Shetland HVDC Connection

Last updated

Shetland HVDC Connection
Shetland HVDC Connection
Map of Shetland HVDC Connection
Location
Country Scotland, United Kingdom
FromUpper Kergord Valley, Shetland
Passes throughNorth Sea
ToCaithness HVDC switching station, near Wick
Ownership information
Operator Scottish Hydro Electric Transmission
Construction information
CommissionedAugust 2024
Technical information
TypeSubmarine cable
Type of current HVDC
Total length260 km (160 mi)
Power rating600 MW
DC voltage+/-320 kV
No. of poles2 (Symmetrical monopole)
No. of circuits1

Shetland HVDC Connection is a high-voltage direct current submarine power cable connecting Shetland to the British mainland.

Contents

History

The project was proposed in 2007. [1] In January 2008, the report published by the Crown Estate found the project would be "economically and technically possible". [2] At the same year, Scottish Hydro Electric Transmission filed planning application and started public consultations. [3]

Originally, the cable was planned to run from Shetland to 320 km (200 miles) to Portgordon on the Scottish mainland, [3] [4] [5] and then on to Blackhillock substation, near Keith, Moray via 25 km (16-mile) underground cable. [3] [5] However, the end point was moved to Caithness, and the remaining part of the connection was constructed separately as the Caithness - Moray Link. [6]

In 2019, Ofgem announced that it was minded to authorise construction, subject to the Viking windfarm winning a CfD contract in the government auction held in September 2019. Viking Energy was unsuccessful in this auction, putting the future of the interconnector in doubt. [7] [8]

SSEN submitted a revised proposal in January 2020. Ofgem carried out a final consultation on this revised proposal, and concluded in April 2020 that it would grant conditional approval for the link, conditional on Ofgem receiving sufficient evidence by the end of 2020 that the 457 MW Viking Wind Farm project is likely to go ahead. [9]

In April 2020, Ofgem approved revised proposals for the project, subject to "evidence that the Shetland Viking Wind Farm project will go ahead". [9] On 17 June 2020, the Viking Wind Farm sponsor, SSE Renewables, made a final investment decision to proceed with the wind farm investment, conditional on certain indu stry code modifications, and "the outcome of the consultation on Ofgem’s minded-to position to approve the transmission link, expected in July 2020". [10] According to Shetland News, this meant that both the Windfarm and the HVDC Connection were "likely to go ahead". [11] On 16 July 2020, Ofgem gave final approval for the connection. [12]

Contracts for construction were awarded in August 2020 to Hitachi and BAM Nuttall. [13] In February 2022, Hitachi Energy started the process of installing HVDC equipment at Kergord. [14] Installation of the subsea cable started in July 2022. [15]

In April 2022, the project was described as "on track to be completed by 2024". [16] The subsea cable installation is ongoing, and expected to continue until 2023. [13] The first transmission of energy happened in June 2024, and the connection was commissioned in August of the same year. [17] [18]

Route

The interconnector starts at the Upper Kergord Valley converter station in Shetland. From the converter station an underground cable runs to a landing area in Weisdale Voe. From there, a subsea cable runs to landfall at Noss Head in Caithness, with onward connection to an HVDC switching station north of the village of Staxigoe in Caithness. [6] [19]

The route of the cable crosses TAT-10, TAT-14 and Atlantic Crossing 1 telecommunication cables and the PiperFlotta oil pipeline. [1]

Technical description

The interconnector will connect to the existing 320 kV Caithness - Moray Link to form a three terminal HVDC network, with converter stations at Spittal in Caithness; Blackhillock Substation in Moray; and Upper Kergord on Shetland. The Shetland leg will have a power rating of 600 MW; [9] the Spittal and Blackhillock converters are rated at 800 MW and 1,200 MW respectively. [20] This will be the first multi-terminal HVDC interconnection in Europe. [21]

Project developer

The project is being developed by Scottish Hydro Electric Transmission, a subsidiary of SSE plc.

Project economics

It is estimated that it will cost more than £600 million. [22] Another source stated cost of £660 million. [16]

The project is needed for development of Shetland's renewable energy potential and it is necessary for the projects such as the Viking Wind Farm. [23]

It also contributes to the security of Shetland's electricity supply, [22] especially as Lerwick Power Station is nearing the end of its operational life. [24]

See also

Related Research Articles

<span class="mw-page-title-main">National Grid (Great Britain)</span> High-voltage electric power transmission network in Great Britain

The National Grid is the high-voltage electric power transmission network supporting the UK's electricity market, connecting power stations and major substations, and ensuring that electricity generated anywhere on the grid can be used to satisfy demand elsewhere. The network serves the majority of Great Britain and some of the surrounding islands. It does not cover Northern Ireland, which is part of the Irish single electricity market.

<span class="mw-page-title-main">Keith, Moray</span> Town in Moray, Scotland

Keith is a small town in the Moray council area in north east Scotland. It has a population of 4,734.

<span class="mw-page-title-main">Moyle Interconnector</span> Electrical connection between Northern Ireland and Scotland

The Moyle Interconnector is a 500 megawatt (MW) HVDC link between Scotland and Northern Ireland, running between Auchencrosh in Ayrshire and Ballycronan More in County Antrim. It went into service in 2001 and is owned and operated by Mutual Energy.

Spittal is a small hamlet in Caithness, Scottish Highlands and is in the Scottish council area of Highland. Spittal lies 9 miles (14 km) south of Thurso, and 1.5 miles (2.4 km) north of Mybster. The main A9 road runs past Spittal.

<span class="mw-page-title-main">North Sea Link</span> Subsea electricity transmission line

The North Sea Link is a 1,400 MW high-voltage direct current submarine power cable between Norway and the United Kingdom.

The NorthConnect was a proposed 650 km (400-mile) 1,400 MW HVDC interconnector over the floor of the North Sea.

The Aegir wave farm was a planned wave farm off the south west of Shetland. The project was developed by Aegir Wave Power, a 2009 formed joint venture of Vattenfall and the wave power technology developer Pelamis Wave Power. The wave farm would have had capacity from 10 MW potentially up to 100 MW. Following the collapse of Pelamis in November 2014, the project was cancelled by Vattenfall in February 2015.

Viking Wind Farm is a large on-shore wind farm in the Shetland Islands which was developed by Viking Energy, a partnership between Shetland Islands Council and SSE plc. It has a generation capacity of 443 MW.

The Western HVDC Link is a high-voltage direct current (HVDC) undersea electrical link in the United Kingdom, between Hunterston in Western Scotland and Flintshire Bridge in North Wales, routed to the west of the Isle of Man. It has a transmission capacity of 2,250 MW and became fully operational in 2019.

<span class="mw-page-title-main">Viking Link</span> Submarine power cable between the UK and Denmark

Viking Link is a 1,400 MW HVDC submarine power cable between the United Kingdom and Denmark, which was completed in 2023. As of 2024, it is the longest land and subsea HVDC interconnector in the world. The project is a cooperation between British National Grid plc and Danish Energinet.

Nemo Link is a 1,000 MegaWatt HVDC submarine power cable between Richborough Energy Park in Kent, the United Kingdom and Zeebrugge, Belgium. The project is a joint venture between British National Grid and Belgian Elia. The 400 kV electrical interconnector is the first between the two countries, with an annual transmission capacity of 8.76 TWh. The link has been fully operational since 31 January 2019, and has transported 29 TWh during its first 5 years; 24.75 TWh to the UK and 4.25 to Belgium with an availability above 99%.

Scottish and Southern Electricity Networks is one of two energy companies in the UK to be involved both in electricity transmission and distribution.

<span class="mw-page-title-main">Blackhillock Substation</span> Electrical substation in Scotland

Blackhillock Substation is an electrical substation located in the north east of Scotland, near the town of Keith in Moray.

<span class="mw-page-title-main">Stornoway power station</span> Power station in Outer Hebrides, Scotland, UK

Stornoway power station, also known as Battery Point Power Station, is an electrical generation facility in Stornoway, Scotland. It was commissioned in 1954 to supply power to the Western Isles and currently comprises eight Mirrlees Blackstone, medium speed, diesel generators with a combined output of 25.5MW. The station is owned and operated by Scottish and Southern Electricity Networks (SSEN) part of SSE plc. The Western Isles power network was originally operated independently of the Scottish mainland network.

NeuConnect is an high-voltage direct current submarine power cable under construction since 2023 between the Isle of Grain, England and Wilhelmshaven Germany, expected to operate in 2028. It will be the first interconnector between the UK and Germany. The cost of £2.4 billion is financed by Meridiam from France, Allianz Capital Partners from Germany, Kansai Electric Power Company from Japan, and Tokyo Electric Power Company from Japan. The Chair of NeuConnect is Julia Prescot CBE.

The Caithness–Moray Link is a 160 km (100-mile) HVDC submarine power cable beneath the Moray Firth in Scotland, linking Spittal in Caithness and Blackhillock in Moray. Constructed by Scottish & Southern Electricity Networks, it is capable of transmitting up to 1,200 MW of power. It was officially completed in January 2019, under budget at a cost of £970 million, and was reported as the largest single investment in the northern Scottish electricity network since the 1950s.

The Western Isles HVDC connection is a proposed 1.8GW HVDC submarine power cable to connect the Isle of Lewis to the Scottish mainland.

<span class="mw-page-title-main">Eastern Green Links</span> Submarine power cables

Eastern Green Links are two planned submarine high voltage direct current power cables from the East coast of Scotland to Northeast England to strengthen the National Grid. The two links combined will deliver 4 GW of renewable energy from Scottish wind farms to England.

References

  1. 1 2 Assessment of the Grid Connection Options for the Scottish Islands (PDF) (Report). Highlands and Islands Enterprise. 27 March 2007. pp. 8–9, 37–38. Retrieved 9 April 2012.
  2. "Undersea power cable 'possible'". BBC News . 17 January 2008. Retrieved 9 April 2012.
  3. 1 2 3 Shetland HVDC Connection. Consultation Report (PDF) (Report). Scottish Hydro Electric Transmission Limited. July 2009. Retrieved 9 April 2012.
  4. Shetland HVDC Connection. Marine Environmental Appraisal Subsea Cable Summary (PDF) (Report). Scottish Hydro Electric Transmission Limited. July 2009. Retrieved 9 April 2012.
  5. 1 2 Keeping the lights on and supporting the growth. A consultation of our plans for the next decade (PDF) (Report). Scottish Hydro Electric Transmission Limited. p. 26. Retrieved 9 April 2012.
  6. 1 2 "Caithness HVDC switching station - To enable a proposed subsea transmission cable from Shetland to connect to the network, we are proposing to construct an HVDC switching station north of Wick in Caithness". SSEN. Retrieved 31 May 2021.
  7. "'Disappointed' but still 'committed' – Viking Energy reacts to CfD decision". Shetland Times. 20 September 2019. Retrieved 27 October 2019.
  8. "Update on the SWW Final Needs Case for the Shetland electricity transmission project and potential next steps" (PDF). OfGEM. 23 October 2019. Retrieved 27 October 2019.
  9. 1 2 3 "Ofgem approves 600MW Shetland transmission link". Ofgem. 23 April 2020. Retrieved 23 April 2020.
  10. "Viking approval secures £580m green recovery investment". Viking Energy. 17 June 2020. Retrieved 18 June 2020.
  11. Chris Cope (17 June 2020). "Viking Energy wind farm looks set to go ahead as SSE agrees to proceed with £580m project". Shetland News. Retrieved 18 June 2020.
  12. "Major Shetland subsea power cable to mainland approved". BBC News. BBC. 16 July 2020. Retrieved 16 July 2020.
  13. 1 2 "Final milestone for Shetland HVDC link complete following appointment of main contractors". 3 August 2020. Retrieved 15 August 2020.
  14. "Shetland Project Newsletter Issue 6" (PDF). SSEN Projects: Shetland. SSEN. 15 June 2022. Retrieved 15 July 2022.
  15. "Undersea cable laid to link Shetland to UK energy grid". BBC News - NE Orkney and Shetland. BBC. 8 July 2022. Retrieved 31 August 2022.
  16. 1 2 "Shetland HVDC link striding forwards". SSEN: Press releases. 18 April 2022. Retrieved 15 July 2022.
  17. Skopljak, Nadja (24 June 2024). "Shetland HVDC Link transmits first power ahead of full commissioning later this summer".
  18. "New Shetland windfarm could power nearly 500,000 homes". BBC News. 28 August 2024.
  19. "Caithness HVDC Switching Station". Scottish and Southern Electricity Networks. Retrieved 23 April 2020.
  20. "Caithness Moray HVDC Link". ABB corporate website. ABB. Retrieved 24 April 2020.
  21. "First multi-terminal HVDC interconnection in Europe will boost renewable energy and enhance power security". Press release. Hitachi ABB. 3 August 2020. Retrieved 15 August 2020.
  22. 1 2 "Ofgem backs Shetland subsea power cable plans". BBC News / Orkney and Shetland. BBC. 23 April 2020. Retrieved 23 April 2020.
  23. "Ofgem approves 600MW Shetland transmission link". Ofgem. 23 April 2020. Retrieved 31 October 2023.
  24. "Ofgem consultation on the costs of the new energy solution for Shetland". Scottish and Southern Electricity Networks. Retrieved 25 April 2020.