Punjab Thermal Power Plant

Last updated
Punjab Thermal Power Plant
Punjab Thermal Power Plant
Country
Location Haveli Bahadur Shah, Punjab
Coordinates 31°06′46″N72°11′15″E / 31.11278°N 72.18750°E / 31.11278; 72.18750
StatusOperational
Construction cost707.759 Million US $
Owner(s)
Operator(s)Punjab Thermal Power (Private) Limited (PTPL)
Combined cycle?Yes
Power generation
Units operational2 x 410 MW
1 x 443 MW
Nameplate capacity 1,263 MW
External links
Website punjabthermal.com

Punjab Thermal Power Plant is a 1,263 MW RLNG-based combined-cycle power plant. It is located near Trimmu Barrage, District Jhang in the province of Punjab, Pakistan. This is the second RLNG-based power project, after the 1,180 MW Bhikki Power Plant, which has been developed by the Government of Punjab through its own resources. Punjab Thermal Power Private Limited (PTPL), a company wholly owned by Government of Punjab is responsible for establishing and operating the power plant. The plant has two RLNG-based units of 410 MW each, while the third unit is a steam unit which has a capacity of 443 MW. The plant started simple-cycle commercial operations on 4 August 2022 by generating 810 MW of electricity from its two RLNG-based gas turbines. It started combined-cycle commercial operations in June 2023 and was inaugurated on 30 July 2023. [1] [2] [3]

See also

Related Research Articles

<span class="mw-page-title-main">NLC India Limited</span> Central Public Sector Undertaking

NLC India Limited (NLC) is a central public sector undertaking under the administrative control of the Ministry of Coal, Government of India. It annually produces about 30 million tonnes of lignite from opencast mines at Neyveli in the state of Tamil Nadu in southern India and at Barsingsar in Bikaner district of Rajasthan state. The lignite is used at pithead thermal power stations of 3640 MW installed capacity to produce electricity. Its joint venture has a 1000 MW thermal power station using coal. Lately, it has diversified into renewable energy production and installed 1404 MW solar power plant to produce electricity from photovoltaic (PV) cells and 51 MW electricity from windmills.

<span class="mw-page-title-main">CESC Limited</span> Electricity supply company in Kolkata, India

The Calcutta Electric Supply Corporation (CESC) is the Kolkata-based flagship company of the RP-Sanjiv Goenka Group, born from the erstwhile RPG Group, under the chairmanship of businessman Sanjiv Goenka. It is an Indian electricity generation and the sole distribution company serving 567 square kilometres (219 sq mi) of area administered by the Kolkata municipal corporation, in the city of Kolkata, as well as parts of Howrah, Hooghly, 24 Parganas (North) and 24 Parganas (South) districts in the state of West Bengal. It also serves power distribution in Kota, Bikaner and Bharatpur in Rajasthan under the name CESC RAJASTHAN. It serves 3.0 million consumers approximately, which includes domestic, industrial and commercial users.

<span class="mw-page-title-main">Hub Power Company</span> Electric power company in India

The Hub Power Company Limited, colloquially known as HUBCO, is the first and largest Independent Power Producer (IPP) in Pakistan, with a combined installed power generation capacity of 3,581 MW.

The Chashma Nuclear Power Plant is a large commercial nuclear power plant located at Chashma in Mianwali, Punjab, Pakistan.

<span class="mw-page-title-main">Punjab State Power Corporation</span> Indian government company

Punjab State Power Corporation Limited (PSPCL) is the electricity generating and distributing company of the Government of Punjab state in India. It was formerly known as Punjab State Electricity Board (PSEB) which was unbundled by the government of Punjab into two companies on 16 April 2010 as Punjab State Power Corporation Ltd. (POWERCOM) and Punjab State Transmission Corporation Ltd. (TRANSCO).

<span class="mw-page-title-main">Adani Power</span> Indian multinational Electricity company in Ahmedabad, India

Adani Power is an Indian multinational power and energy company, subsidiary of Adani Group and based in Khodiyar in Ahmedabad, India. It is a private thermal power producer, with a capacity of 15,250 MW and operates a mega solar plant of 40 MW at Naliya, Bitta, Kutch, Gujarat. Adani Godda Power is implementing a 1,600 MW plant at Jharkhand. The company has signed long term power purchase agreements of about 9,153 MW with the government of Gujarat, Maharashtra, Haryana, Rajasthan, Karnataka, and Punjab.

<span class="mw-page-title-main">NTPC Limited</span> National Thermal Power Corporation, Central Public Sector Undertaking coal mining

NTPC Limited, formerly known as National Thermal Power Corporation, is an Indian central Public Sector Undertaking (PSU) under the ownership of the Ministry of Power and the Government of India, who is engaged in the generation of electricity and other activities. The headquarters of the PSU are situated at New Delhi. NTPC's core function is the generation and distribution of electricity to State Electricity Boards in India. The body also undertakes consultancy and turnkey project contracts that involve engineering, project management, construction management, and operation and management of power plants.

Uch Power Plant is a combined cycle power plant, located in Dera Murad Jamali, Nasirabad District, Baluchistan, Pakistan. It has three GE frame 9E gas turbines, three Deltak HRSGs and one GE steam turbine which can generate an output of 560 MW. It is regarded as the best power plant in the region with an availability of 97% and above. Uch-I Power started its commercial operation in 2000. The plant is certified for compliance with ISO9001, ISO14001 and OHSAS 18001.

<span class="mw-page-title-main">Tatan Power Plant</span> Power plant in Guanyin, Taoyuan City, Taiwan

The Tatan Power Plant, Dah-Tarn Power Plant or Ta-Tan Power Plant is a gas-fired power plant in Guanyin District, Taoyuan City, Taiwan. At the capacity of 4,384 MW, the plant is the world's largest gas turbine combined cycle power plant and Taiwan's largest gas-fired power plant.

The Nandipur Power Project is a 425 MW combined cycle thermal power plant situated at Nandipur near Gujranwala in the Punjab province of Pakistan. Being constructed by the China Dongfang Electric Corporation, the project was completed in March 2015. The initial cost of the project was Rs. 27 billion, but this escalated during the revised project cycle-1 and totalled Rs. 58.42 bn at completion. The power plant faced a series of hiccups during and after launching its commercial operations. Prior and after construction, the project continued to attract a number of court cases, inquiries, investigations, audits, and political and commercial disputes. The plant collapsed after 5 days of operation, launching a series of inquiries ordered by then prime minister Nawaz Sharif.

<span class="mw-page-title-main">Jamshoro Power Station</span>

Jamshoro Thermal Power Station also known by other names such as GENCO-I, and TPS Jamshoro is a gas / furnace oil and coal based thermal power plant with a total installed capacity of 880 MW located in Jamshoro near Hyderabad, Sindh in Pakistan. It is operated by the Jamshoro Power Company. The first phase of the project was commissioned between 1989 and 1991. It consists of one 250 MW unit and three 210 MW units. The power station is undergoing a planned expansion with additional 2 x 660 MW coal fired units. One 660 MW unit has been constructed and is ready for commissioning. Site preparation of second 660 MW unit is in progress with an expected commissioning date of July 2029.

<span class="mw-page-title-main">GMR Vasavi Diesel Power Plant</span> Building in India

GMR Vasavi Diesel Power Plant, owned by GMR Power Corporation Limited, was a private-owned power plant located in Basin Bridge, Chennai. It was a 200-MW LSHS fuel power plant of the GMR Group. The plant was based on two-stroke diesel engine technology from MAN B&W, Germany. It was the state's first plant commissioned by the private sector. The plant was decommissioned in 2018.

The Quaid-e-Azam Solar Park is a photovoltaic power station in Bahawalpur, Punjab, Pakistan, named in honor of Quaid-e-Azam Muhammad Ali Jinnah, the Founder of Pakistan. It is a 400 MW solar facility spanning an area of 8 km2 and hosting 1.6 million solar modules. The initial phase of the project was constructed by the Government of Punjab through a 100% owned subsidiary QA Solar in May 2015 at a cost of $131 million. On 5 May 2015, the then Prime Minister of Pakistan Nawaz Sharif inaugurated the first 100 MW project and dedicated it to the nation. Subsequent expansion was done in public-private partnership with Appolo Solar Development Pakistan Limited, Best Green Energy Pakistan Limited and Crest Energy Pakistan Limited each installing a 100 MW unit. The next phase of 100 MW will be installed by Zorlu Solar Pakistan (Pvt.) Limited, making it a 500 MW facility. Total planned capacity of the solar park is 1,000 MW.

The Balloki Power Plant is a 1,223 MW natural gas power plant completed in mid 2018 in Pattoki, in the Punjab province of Pakistan. Groundbreaking was commenced on November 11, 2015, and construction was scheduled for completion by December 2017. The project utilizes regasified liquefied natural gas (RLNG) for fuel, with diesel as an alternate backup. A 40 kilometer long transmission line with a capacity of 500 kilovolts was also constructed between the new plant and a grid station in southern Lahore.

The Sahiwal Coal Power Project is a coal power plant project located in the province of Punjab in Pakistan by the name of Huaneng Shandong Ruyi (Pakistan) Energy (Limited). It has an installed capacity of 1320 MW. It commenced full operations on 3 July 2017.

The Payra 1320 MW thermal power plant is a 1,320 megawatt coal-fired power station built in Kalapara Upazila of Patuakhali District in southern Bangladesh. It is a joint venture between the North-West Power Generation Company Bangladesh Limited (NWPGCL) and China National Machinery Import and Export Corporation (CMC). Till May 2023, this plant was producing 700 to 1000 megawatts of electricity every day.

<span class="mw-page-title-main">Chief ministership of Shehbaz Sharif</span>

Shehbaz Sharif served the longest tenure in history as chief minister of Punjab spanning over 11 years of rule. His tenures involved the 1997 Nawaz Government, the 2008 Pakistan Peoples Party's regime and the 2013 PML-N's rule. His prominent contribution involves infrastructure development, transit projects and power plants. He has developed flyovers, road infrastructures, transit services and power projects. He is best known for his dedication, working speed, ability to execute mega projects and quick actions. However, he is also criticised over lack of priorities, spending development funds mostly in Lahore and large cities, keeping major power and assignments within himself, nepotism, conflict of interests, and misuse of authority by opposition parties.

The Bhikki Power Plant is a 1,180 MW RLNG based combined cycle power plant located near Sheikhupura, in the Punjab province of Pakistan. This is the first RLNG based power plant which is developed by Government of Punjab through its own resources. The plant is owned and operated by Quaid-e-Azam Thermal Power Limited (QATPL), a company wholly-owned by the government of Punjab. It is one of the three major RLNG power plants including Haveli Bahadur Shah and Balloki which were built between 2015 and 2018 to curb the electricity loadshedding in Pakistan. Letter of Intent (LOI) was issued on 13 May, 2015 and the project achieved its commercial operations in just 34 months on May 20, 2018.

References

  1. "PM inaugurates 1263MW thermal power plant project" . Retrieved 2023-07-30.
  2. "PPIB Annual Report 2020" (PDF). ppib.gov.pk. Retrieved 2022-07-25.
  3. "Chinese Company To Operate Two Units Of PTPL". nation.com.pk. Retrieved 2022-07-25.