The Crescent Development Project | |
---|---|
General information | |
Status | Completed |
Type | office, residential, hotel, shopping mall [1] [2] [3] |
Location | Baku, Azerbaijan |
Construction started | October 2009 |
Estimated completion | 2022 |
Opening | 2023 |
Owner | Gilan Construction |
Height | |
Roof | The Crescent City 210 m (690 ft) [4] The Crescent Place 170 m (560 ft) [5] Crescent Hotel 166 m (545 ft) [6] |
Technical details | |
Floor count | 43 (Crescent City) [4] 32 (28+4) (Crescent Hotel) [7] |
Design and construction | |
Architect(s) | DSA Architects International [8] / Heerim Architects & Planners Co. Ltd. |
Main contractor | Gilan Holding |
The Crescent Development Project or The Crescent Bay (formerly known as Caspian Plus) is skyscraper complex which is under construction on the Caspian Sea coast in Baku, Azerbaijan.
The complex comprises an offshore hotel (Crescent Hotel), office tower (Crescent City), residential tower, and a retail and entertainment centre (Crescent Place). The project is intended to be an architectural landmark. [9]
In February 2008, skyscrapernews.com, a well-known architectural review website, published an article about two projects designed by the Korean company, Heerim Architects, for construction in Baku. The projects, both with a lunar theme, were described as, "an attempt to reinvent the concept of the skyscraper beyond the traditional". [10] The article described two skyscraper complexes, proposed for construction on neighbouring peninsulas, on opposite shores of Baku Bay. The first, Full Moon Bay, was to be constructed on the western side of the bay. It included a 158-meter, 35-storey, discoid hotel called "Palace of the Winds 1 and 2". [10] The second complex, "Caspian Plus", had been proposed for construction on the eastern edge of Baku Bay near the seaport, acting as a counterpoint to "Full Moon Bay". Initially, the second project included a 32-storey crescent-shaped hotel (standing on its "horns" offshore), four high-rise residential buildings, and a 43-story business centre standing 203 metres tall (now called Crescent City Tower). [10] The fate of the related projects remained uncertain until October 2009 when foundation work in the location of the "Caspian Plus" complex was started.[ citation needed ]
The project has since been modified. A trio of high-rise residential buildings was removed to avoid visual overlapping of two other buildings (Port Baku Towers and Port Baku Residence). After modification, the project consisted of a hotel ("The Crescent Hotel"), an office tower ("The Crescent City"), and a high-rise residential building with a podium ("The Crescent Place"). The previous name of the project, "Caspian Plus", was changed to "The Crescent Development Project". [11]
The project Full Moon Bay was cancelled.
The "Crescent Development Project" is situated with one part on the waterfront of Baku. An offshore part, which includes "The Crescent Hotel", will be located on an artificial island about 170 metres from shore. There will be an office tower ("The Crescent City"), and a residential high-rise building with a podium ("The Crescent Place"), on the coastline behind "The Crescent Hotel".
"The Crescent Hotel" is a curving arched building. It is designed to look like a crescent moon with its points on the surface of the Caspian Sea. The crescent shape of the building refers to one of the symbols of Azerbaijan, depicted on its national flag. The skyscraper’s arcuate configuration will not affect the interior of the hotel as the building will rely on two multi-storey column-like towers, which will create additional space and act as a support for the hotel. [10] These supporting towers are called Eastern and Western in accordance with their location. "The Crescent Hotel" comprises 32 floors (28 storeys of the hotel itself standing over a 4-storeys podium). [7] [12] Upon completion, the hotel will comprise 230 guest rooms, 74 apartments and 16 villas. The total area is 177,969 m²2, [7] parking is planned for 601 cars. [10] "The Crescent Hotel" will be connected to the shore and other buildings of the project via a bridge. This hotel is planned to be a 'seven-star' facility. [13]
The office tower, “The Crescent City”, is a 210-metre skyscraper with 43 overground levels. [4] [10] It is being built behind "The Crescent Hotel" on the waterfront next to the seaport of Baku and the “JW Marriott Absheron”. According to the project design, the facade of the building is cylindrical and slightly flattened at the north-south direction. The bottom of the tower is narrow and widens as it approaches the top which includes a concave notch. The shape of "The Crescent City" is designed to resemble a torch.
"The Crescent Place" consists of 3 basement floors and 32 overground levels: a 5-storey podium, 2 floors of town houses and a 25-storey residential tower with 2 additional penthouse levels. The Crescent Place will be located onshore next to the tower of "The Crescent City". This residential building, standing 170 metres tall, will include 168 apartments. [14] The total area of the Crescent Place is 273 000 m², with space for approximately 100 retail outlets and an additional 40 food and beverage units.
According to a report published by the management company, almost all piling work for the project had been completed by November 2013. Nine percent of the entire project had been constructed. Ten percent of the coastal part of the Project had been completed. [15]
In July 2015, DSA Architects International was appointed to take over multidisciplinary lead consultancy design services on the Crescent Development Project, with construction works ongoing.
The plot for "The Crescent Hotel" lies within an area in the Caspian Sea. In May 2012, hehe setting was started. These piles were installed in two rows around the perimeter of the future hotel's location.[ citation needed ] A double metal fence was then installed around the site which restricted any additional water entering the area.[ citation needed ] Once the fence was completed, water was pumped from the site, and it was filled with sand to create the foundation of the building.[ citation needed ] As of early 2013, the soil creating the artificial island has been formed, and foundation work for the Western and Eastern towers is completed. [16] The piles constructed for "The Crescent Hotel", with a diameter 1500–2000 mm and a length 76.1 meters, are the biggest ever built in Azerbaijan. It was planned to build 464 piles by the end of 2013. [17] [18] By the beginning of 2015, development of both the Eastern and Western Towers had begun on the artificial island.
Given the complexity of the building’s geometry, a number of contracting companies from the world-wide were engaged in the construction. Many of them faced challenges in achieving their goals. So, Derby Design Engineering cited that the main challenge was to design a constructible solution for the link-bridge between the column-like towers. This arch has a span of 90 meters which supports 5 hotel levels, hanging off the link-bridge truss. [19] The Koltay Facades website stated that curved sides of the hotel represent an exciting challenge for engineers and designers; floor by floor, the slope of the glass is changing, and so are the components of the reaction forces on the slab, the appearance of the glass, the safety requirements, amongst the others. [8]
Construction of the onshore foundation started in October 2009. For all parts of the coastline (sites of "The Crescent City" and "The Crescent Place"), 691 short piles with a diameter of 1.2 m and a depth of 26 meters have been installed . [20] For the tower “The Crescent city” 118 deep piles (diameter 1500 mm, depth of 52-61,5 meters) were constructed. [21] [22]
By November 2013, 4 taps had been installed on the site of "The Crescent Place". The first floors of the podium were appearing above the fence. The construction of the residential tower, "The Crescent Place", had been started.[ citation needed ] By the beginning of 2015, 35th floor of The Crescent Place Tower was being constructed.
By March 2014, the foundation of "Crescent City Tower" had been ready for concrete core pouring.[ citation needed ] As of beginning 2015, The Crescent City Tower was being constructed at 16-17 levels. In August 2015, the concrete core of the building reached up to the 30th level. By December 2015, the 43rd level of the concrete core of the Crescent City was completed.
According to a spokesman of Ilk Construction, completion of the shell and core of "The Crescent Place" is scheduled for January 2015; the site of "The Crescent City" must be finished by May of the same year. [6] Completion of the entire project was planned for the second half of 2017 but as of February 2019, technical difficulties have prevented the completion of the arch section that will ultimately join the two towers. The completion date is currently estimated as late 2020.(Update) The date of completion is unknown. [23]
The JW Marriott Marquis Dubai Hotel is the world's second tallest hotel, a 72-storey, 355 m (1,165 ft) twin-tower skyscraper complex in Dubai, United Arab Emirates. The AED1.8 billion complex features a 1,608-room hotel run by Marriott International.
The Burj Al Alam was a proposed 108-story, 510 m (1,670 ft) hyperboloid skyscraper in the Business Bay area of Dubai, United Arab Emirates, though the project's roots are in a 101-storey design called "Fortune 101" and slated for the Dubai Marina area. It was designed to resemble a crystal flower. If constructed, it would have become one of the world's tallest buildings. The tower was one of the projects of the Fortune Group, which has a number of other projects in Dubai such as the Fortune Bay and Fortune Tower.
The Marina Torch, also known as Dubai Torch, Dubai Torch Tower, and The Torch, is a residential skyscraper in Dubai Marina in Dubai, United Arab Emirates. It is 352 metres (1,155 ft) tall, with 86 floors above ground and 4 below, and was the tallest residential building in the world on its completion in 2011, surpassing Q1 in Gold Coast, Australia.
Business Bay is a central business district under construction in Dubai, United Arab Emirates. The project features numerous skyscrapers located in an area where Dubai Creek has been dredged and extended, and located immediately south of Downtown Dubai. Business Bay will have upwards of 240 buildings, comprising commercial and residential developments. The infrastructure of Business Bay has been completed in 2008, and the entire development was expected to be completed between 2012-2015. Business Bay is part of the vision of His Highness Sheikh Mohammed Bin Rashed Al Maktoum, UAE Vice President, Prime Minister, Minister of Defence, and Ruler of Dubai. Business Bay will be a new 'city' within the city of Dubai and is being built as a commercial, residential and business cluster along a new extension of Dubai Creek extending from Ras Al Khor to Sheikh Zayed Road. Covering an area of 64,000,000 square feet (5,900,000 m2), it is composed of office and residential towers set in landscaped gardens with a network of roads, pathways and canals.
One Bayfront Plaza is a proposed supertall skyscraper in Miami, Florida, U.S. The building, construction of which has been approved, would stand at 1,049 feet (320 m), with 93 floors,[A] becoming the tallest building in Miami and Florida. One Bayfront Plaza would primarily consist of offices and hotel space, but also would include a retail mall, condominiums, and parking garage on the lower levels, as well as possibly an observation deck at the top. The entire project consists of over 1,400,000 square feet (100,000 m2) of Class A office and hotel space, as well as a total building area of over 4,000,000 square feet (371,612 m2) including the large podium. One Bayfront Plaza is the first skyscraper over 1,000 feet (305 m) to be approved for construction in Miami. The building's primary advocate is real estate developer Tibor Hollo, who has won several awards for his 55 years as a developer in Miami, and is currently the president of Florida East Coast Realty.
The architecture of Azerbaijan refers to the architecture development in Azerbaijan.
International Plaza is a high-rise commercial and residential building at 10 Anson Road in Tanjong Pagar, within the Downtown Core of Singapore, next to Tanjong Pagar MRT station on the East West line.
One Bloor, previously One Bloor East and Number One Bloor, is a mixed-use skyscraper at the intersection of Bloor Street and Yonge Street in downtown Toronto, Ontario, Canada. The project was initially launched by developer Bazis International Inc. in 2007, before being cancelled and re-developed by Great Gulf. As of 2018, it is the tenth-tallest residential building outside of Asia and the 40th tallest residential building in the world.
Snowhill is a mixed-use development in the Colmore business district, known historically as Snow Hill, in Central Birmingham, England. The area, between Snow Hill Queensway and Birmingham Snow Hill station, is being redeveloped by the Ballymore Group. The £500 million phased scheme has been partly completed on the site of a former surface car park adjacent to the railway station and West Midlands Metro terminus.
Deansgate Square, formerly known as Owen Street, is a residential skyscraper cluster on the southern edge of Manchester City Centre, England, consisting of four towers, the tallest of which is 201 metres (659 ft). The site is just south of Deansgate railway station and north of the Mancunian Way, bounded by Deansgate, Owen Street and the River Medlock. The towers sit at different angles to each other, with a slight bevel, or 'cut back', on each side of each building which ensures the towers catch the light at different times of day.
The Metrobank Center is a 318 m (1,043 ft) mixed-use supertall skyscraper, located in Bonifacio Global City, Taguig, Metro Manila. It is currently the tallest building in Metro Manila and in the Philippines.
The Flame Towers are a group of three skyscrapers in Baku, Azerbaijan. The main contractor, Dia Holdings, is owned by actors that are linked to Azerbaijan's ruling Aliyev family's network of offshore companies.
Brisbane Skytower is a 269.6-metre (885 ft) skyscraper at 222 Margaret Street in Brisbane, Queensland, Australia. The 90-storey residential tower is Brisbane's tallest building, and the sixth tallest building in Australia. It is also the largest residential building in the southern hemisphere.
Australia 108 is a residential supertall skyscraper in the Southbank precinct of Melbourne, Victoria, Australia. Having officially topped out in June 2020, it became the tallest building in Australia by roof height, surpassing the Eureka Tower, and the second-tallest building in Australia by full height, surpassed by Q1 Tower.
6 & 8 Parramatta Square is a skyscraper in Parramatta, New South Wales, Australia, a centrepiece of the Parramatta Square development. The building consists entirely of commercial office space, making up 120,000 square metres (1,300,000 sq ft) of floorspace, at a height of 225.45 metres (739.7 ft), making it the tallest building in Parramatta and outside the Sydney central business district. It was built in the Parramatta Square Development on plot 8 called PSQ8.
One Queensbridge was a proposed mixed–used supertall skyscraper to be located in the Southbank precinct of Melbourne, Australia. The skyscraper would have become the tallest building in Melbourne, surpassing the height of Australia 108, and the tallest building in Australia, eclipsing the height of Q1. In addition to being the tallest, the development would have been one of the biggest single–building projects in Australia, encompassing 300,376 square metres of floor area.
The Legacy Tower is an under-construction supertall skyscraper in Dhaka, Bangladesh. The skyscraper is a part of Bangabandhu tri-tower: alongside 71-floors Liberation Tower and 52-floors Language Tower and the centerpiece of US$12 billion central business district development project in Purbachal. The 111-floors tower will rise 468 m (1,535 ft) tall.
One Bangkok is a US$3.9 billion mixed-use development under construction in Bangkok, Thailand. One Bangkok is being developed by Frasers Property, a subsidiary of TCC Group, one of Thailand's largest conglomerates. It was expected to open in stages between 2023 and 2026 but due to delays has commenced opening in March 2024 starting with the first office building and other elements expected to open during 2024 onwards.