International Journal of Project Management, Volume 12, Issue 4, November 1994, Pages 216-221, ISSN   0263-7863, doi : 10.1016/0263-7863(94)90045-0

Sources