Kaiseraugst Nuclear Power Plant

Last updated
Kaiseraugst Nuclear Power Plant
Kaiseraugst Nuclear Power Plant
Country Switzerland
Location Kaiseraugst (AG)
Coordinates 47°32′24″N7°44′56″E / 47.54000°N 7.74889°E / 47.54000; 7.74889
StatusProject abandoned
Construction began1974
Commission date never
Operator(s)Kernkraftwerk Kaiseraugst AG
Power generation
Units planned1 x 1,000 MW

The site for the Kaiseraugst Nuclear Power Plant is located in north-west Switzerland beside the river at Kaiseraugst, a short distance to the east of Basel.

Contents

Plans to build and operate the power plant were the subject of increasingly high-profile controversy over many years. The project failed because of bitter and ultimately effective opposition from the local population and because it became a cause célèbre for environmentalist pressure groups in Switzerland and across German speaking central Europe more generally. The matter hit the headlines most powerfully in 1975, with an eleven-week occupation of the site by a large number of people (estimated, initially, at around 15,000 people). The project was finally abandoned in 1988. [1]

History

The local energy generation company, Motor-Columbus, designed the Kaiseraugst Nuclear Power Plant in response to growing electricity consumption in Switzerland. In order to cover the perceived power generation shortfall as quickly as possible, attempts were made to accelerate the planning and authorization phases of the project. For political reasons the intended timetable turned out to be unachievable, however. In the end the planning phase lasted more than twenty years, and by 1988 the project had absorbed 1.3 billion Swiss francs. [1]

Protest 1975 ETH-BIB-Besetzung des Kernkraftwerkgelandes in Kaiseraugst (AG)-Com L24-0171-0129.tif
Protest 1975
Demonstration, ca. April 1975 ETH-BIB-Kaiseraugst, Atomkraftwerk, Demonstration und Parolen-Com LC0797-008.tif
Demonstration, ca. April 1975
Demonstration 1983 ETH-BIB-Kaiseraugst, Atomkraftwerk, Demonstration-Com LC2061-001-005.tif
Demonstration 1983

Opposition to the Kaiseraugst Nuclear Plant began early in the decade. In May 1970 the first Switzerland-wide organised opposition group to an atomic power plant project, the NAK, [2] was established. It later became better known as the NWA [3] [4]

A critical decision of the Federal Court was delivered in July 1973, when it was determined that the municipality of Kaiseraugst and the nearby urban canton of Basel-Stadt could not file a valid complaint against the project with the court. The court held that the constitutional position and the relevant legislation left the federal (i.e. national) state as the sole authorizing body in this case.

The federal authorities examined a range of scenarios, always focused on the need to secure national energy supplies. In the end they endorsed the Kaiseraugst Nuclear Plant, however. After this the project was rejected by many. At that time others saw things differently, however. Nationally the majority in Switzerland supported the use of nuclear power generation.

Outline permission to locate an 850 MW power station at Kaiseraugst was granted on 28 August 1972. There was also provision for repositioning the plant by 600 meters within the site in order to allow for the erection of cooling towers. Concrete project planning began in 1974. [1]

In April 1975 the site for the power plant was occupied by activists. This was the second such occupation, but this time it involved around 15,000 people which was enough to hamper excavation work, which had already started. In the end the start of the construction was delayed this time by eleven weeks as a result of resistance by the demonstrators. Less than four years later, in February 1979, the "Information Pavilion" for the planned nuclear power plant was blown up by militant project opponents. The force of the explosion also lifted into the air an Audi, parked nearby and belonging to Michael Kohn, president of Kernkraftwerke Gösgen AG and initiator of the power plant construction. [5]

On 28 October 1981 the Federal government mandated an upgrade, raising the output of the planned power plant from 900 to 1,000 MW. [1] Between 17 and 25 September 1985, three different reactor types were more closely considered, all three of them variously configured water cooled reactors: [6]

Two years later, in 1987, authorization was given for construction using an air cooled device, although the option of adding cooling towers had to remain open. Finally all the prerequisites were put in place for a comprehensive Emergency Plan, having regard to the Basel region's seismic record. The next stage, which could no longer be deferred, involved selecting a supplier for the reactor. That stage would never be completed, however, because a contract for a reactor was never signed. In 1988 the project was dropped on economic grounds. [1]

According to government figures the total loss to Kernkraftwerk Kaiseraugst AG had reached between 1.1 and 1.3 billion francs. [1]

See also

Related Research Articles

<span class="mw-page-title-main">Lucens reactor</span> Decommissioned experimental nuclear reactor in Lucens, Vaud, Switzerland

The Lucens reactor was a 6 MW experimental nuclear power reactor built next to Lucens, Vaud, Switzerland. After its connection to the electrical grid on 29 January 1968, the reactor only operated for a few months before it suffered an accident on 21 January 1969. The cause was a corrosion-induced loss of heat dispersal leading to the destruction of a pressure tube which caused an adjacent pressure tube to fail, and partial meltdown of the core, resulting in radioactive contamination of the cavern.

<span class="mw-page-title-main">Nuclear power phase-out</span> Discontinuation of usage of nuclear power for energy production

A nuclear power phase-out is the discontinuation of usage of nuclear power for energy production. Often initiated because of concerns about nuclear power, phase-outs usually include shutting down nuclear power plants and looking towards fossil fuels and renewable energy. Three nuclear accidents have influenced the discontinuation of nuclear power: the 1979 Three Mile Island partial nuclear meltdown in the United States, the 1986 Chernobyl disaster in the USSR, and the 2011 Fukushima nuclear disaster in Japan.

<span class="mw-page-title-main">THTR-300</span> Thorium nuclear reactor in Germany

The THTR-300 was a thorium cycle high-temperature nuclear reactor rated at 300 MW electric (THTR-300) in Hamm-Uentrop, Germany. It started operating in 1983, synchronized with the grid in 1985, operated at full power in February 1987 and was shut down September 1, 1989. The THTR-300 served as a prototype high-temperature reactor (HTR) to use the TRISO pebble fuel produced by the AVR, an experimental pebble bed operated by VEW. The THTR-300 cost €2.05 billion and was predicted to cost an additional €425 million through December 2009 in decommissioning and other associated costs. The German state of North Rhine Westphalia, Federal Republic of Germany, and Hochtemperatur-Kernkraftwerk GmbH (HKG) financed the THTR-300’s construction.

Nuclear power in Canada is provided by 19 commercial reactors with a net capacity of 13.5 gigawatt (GW), producing a total of 95.6 terawatt-hours (TWh) of electricity, which accounted for 16.6% of the country's total electric energy generation in 2015. All but one of these reactors are located in Ontario, where they produced 61% of the province's electricity in 2019. Seven smaller reactors are used for research and to produce radiopharmaceuticals for use in nuclear medicine.

<span class="mw-page-title-main">Nuclear power in France</span> Overview of nuclear power in France

Since the mid 1980s, the largest source of electricity in France has been nuclear power, with a generation of 379.5 TWh in 2019 and a total electricity production of 537.7 TWh. In 2018, the nuclear share was 71.67%, the highest percentage in the world.

<span class="mw-page-title-main">Nuclear power in Germany</span> Overview of nuclear power in Germany

Nuclear power was used in Germany from the 1960s until it was phased out in April 2023.

Nuclear power in Switzerland is generated by three nuclear power plants, with a total of four operational reactors (see list below). Nuclear power has contributed a steady fraction of around forty percent to the Swiss electricity production since 1985. In 2022, it produced 23 terawatt-hours (TWh) of electricity, and accounted for 37% of the nation's gross electricity generation of 62 TWh, while 55% was produced by hydroelectric plants and 8% came from conventional thermal power stations and non-hydro renewable energy sources.

<span class="mw-page-title-main">Beznau Nuclear Power Plant</span> Nuclear power plant in Canton of Aargau, Switzerland

The Beznau nuclear power plant is a nuclear power plant of the Swiss energy utility Axpo, located in the municipality Döttingen, Canton of Aargau, Switzerland, on an artificial island in the Aare river. The plant has been operating since September 1969.

<span class="mw-page-title-main">Gösgen Nuclear Power Plant</span> Nuclear power plant in Switzerland

The Gösgen Nuclear Power Plant is located in the Däniken municipality on a loop of the Aar river. It is operated by the ad hoc society Kernkraftwerk Gösgen-Däniken AG.

<span class="mw-page-title-main">Leibstadt Nuclear Power Plant</span>

The Leibstadt Nuclear Power Plant is located near Leibstadt, canton of Aargau, Switzerland, on the Rhine River and close to the border to Germany. Commissioned in 1984, it is the youngest and most powerful of the country's four operating reactors.

<span class="mw-page-title-main">Mühleberg Nuclear Power Plant</span> Nuclear power plant in Switzerland

The Mühleberg Nuclear Power Plant is a formerly operational nuclear power plant in the Mühleberg municipality in the Canton of Berne, Switzerland. Operated by BKW FMB Energie AG, the plant generated power from 6 November 1972 until 20 December 2019. Nuclear decommissioning of the plant began January 2020 and is currently forecasted to be completed by 2034.

<span class="mw-page-title-main">Obrigheim Nuclear Power Plant</span>

Obrigheim Nuclear Power Plant (KWO) is a nuclear power plant currently in the decommissioning phase. The plant is located in Obrigheim, Neckar-Odenwald-Kreis, on the banks of the Neckar and owned by EnBW. It operated a pressurized water reactor unit from 1969 to 2005. The defuelling process was completed in 2007, with spent fuel rods awaiting transport to an interim storage facility. In March 2017, EnBW tested the shipment of numerous castors by a barge on the Neckar to Neckarwestheim Nuclear Power Plant.

<span class="mw-page-title-main">Rheinsberg Nuclear Power Plant</span>

Rheinsberg Nuclear Power Station was the second nuclear reactor in East Germany after the Rossendorf Research Reactor, and the first nuclear power reactor in East Germany. It was built close to the city of Rheinsberg on the Stechlinsee. The power station was one of the first generation of demonstration power reactors.

<span class="mw-page-title-main">Mülheim-Kärlich Nuclear Power Plant</span>

The nuclear power station Mülheim-Kärlich lies on the Rhine, about 10 km northwest from Koblenz, close to the town Mülheim-Kärlich in Germany. The operating company was Société Luxembourgeoise de Centrales Nucléaires, a daughter company of RWE. It was the only nuclear power plant in the Rhineland-Palatinate after it was finished in 1986, however, due to problems with the building permit it only operated for 3 years and was taken offline in 1988. Subsequent attempts to bring the plant online continued until 1998 when the supreme court ruled for it to never be restarted.

In 2008, nuclear energy provided Switzerland with 40 percent of its electricity, but a survey of Swiss people found that only seven percent of respondents were totally in favor of energy production by nuclear power stations. Many large anti-nuclear demonstrations and protests have occurred over the years.

<span class="mw-page-title-main">Swiss Federal Nuclear Safety Inspectorate</span> Nuclear safety authority in Switzerland

The Swiss Federal Nuclear Safety Inspectorate is Switzerland's regulatory supervisory authority for nuclear safety and for the security of nuclear installations; it supervises the nuclear power plants at Beznau, Gösgen, Leibstadt and Mühleberg, the research reactors at the Paul Scherrer Institute, the University of Basel and the Swiss Federal Institute of Technology, as well as the Swiss national central interim storage facility for radioactive waste (ZWILAG). ENSI's headquarters are located in Brugg in the Canton of Aargau.

<span class="mw-page-title-main">Small modular reactor</span> Small nuclear reactors that could be manufactured in a factory and transported on site

Small modular reactors (SMRs) are a class of small nuclear fission reactors, designed to be built in a factory, shipped to operational sites for installation and then used to power buildings or other commercial operations. The first commercial SMR was invented by a team of nuclear scientists at Oregon State University (OSU) in 2007. Working with OSU's prototype, NuScale Power developed the first working model, available to the US market, in 2022. The term SMR refers to the size, capacity and modular construction. Reactor type and the nuclear processes may vary. Of the many SMR designs, the pressurized water reactor (PWR) is the most common. However, recently proposed SMR designs include: generation IV, thermal-neutron reactors, fast-neutron reactors, molten salt, and gas-cooled reactor models.

The Niederamt Nuclear Power Plant was the name for a planned nuclear power plant near the existing Gösgen Nuclear Power Plant in Niederamt in the Canton of Solothurn between Olten and Aarau in Switzerland. The land earmarked for the project would have taken in some of the residential areas of Niedergösgen, Gretzenbach and Däniken.

<span class="mw-page-title-main">Electricity sector in Switzerland</span> Overview of the electricity sector in Switzerland

The electricity sector in Switzerland relies mainly on hydroelectricity, since the Alps cover almost two-thirds of the country's land mass, providing many large mountain lakes and artificial reservoirs suited for hydro power. In addition, the water masses drained from the Swiss Alps are intensively used by run-of-the-river hydroelectricity (ROR). With 9,052 kWh per person in 2008, the country's electricity consumption is relatively high and was 22% above the European Union's average.

<span class="mw-page-title-main">Switzerland and weapons of mass destruction</span> Planned Swiss weapons of mass destruction

Switzerland made detailed plans to acquire and test nuclear weapons during the Cold War. Less than two weeks after the nuclear bombings of Hiroshima and Nagasaki, the Swiss government started studying the possibility of building nuclear weapons, and continued its military nuclear program for 43 years until 1988. It has since signed and ratified the Treaty on the Non-Proliferation of Nuclear Weapons. Switzerland never possessed biological weapons, but did have a program of the Swiss Army high command to develop and test chemical weapons.

References

  1. 1 2 3 4 5 6 Kernkraftwerk Kaiseraugst. Nichtrealisierung Archived 2016-06-03 at the Wayback Machine . Schweizer Nationalrat, Motion 88.334, eingereicht von Nationalrat Georg Stucky am 3. März 1988 mit Antwort des Bundesrates vom 28. September 1988. Dort Punkt 2.2.6 Die aufgelaufenen Kosten (retrieved 22 July 2008)
  2. Northwest Swiss Action Committee against the Kaiseraugst Nuclkaer Power Plant" ("Nordwestschweizer Aktionskomitee gegen das Atomkraftwerk Kaiseraugst")
  3. Its later name, slightly more succinctly, was the WNorthwest Swiss Action Committee against atomic power plants" ("Nordwestschweizer Aktionskomitee gegen Atomkraftwerke"). The name has subsequently been further simplified to "Nie wieder Atomkraftwerke" [Atomic power plants: never again].
  4. Historisches Lexikon der Schweiz: Antiatombewegung , accessed 30 September 2014.
  5. Beobachter: Der Mythos Kaiseraugst
  6. Archiv zur Geschichte der Kernenergie in der Schweiz (S. 142)