The Achilleas | |
---|---|
Court | House of Lords |
Full case name | Transfield Shipping Inc v Mercator Shipping Inc |
Decided | 9 July 2008 |
Citation(s) | [2008] UKHL 48, [2008] 3 WLR 345, [2008] 4 All ER 159, [2008] 2 All ER (Comm) 753, [2008] 2 Lloyd's Rep 275 |
Transcript(s) | Full House of Lords judgment |
Case history | |
Prior action(s) | [2006] EWHC 3030 (Comm) [2007] EWCA Civ 901 |
Court membership | |
Judge(s) sitting | Lord Hoffmann; Lord Hope of Craighead; Lord Rodger of Earlsferry; Lord Walker of Gestingthorpe; Baroness Hale of Richmond |
The Achilleas or Transfield Shipping Inc v Mercator Shipping Inc [2008] UKHL 48 [1] is an English contract law case, concerning remoteness of damage.
Transfield Shipping was a charterer. It hired use of Mercator's ship, The Achilleas. Transfield was meant to have the ship for five to seven months, and return it no later than midnight on 2 May 2004. Mercator contracted to let the ship to another charterer (Cargill International SA) on 8 May 2004 at $39,500 a day for four to six months. But Transfield did not return the ship until 11 May. With two weeks to go they were appointed to carry coals from Qingdao, China across the Yellow Sea to Tobata and Oita, Japan. [2] Since it was returned late, the new charterer, Cargill, agreed to take the ship, but only at $31,500 a day, since the freight market had fallen sharply.
The question was how much Transfield should pay to Mercator for returning the ship late. Transfield argued they should only pay an amount reflecting the difference between the first contract rate and the market rate for daily hire during the delay, at the market rate prevailing then. This would make $158,301.17. Mercator argued Transfield should pay the amount they had lost on the new chartering contract because of the late return, which adding up the cost over the months would be $1,364,584.37.
The arbitrators of the case, by a majority, decided in favour of Mercator. They held that the loss from getting a lower price on the next chartering contract was within the first rule in Hadley v Baxendale [3] as arising "naturally, i.e. according to the usual course of things, from such breach of contract itself". It fell within that rule because it was damage "of a kind which the [charterer], when he made the contract, ought to have realised was not unlikely to result from a breach of contract [by delay in redelivery]".
The dissenting arbitrator, however, concluded that a reasonable person in Transfield's position would not have understood he was assuming liability for the risk of the type of loss that occurred. The shipping market's general understanding was that liability was restricted to the difference between the market rate and the charter rate for the period of lateness and
"any departure from this rule [is] likely to give rise to a real risk of serious commercial uncertainty which the industry as a whole would regard as undesirable".
The Court of Appeal upheld the arbitrators' ruling. [4] In concluding his opinion, Rix LJ stated that the argument that:
"damages for late redelivery should be limited to the overrun period measure unless the owners can show that, at the time of the contract, they had given their charterers special information of their follow-up fixture, is both undesirable and uncommercial." [4]
According to Rix,
"It is undesirable because it puts owners too much at the mercy of their charterers, who can happily drain the last drop and more of profit at a time of raised market rates, taking the risk of late redelivery, knowing that they will never have to pay their owners more than the current market rate for the overrun period, a rate which will never in truth properly reflect the value to the charterers of being able to fit in another spot voyage at the last moment. It is uncommercial because, if it is demanded that the charterers need to know more than they already do in the ordinary course of events, when they already know that a new fixture, in all probability fixed at or around the time of redelivery, will follow on their own charter, then the demand is for something that cannot be provided. All that an owner will be able to tell his charterer in most cases is that he plans to fix his vessel anew at the time of redelivery. To which the charterer might reply: 'well I know that already! But don’t expect that your telling me that is enough to put me on notice for the purpose of claiming loss of fixture damages, if I deliver the vessel late and you turn out to lose your fixture!' Such an answer, however, reflects the uncommerciality and error of the charterers’ submission." [4]
The House of Lords reversed Court of Appeal's decision, holding unanimously that the loss of profits in the next charter was not within the rule in Hadley v Baxendale . However, their Lordships were divided on the interpretation of the rule.
Lord Hoffmann (with whom Lord Hope gave a concurring judgment) noted that it had always been assumed that damages for late delivery were the difference between market and charter rate. [5] As to the core issue in this case, he said this.
"The case therefore raises a fundamental point of principle in the law of contractual damages: is the rule that a party may recover losses which were foreseeable ("not unlikely") an external rule of law, imposed upon the parties to every contract in default of express provision to the contrary, or is it a prima facie assumption about what the parties may be taken to have intended, no doubt applicable in the great majority of cases but capable of rebuttal in cases in which the context, surrounding circumstances or general understanding in the relevant market shows that a party would not reasonably have been regarded as assuming responsibility for such losses?"
He stated that the majority of arbitrators had applied too crude a test of what the type of foreseeable loss was. The industry's common understanding was crucial to Hadley v Baxendale. The question was not simply, what was a probable loss, but what the parties had in mind, or what was in their contemplation, regarding the nature of the business transaction. He noted Goff J's statement in Satef-Huttenes Albertus SpA v Paloma Tercera Shipping Co SA (The Pegase) [1981] Lloyd’s Rep 175, 183, asking what a reasonable person would have thought his responsibility was.
“The test appears to be: have the facts in question come to the defendant’s knowledge in such circumstances that a reasonable person in the shoes of the defendant would, if he had considered the matter at the time of making the contract, have contemplated that, in the event of a breach by him, such facts were to be taken into account when considering his responsibility for loss suffered by the plaintiff as a result of such breach.”
Lord Hoffmann said one should look at "the background of market expectations". [6] Liability for the next contract would be "completely unquantifiable". And according to Lord Reid in C Czarnikow Ltd v Koufos , [7] the question was if short delay, resulting in extraordinary loss was
"sufficiently likely to result from the breach of contract to make it proper to hold that the loss flowed naturally from the breach or that loss of that kind should have been within [Transfield's] contemplation".
In this case it was not. It was contrary to the principle in Victoria Laundry (Windsor) v Newman Industries [8] to think that Transfield was going to be liable for any loss, however enormous, when it had no knowledge or control over what contract Mercator might be making next. To work out what is "in the parties' contemplation" and what is not, Lord Hoffmann said,
"the only rational basis for the distinction is that it reflects what would have been reasonable and have been regarded by the contracting party as significant for the purposes of the risk he was undertaking."
On the nature of the "contemplation" rule, Lord Hoffmann said the following,
"I agree that cases of departure from the ordinary foreseeability rule based on individual circumstances will be unusual, but limitations on the extent of liability in particular types of contract arising out of general expectations in certain markets, such as banking and shipping, are likely to be more common. There is, I think, an analogy with the distinction which Lord Cross of Chelsea drew in Liverpool City Council v Irwin [1977] AC 239, 257-258 between terms implied into all contracts of a certain type and the implication of a term into a particular contract... It seems to me logical to found liability for damages upon the intention of the parties (objectively ascertained) because all contractual liability is voluntarily undertaken. It must be in principle wrong to hold someone liable for risks for which the people entering into such a contract in their particular market, would not reasonably be considered to have undertaken."
Lord Hope agreed. He noted Blackburn J said in Cory v Thames Ironworks Co [9] saying if the damage were exceptional and unnatural it would be harsh to make a party liable for it, because had he known he would have pushed for more time in the first place.
Lord Rodger and Lady Hale on the other hand, decided the case on the more narrow ground, that the rule in Hadley was simply a question of what is foreseeable or ‘likely’. Lord Rodger said at [53],
"it is important not to lose sight of the basic point that, in the absence of special knowledge, a party entering into a contract can only be supposed to contemplate the losses which are likely to result from the breach in question - in other words, those losses which will generally happen in the ordinary course of things if the breach occurs. Those are the losses for which the party in breach is held responsible - the stated rationale being that, other losses not having been in contemplation, the parties had no opportunity to provide for them."
The Commercial Court in 2010, in the case of Sylvia Shipping Co Ltd v Progress Bulk Carriers Ltd., reviewed the Transfield decision, because Transfield's conclusion - that a defaulting party would not be liable for reasonably foreseeable costs if the parties did not intend the party in breach to have assumed liability for those costs when the contract was formed - had led to some confusion. Hamblen J commented that there were two distinct approaches in use: an "orthodox" approach which followed the principles laid down in Hadley v Baxendale, and a "broader" approach which "added another layer onto the traditional rules on remoteness". The court in Sylvia Shipping came to the conclusion that the orthodox or traditional approach to remoteness, following Hadley, would apply in most cases, but in exceptional situations the "broader" approach based on whether there was also "an assumption of responsibility" should also be applied. [10]
At common law, damages are a remedy in the form of a monetary award to be paid to a claimant as compensation for loss or injury. To warrant the award, the claimant must show that a breach of duty has caused foreseeable loss. To be recognised at law, the loss must involve damage to property, or mental or physical injury; pure economic loss is rarely recognised for the award of damages.
Negligence is a failure to exercise appropriate and/or ethical ruled care expected to be exercised amongst specified circumstances. The area of tort law known as negligence involves harm caused by failing to act as a form of carelessness possibly with extenuating circumstances. The core concept of negligence is that people should exercise reasonable care in their actions, by taking account of the potential harm that they might foreseeably cause to other people or property.
Hadley & Anor v Baxendale& Ors [1854] EWHC J70 is a leading English contract law case. It sets the leading rule to determine consequential damages from a breach of contract: a breaching party is liable for all losses that the contracting parties should have foreseen. However, if the other party has special knowledge that the party-in-breach does not, the breaching party is only liable for the losses that he could have foreseen on the information available to them.
In common law jurisdictions, a misrepresentation is a false or misleading statement of fact made during negotiations by one party to another, the statement then inducing that other party to enter into a contract. The misled party may normally rescind the contract, and sometimes may be awarded damages as well.
Fundamental breach of contract, is a controversial concept within the common law of contract. The doctrine was, in particular, nurtured by Lord Denning, Master of the Rolls from 1962 to 1982, but it did not find favour with the House of Lords.
Consequential damages, otherwise known as special damages, are damages that can be proven to have occurred because of the failure of one party to meet a contractual obligation, a breach of contract. From a legal standpoint, an enforceable contract is present when it is: expressed by a valid offer and acceptance, has adequate consideration, mutual assent, capacity, and legality. Consequential damages go beyond the contract itself and into the actions that arise from the failure to fulfill. The type of claim giving rise to the damages, such as whether it is a breach of contract action or tort claim, can affect the rules or calculations associated with a given type of damages. For example, consequential damages are a potential type of expectation damages that arise in contract law.
Causation is the "causal relationship between the defendant's conduct and end result". In other words, causation provides a means of connecting conduct with a resulting effect, typically an injury. In criminal law, it is defined as the actus reus from which the specific injury or other effect arose and is combined with mens rea to comprise the elements of guilt. Causation only applies where a result has been achieved and therefore is immaterial with regard to inchoate offenses.
Causation in English law concerns the legal tests of remoteness, causation and foreseeability in the tort of negligence. It is also relevant for English criminal law and English contract law.
In English law, remoteness between a cause of action and the loss or damage sustained as a result is addressed through a set of rules in both tort and contract, which limit the amount of compensatory damages available for a wrong.
Expectation damages are damages recoverable from a breach of contract by the non-breaching party. An award of expectation damages protects the injured party's interest in realising the value of the expectancy that was created by the promise of the other party. Thus, the impact of the breach on the promisee is to be effectively "undone" with the award of expectation damages.
Overseas Tankship (UK) Ltd v Morts Dock and Engineering Co Ltd, commonly known as Wagon Mound , is a landmark tort law case, which imposed a remoteness rule for causation in negligence. The Privy Council held that a party can be held liable only for loss that was reasonably foreseeable. Contributory negligence on the part of the dock owners was also relevant in the decision, and was essential to the outcome, although not central to this case's legal significance.
English contract law is the body of law that regulates legally binding agreements in England and Wales. With its roots in the lex mercatoria and the activism of the judiciary during the industrial revolution, it shares a heritage with countries across the Commonwealth, from membership in the European Union, continuing membership in Unidroit, and to a lesser extent the United States. Any agreement that is enforceable in court is a contract. A contract is a voluntary obligation, contrasting to the duty to not violate others rights in tort or unjust enrichment. English law places a high value on ensuring people have truly consented to the deals that bind them in court, so long as they comply with statutory and human rights.
Royscot Trust Ltd v Rogerson[1991] EWCA Civ 12 is an English contract law case on misrepresentation. It examines the Misrepresentation Act 1967 and addresses the extent of damages available under s 2(1) for negligent misrepresentation.
South Australia Asset Management Corporation v York Montague Ltd and Banque Bruxelles Lambert SA v Eagle Star Insurance Co Ltd [1996] UKHL 10 is a joined English contract law case on causation and remoteness of damage. It arose out of the property crash in the early 1990s, whereby banks were suing valuers for overpricing houses in order to recover the lost market value. Owners themselves often had little or no money, since they had fallen victim to negative equity, so mortgage lenders would pursue a valuer instead to recover some losses. The legal principle arising from the case is often referred to as the "SAAMCO principle".
Golden Strait Corporation v Nippon Yusen Kubishika Kaisha[2007] UKHL 12, also known as The Golden Victory, is an English contract law case, concerning the measure of damages for breach of contract.
Jackson v Royal Bank of Scotland [2005] UKHL 3 is an English contract law case, which concerns remoteness of damage.
Parsons (Livestock) Ltd v Uttley Ingham & Co Ltd [1978] QB 791 is an English contract law case, concerning remoteness of damage. In it, the majority held that losses for breach of contract are recoverable if the type or kind of loss is a likely result of the breach of contract. Lord Denning MR, dissenting on the reasoning, held that a distinction should be drawn between losses for physical damage and economic losses.
C Czarnikow Ltd v Koufos or The Heron II [1969] 1 AC 350 is an English contract law case, concerning remoteness of damage. The House of Lords held that the "remoteness" test, as a limit to liability, is, in contract, more restrictive than it is in tort.
In English law, implied terms are default rules for contracts on points where the terms which contracting parties expressly choose are silent, or mandatory rules which operate to override terms that the parties may have themselves chosen. The purpose of implied terms is often to supplement a contractual agreement in the interest of making the deal effective for the purpose of business, to achieve fairness between the parties or to relieve hardship.
AIB Group (UK) plc v Mark Redler & Co Solicitors [2014] UKSC 58 is an English trust law case, concerning the applicable principles of causation for a breach of trust. It held that a "but for" test of causation applies for equitable compensation.