In industrial engineering, the standard time

Standard time =normal time +allowance Where; normal time =avg time *rating factor. (take rating factor between 1.1 and 1.1)

Contents

Usage of the standard time

Time times for all operations are known.

Techniques to establish a standard time

The standard time can be determined using the following techniques: [1]

  1. Time study
  2. Predetermined motion time system aka PMTS or PTS
  3. Standard data system
  4. Work sampling

Method of calculation

The Standard Time is the product of three factors:

  1. Observed time: The time measured to complete the task.
  2. Performance rating factor: The pace the person is working at. 90% is working slower than normal, 110% is working faster than normal, 100% is normal. This factor is calculated by an experienced worker who is trained to observe and determine the rating.
  3. Personal, fatigue, and delay (PFD) allowance.

The standard time can then be calculated by using: [2]

Related Research Articles

Horsepower Unit of power with different values

Horsepower (hp) is a unit of measurement of power, or the rate at which work is done, usually in reference to the output of engines or motors. There are many different standards and types of horsepower. Two common definitions used today are the mechanical horsepower, which is about 745.7 watts and the metric horsepower, which is approximately 735.5 watts.

Efficiency factor is a ratio of some measure of performance to an expected value.

Elo rating system Method for calculating the relative skill levels of players in zero-sum games such as chess

The Elo rating system is a method for calculating the relative skill levels of players in zero-sum games such as chess. It is named after its creator Arpad Elo, a Hungarian-American physics professor.

Material requirements planning (MRP) is a production planning, scheduling, and inventory control system used to manage manufacturing processes. Most MRP systems are software-based, but it is possible to conduct MRP by hand as well.

Time and motion study

A time and motion study is a business efficiency technique combining the Time Study work of Frederick Winslow Taylor with the Motion Study work of Frank and Lillian Gilbreth. It is a major part of scientific management (Taylorism). After its first introduction, time study developed in the direction of establishing standard times, while motion study evolved into a technique for improving work methods. The two techniques became integrated and refined into a widely accepted method applicable to the improvement and upgrading of work systems. This integrated approach to work system improvement is known as methods engineering and it is applied today to industrial as well as service organizations, including banks, schools and hospitals.

A predetermined motion time system (PMTS) is frequently used to perform Labor Minute Costing in order to set piece-rates, wage-rates and/or incentives in labor (labour) oriented industries by quantifying the amount of time required to perform specific tasks under defined conditions. Today the PMTS is mainly used in work measurement for shorter cycles in labour oriented industries such as apparel and footwear. This topic comes under wider industrial and production engineering.

Operations management In business operations, controlling the process of production of goods

Operations management is an area of management concerned with designing and controlling the process of production and redesigning business operations in the production of goods or services. It involves the responsibility of ensuring that business operations are efficient in terms of using as few resources as needed and effective in meeting customer requirements.

Safety stock is a term used by logisticians to describe a level of extra stock that is maintained to mitigate risk of stockouts caused by uncertainties in supply and demand. Adequate safety stock levels permit business operations to proceed according to their plans. Safety stock is held when uncertainty exists in demand, supply, or manufacturing yield, and serves as an insurance against stockouts.

Pilot plant

A pilot plant is a pre-commercial production system that employs new production technology and/or produces small volumes of new technology-based products, mainly for the purpose of learning about the new technology. The knowledge obtained is then used for design of full-scale production systems and commercial products, as well as for identification of further research objectives and support of investment decisions. Other (non-technical) purposes include gaining public support for new technologies and questioning government regulations. Pilot plant is a relative term in the sense that pilot plants are typically smaller than full-scale production plants, but are built in a range of sizes. Also, as pilot plants are intended for learning, they typically are more flexible, possibly at the expense of economy. Some pilot plants are built in laboratories using stock lab equipment, while others require substantial engineering efforts, cost millions of dollars, and are custom-assembled and fabricated from process equipment, instrumentation and piping. They can also be used to train personnel for a full-scale plant. Pilot plants tend to be smaller compared to demonstration plants.

Human processor model or MHP is a cognitive modeling method developed by Stuart K. Card, Thomas P. Moran, & Allen Newell (1983) used to calculate how long it takes to perform a certain task. Other cognitive modeling methods include parallel design, GOMS, and keystroke-level model (KLM).

A safety instrumented system (SIS) consists of an engineered set of hardware and software controls which are especially used on critical process systems.

Reservoir simulation Using computer models to predict the flow of fluids through porous media

Reservoir simulation is an area of reservoir engineering in which computer models are used to predict the flow of fluids through porous media.

Methods-Time Measurement (MTM) is a predetermined motion time system that is used primarily in industrial settings to analyze the methods used to perform any manual operation or task and, as a product of that analysis, set the standard time in which a worker should complete that task.

Work measurement is the application of techniques which is designed to establish the time for an average worker to carry out a specified manufacturing task at a defined level of performance. It is concerned with the duration of time it takes to complete a work task assigned to a specific job. It means the time taken to complete one unit of work or operation it also that the work should completely complete in a complete basis under certain circumstances which take into account of accountants time

Industrial engineering Branch of engineering which deals with the optimization of complex processes or systems

Industrial Engineering is an engineering profession that is concerned with the optimization of complex processes, systems, or organizations by developing, improving and implementing integrated systems of people, money, knowledge, information and equipment. Industrial engineering is central to manufacturing operations.

Standard time is the amount of time that should be allowed for an average worker to process one work unit using the standard method and working at a normal pace. The standard time includes some additional time, called the contingency allowance, to provide for the worker's personal needs, fatigue, and unavoidable delays during the shift.

Performance rating is the step in the work measurement in which the analyst observes the worker's performance and records a value representing that performance relative to the analyst's concept of standard performance.

PFD allowance in work systems is the adjustment done to the normal time to obtain the standard time for the purpose of recovering the lost time due to personal needs, fatigue, and unavoidable delays. By providing a small increase to the normal time in each cycle, a worker can still be able to cover lost time and complete the work assigned to him or her.

Human factors and ergonomics Designing systems to suit their users

Human factors and ergonomics is the application of psychological and physiological principles to the engineering and design of products, processes, and systems. Four primary goals of human factors learning are to reduce human error, increase productivity, and enhance safety, system availability and comfort with a specific focus on the interaction between the human and the engineered system.

Production planning

Production planning is the planning of production and manufacturing modules in a company or industry. It utilizes the resource allocation of activities of employees, materials and production capacity, in order to serve different customers.