Vianden Pumped Storage Plant

Last updated
Vianden Pumped Storage Plant
SEO main cavern Stolzembourg.jpg
The plant's main pump-generator cavern
Official namePSW Vianden (Pumpspeicherkraftwerk Vianden)
CountryLuxembourg
Location Vianden
Coordinates 49°57′08″N6°10′38″E / 49.95222°N 6.17722°E / 49.95222; 6.17722
StatusOperational
Construction began1959
Opening date1962-64/1976
Owner(s) Société électrique de l'Our (SEO)/RWE
Operator(s)SEO
Upper reservoir
CreatesVianden Upper I & II
Total capacity10,800,000 m3 (8,800 acre⋅ft)
Lower reservoir
CreatesVianden Lower
Total capacity7,230,000 m3 (5,860 acre⋅ft)
Power Station
Hydraulic head 291 m (955 ft) (max)
Pump-generators9 x 100 MW (130,000 hp), 1 x 196 MW (263,000 hp) Francis pump-turbine
Pumps9 x 70 MW (94,000 hp), 1 x 220 MW (300,000 hp)
Installed capacity 220 MW (300,000 hp)
Annual generation 1,650 GWh (5,900 TJ) [1]

The Vianden Pumped Storage Plant is located just north of Vianden in Diekirch District, Luxembourg. The power plant uses the pumped-storage hydroelectric method to generate electricity and serves as a peaking power plant. Its lower reservoir is located on the Our River, bordering Germany, and the upper is elevated above on the nearby Saint Nicholas Mountain. Construction on the plant began in 1959 and the first pump-generators were commissioned in 1962. A tenth pump-generator was installed in 1976 bringing the plant's installed generating capacity to 1,096 megawatts (1,470,000 hp). The plant generates an average of 1,650 gigawatt-hours (5,900 TJ) annually but of course consumes even more. Generally the efficiency of this energy storage method is around 70–80%. The plant is owned by Société électrique de l'Our and RWE. Construction on an eleventh pump-generator began in 2010 and it is expected to be commissioned in 2013, which will bring the plant's installed capacity to 1,296 megawatts (1,738,000 hp).

Contents

Background

Planning for the project began in 1925 [2] but the idea failed due to a lack of funding and political pressure. On 10 July 1958, a treaty was signed between Luxembourg and the German state of Rhineland-Palatinate, which also shares the Our River, allowing construction. [3] Construction began in August 1959. The first four pump-generators were commissioned in the winter of 1962/63 and five through nine in 1964. The official inauguration of the plant was held on 17 April 1964. Construction on a tenth pump-generator began in 1970 and was operational in late 1976. [3] It required the expansion of the upper reservoir, known as Upper Reservoir II. [2]

Second expansion

Planning for a 200 megawatts (270,000 hp) eleventh unit began in 2006 and the designs were completed in 2009 by Lahmeyer International. [1] [4] Construction on the unit began in January 2010. To accommodate the new unit, the capacities of both the upper and lower reservoirs are being increased by 500,000 m3 (410 acre⋅ft). To accomplish this, the upper reservoir wall will be raised 100 centimetres (39 in) and the lower Vianden Dam raised 50 centimetres (20 in). Additionally, a new cavern and set of tunnels just east of the main power cavern will be constructed to house the turbine-generator and penstock. Excavation of these tunnels and caverns was completed on 31 May 2011. On 15 June 2010, Upper Reservoir I was drained to install a new intake structure, which was completed in November 2010. Construction on the new suction/discharge pipe began on 16 May 2011. A cofferdam was constructed around the site in the lower reservoir. The entire expansion is expected to be complete in late 2013. [5] [6]

Design and operation

Upper Reservoir I Niklosbierg basengen panorama.jpg
Upper Reservoir I

The power plant consists of two reservoirs (upper and lower), two power stations and appurtenant structures such as tunnels, intakes and transformers. The upper reservoir for the plant is separated into two sections, I & II. It is formed by a continuous dam and both sections are divided by a dam with floodgates. The total storage capacity of the upper reservoir (both I & II) is 7,230,000 cubic metres (5,860 acre⋅ft). [7] The active (or usable) capacity of the upper reservoir is 6,840,000 cubic metres (5,550 acre⋅ft). Upper Reservoir I itself has as active capacity of 3,010,000 cubic metres (2,440 acre⋅ft) and Upper Reservoir II: 3,830,000 cubic metres (3,110 acre⋅ft). To supply water to the generators and to serve as a discharge for the pumps, both Upper Reservoirs I & II have combined intakes/outlets. Upper Reservoir I primarily supplies the main powerhouse (900 megawatts (1,200,000 hp)) with water and Upper Reservoir II supplies a secondary powerhouse (196 megawatts (263,000 hp)) with water although both reservoirs are at the same altitude and can balance one another. [7]

The lower reservoir dam, Vianden Dam Barrage Veianen vun enne gesinn.jpg
The lower reservoir dam, Vianden Dam

Water from Upper Reservoir I is sent to the main power house, which contains nine Francis pump-turbine-generators, via a system of tunnels and penstocks. When generating power, each generator has an installed capacity of 100 megawatts (130,000 hp) and when pumping the capacity is 70 megawatts (94,000 hp). Each of the nine pump-generators can discharge 39.5 cubic metres per second (1,390 cu ft/s) of water when generating electricity and can pump 21 cubic metres per second (740 cu ft/s) back to the upper reservoir when in pumping mode. Upper Reservoir II's intake/outlet sends water down to the secondary powerhouse which contains one Francis turbine-pump-generator. When generating electricity, the pump-generator has an installed capacity of 196 MW and when pumping the capacity is 220 megawatts (300,000 hp). This pump-generator can discharge 77 cubic metres per second (2,700 cu ft/s) of water and can pump 74 cubic metres per second (2,600 cu ft/s). After electricity is generated, both power stations discharge water into the lower reservoir which is created on the Our River by the 30 metres (98 ft) tall and 130 metres (430 ft) long gravity dam, Vianden Dam. The lower reservoir has a gross storage capacity of 10,080,000 cubic metres (8,170 acre⋅ft) of which 6,840,000 cubic metres (5,550 acre⋅ft) of water is active (or usable for pumping to the upper reservoir). The lower reservoir is at an elevation of 227.5 metres (746 ft) while the upper reservoir is situated at 510.4 metres (1,675 ft). The difference in elevation between the reservoirs affords a maximum hydraulic head of 291.3 metres (956 ft) and minimum of 266.5 metres (874 ft). [7] [8]

Water is pumped from the lower reservoir to the upper during periods of low demand, usually during the night for a period of eight hours. When energy demand is high, water from the upper reservoir is used to generate power and meet peak energy demand. The process repeats daily or as needed. During pumping and generating about 5,500,000 m3 (4,459 acre⋅ft) is oscillated between both reservoirs. When the 200 MW expansion is completed, the size of both the upper and lower reservoirs will be expanded and the installed generating capacity of the power plant will increase from 1,096 MW to 1,296 MW. [5] [7]

See also

Related Research Articles

<span class="mw-page-title-main">Guangdong Pumped Storage Power Station</span> Dam in Conghua District, Guangdong

The Guangdong Pumped Storage Power Station or Guangzhou Pumped Storage Power Station is a pumped-storage hydroelectric power station near Guangzhou, Guangdong Province, China. Power is generated by utilizing eight turbines, each with a 300 megawatts (400,000 hp) capacity, totalling the installed capacity to 2,400 megawatts (3,200,000 hp). The generated power is sold to CLP customers in Hong Kong. The power station was constructed in two stages, the first four turbines were completed in 1994 and the second four in 2000.

<span class="mw-page-title-main">Tamahara Dam</span> Dam in Numata

Tanbara Dam is a rock-fill embankment dam impounding the headwaters of the Hotchi River, a Tone River tributary in Gunma Prefecture of Japan. It is located 14 kilometres (8.7 mi) north of Numata. It creates the upper reservoir for the 1,200 megawatts (1,600,000 hp) Tamahara Pumped Storage Power Station (玉原発電所). Construction began in 1973 and the dam was complete in 1981 while the power station was commissioned in 1986. It is 116 metres (381 ft) tall and withholds a reservoir with a storage capacity of 14,800,000 m3 (11,999 acre⋅ft). Of that capacity, 13,000,000 cubic metres (11,000 acre⋅ft) is active for power generation. The lower reservoir for the pumped-storage power station is created by the Fujiwara Dam, located 4 km (2 mi) to the northwest on another Tone River tributary. Power is generated during periods of high energy demand and pumping occurs during times when energy demand is low such as at night. The power station contains four 300 megawatts (400,000 hp) reversible Francis turbine pump-generators which serve to both pump water and generate electricity. The upper Tamahara Reservoir is at an elevation of 1,177 metres (3,862 ft) and the lower Fujiwara Reservoir is at 651 metres (2,136 ft) which affords the power station an effective hydraulic head of 518 metres (1,699 ft). When pumping, the pump-generators can move up to 210 cubic metres per second (7,400 cu ft/s) of water and when generating, they discharge up to 276 cubic metres per second (9,700 cu ft/s).

<span class="mw-page-title-main">Siah Bishe Pumped Storage Power Plant</span> Dam in Chalus

The Siah Bisheh Pumped Storage Power Plant, also spelled Siyāhbisheh and Siah Bishe, is located in the Alborz Mountain range near the village of Siah Bisheh and 48 km (30 mi) south of Chalus in Mazandaran Province, Iran. The power plant uses the pumped-storage hydroelectric method to generate electricity during periods of high energy demand, making it a peaking power plant, intended to fulfill peak electricity demand in Tehran 60 km (37 mi) to the south. When complete it will have an installed generating capacity of 1,040 megawatts (1,390,000 hp) and a pumping capacity of 940 megawatts (1,260,000 hp). Planning for the project began in the 1970s and construction began in 1985. It was delayed from 1992 until 2001 and the first generator went online in May 2013. The remaining generators were commissioned by 1 September 2015. The power plant is the first pumped-storage type in Iran and will also use the country's first concrete-face rock-fill dam – two of them.

<span class="mw-page-title-main">Kannagawa Hydropower Plant</span> Dam in Nagano Prefecture and Gunma Prefecture

The Kannagawa Hydropower Plant (神流川発電所) is an under construction pumped-storage hydroelectric power plant near Minamiaiki in Nagano Prefecture and Ueno in Gunma Prefecture, Japan. The power plant utilizes the Minamiaiki River along with an upper and lower reservoir created by two dams, the upper Minamiaiki Dam and the lower Ueno Dam. The power station in between the two dams will contain six 470 megawatts (630,000 hp) pump-generators for a total installed capacity of 2,820 megawatts (3,780,000 hp). Unit 1 commenced commercial operation in 2005 and Unit 2 in 2012. When completed, the plant will have the second-largest pumped-storage power capacity in the world.

The Serra da Mesa Dam, once known as Sao Felix, is an embankment dam on the Tocantins River near Minaçu in Goiás, Brazil. The dam serves an associated hydroelectric power plant with a 1,275 megawatts (1,710,000 hp) installed capacity. The dam creates the largest reservoir by volume in Brazil.

<span class="mw-page-title-main">Tianhuangping Pumped Storage Power Station</span> Dam in Anji County of Zhejiang Province, China

The Tianhuangping Pumped Storage Power Station is a pumped-storage power station in Tianhuangping, Anji County of Huzhou, Zhejiang Province, China. The power station has an installed capacity of 1,836 megawatts (2,462,000 hp) utilizing 6 reversible Francis turbines. Construction began in 1993 and the power station was completed in 2004.

The Baishan Dam is an arch-gravity dam on the Second Songhua River near the town of Baishanzhen, Huadian, Jilin Province, China. The purpose of the dam is hydroelectric power generation and flood control. The dam supplies water to five turbine-generators in two different powerhouses for an installed capacity of 1,500 megawatts (2,000,000 hp) while it can also control a design 19,100 cubic metres per second (670,000 cu ft/s) flood. Additionally, it has a 300 megawatts (400,000 hp) pumped-storage hydroelectric generation capacity. It is named after Baekdu Mountain, near the city of Baishan.

<span class="mw-page-title-main">Srinagarind Dam</span> Dam in Si Sawat, Kanchanaburi

The Srinagarind Dam is an embankment dam on the Khwae Yai River in Si Sawat District of Kanchanaburi Province, Thailand. The purposes of the dam are river regulation and hydroelectric power generation. The dam's power station has a 720 megawatts (970,000 hp) capacity of which 360 megawatts (480,000 hp) is pumped storage. The dam was named after Princess Srinagarindra.

<span class="mw-page-title-main">Shin-Takasegawa Pumped Storage Station</span> Dam in Ōmachi, Nagano Prefecture

The Shin-Takasegawa Pumped Storage Station (新高瀬川発電所) uses the Takase River to operate a pumped storage hydroelectric scheme about 12 kilometres (7.5 mi) west of Ōmachi in Nagano Prefecture, Japan. Part of the system is within Chūbu-Sangaku National Park.

<span class="mw-page-title-main">Kazunogawa Pumped Storage Power Station</span> Dam in Kōshū

The Kazunogawa Pumped Storage Power Station is a pumped-storage hydroelectric power station near Kōshū in Yamanashi Prefecture, Japan. The station is designed to have an installed capacity of 1,600 megawatts (2,100,000 hp) and three of the four 400 megawatts (540,000 hp) generators are currently operational, for a total operational capacity of 1200 MW. Construction on the power station began in 1993 and the first generator was commissioned on 3 December 1999. The second was commissioned on 8 June 2000. The third one became operational on 9 June 2014, six year early due to post-power demand from the Great East Japan earthquake. The fourth and final generator is slated to be commissioned by 2024. It is owned by TEPCO and was constructed at a cost of US$2.2 billion.

The Bailianhe Pumped Storage Power Station is a pumped-storage hydroelectric power station located 58 kilometres (36 mi) east of Huanggang in Hubei Province, China. It was constructed between 2004 and 2010 and has a 1,200 megawatts (1,600,000 hp) installed capacity. The power station operates by shifting water between an upper and lower reservoir to generate electricity. For this project, only the upper reservoir had to be created as an existing reservoir, the Bailianhe Reservoir, was used as the lower. During periods of low energy demand, such as at night, water is pumped from Bailianhe Reservoir up to the upper reservoir. When energy demand is high, the water is released back down to the lower reservoir but the pump turbines that pumped the water up now reverse mode and serve as generators to produce electricity. The process is repeated as necessary and the plant serves as a peaking power plant.

The Baoquan Pumped Storage Power Station is a pumped-storage hydroelectric power station located 34 kilometres (21 mi) northeast of Jiaozuo in Henan Province, China. It was constructed between June 2004 and December 2011 and has a 1,200 megawatts (1,600,000 hp) installed capacity. The power station operates by shifting water between an upper and lower reservoir to generate electricity.

<span class="mw-page-title-main">Entracque Power Plant</span> Dam in Entracque

The Entracque Power Plant, also known as The Upper Gesso Plant, is a pumped-storage hydroelectric power station located in Valle Gesso just south of Entracque, Italy. The power station contains pump-generators for two co-located but hydraulically separated power schemes; the Chiotas-Piastra Plant and Rovina-Piastra Plant. Both plants use separate upper reservoirs but use Lago della Piastra as their common lower reservoir. To produce power, water is released from the upper reservoirs to the power station located at the lower reservoir. The pump-generators re-fill the reservoirs and the process repeats as needed. The Chiotas' upper reservoir, Lago del Chiotas, is located much higher in the valley and larger than Rovina's Lago della Rovina which affords it the ability to produce more electricity. The installed capacity of Chiotas is 1,184 megawatts (1,588,000 hp) with a hydraulic head of 1,048 m (3,438 ft) while Rovina has an installed capacity of 133.67 megawatts (179,250 hp) and a head of 598 metres (1,962 ft). Construction on the plant began in 1962 and operations started in 1982. It is owned and operated by Enel.

The Heimifeng Pumped Storage Power Station is located at the hills of Heimifeng, Qiaoyi town, Wangcheng district, 25 kilometres (16 mi) north of Changsha in Hunan province, China. It was constructed between 2005 and 2009 with the generators being commissioned in 2009 and 2010. The station generates power by transferring water between an upper and lower reservoir. When energy demand is high, water from the upper reservoir is released and used to generate electricity before being discharged into the lower reservoir. During times of low demand, water from the lower reservoir is then pumped back up to replenish upper reservoir. This process allows the station to meet peak energy demand and it can go from standstill to operational in three minutes.

The Hohhot Pumped Storage Power Station, also known by Huhehaote, is located 20 kilometres (12 mi) north of Hohhot in Inner Mongolia, China. It uses the pumped-storage hydroelectric method to generate electricity. The plant has an installed capacity of 1,224 megawatts (1,641,000 hp). Construction began in 2005 and the first generator was commissioned on 20 November 2014. The second generator was commissioned on 26 December 2014 and the final two were commissioned in June 2015.

<span class="mw-page-title-main">Matanoagawa Dam</span> Dam in Kōfu

The Matanogawa Dam (俣野川ダム) is a concrete gravity dam on a tributary of the Hino River located 2.3 km (1 mi) south of Kōfu in Tottori Prefecture, Japan. Construction on the dam began in 1978 and it was complete in 1984. The primary purpose of the dam is hydroelectric generation and it creates the lower reservoir for the Matanogawa Pumped Storage Power Station (俣野川発電所). It is 69.3 metres (227 ft) tall and creates a reservoir with a 7,940,000-cubic-metre (6,440 acre⋅ft) storage capacity. The power station is located on the southern bank of the reservoir and contains four 300 megawatts (400,000 hp) Francis pump-turbine-generators. The upper reservoir for the pumped-storage scheme is created by the Doyo Dam located 6 kilometres (3.7 mi) to the southeast in Okayama Prefecture. To generate power, water from the Doyo Dam is sent to the power station, used to generate electricity and then discharged into the Matanogawa Reservoir. This occurs when energy demand is high and when it is low, water is pumped back up to the Doyo Dam as stored energy. The same pump-generators that pump the water to Doyo reverse and generate electricity when it is sent back down. The first generator was operational in 1992 and the last in 1996.

<span class="mw-page-title-main">Okuyoshino Pumped Storage Power Station</span> Dam in Totsukawa

The Okuyoshino Pumped Storage Power Station (奥吉野発電所) is located 15 kilometres (9.3 mi) north of Totsukawa in Nara Prefecture, Japan. Using the pumped-storage hydroelectric method, the power plant has an installed capacity of 1,206 megawatts (1,617,000 hp). To accomplish power generation, the power station shifts water between two reservoirs, the lower Asahi Reservoir and the upper Seto Reservoir. Construction on both the Asahi and Seto Dams began in 1971 and was complete in 1978. The power station was commissioned in 1980. Due to heavy sediment and turbidity in the Seto Reservoir, caused by logging and landslides upstream, a sediment bypass tunnel was constructed between 1992 and 1998.

The Presenzano Hydroelectric Plant, officially known as the Domenico Cimarosa Hydroelectric Plant, is located along the Volturno River in Presenzano, Province of Caserta, Italy. Using the pumped-storage hydroelectric method, it has an installed capacity of 1,000 megawatts (1,300,000 hp). Construction began in 1979, it was finished in 1990 and the generators commissioned in 1991. In 2004, the plant was renamed after Domenico Cimarosa. Power is generated by releasing water from the upper Cesima reservoir down to the power plant which contains four reversible 250 MW Francis pump-turbine-generators. After power production, the water is sent to the lower reservoir. During periods of low energy demand, the same pump-generators pump water from the lower reservoir back to the upper where it becomes stored energy. Power generation occurs when energy demand is high. The upper reservoir, formed by an embankment dam, is located at an elevation of 643 metres (2,110 ft) in the municipality of Sesto Campano in the Province of Isernia. Both the upper and lower reservoirs have an active storage capacity of 6,000,000 cubic metres (4,900 acre⋅ft). The difference in elevation between both the upper and lower affords a hydraulic head of 495 metres (1,624 ft).

<span class="mw-page-title-main">Roncovalgrande Hydroelectric Plant</span> Dam in Maccagno

The Roncovalgrande Hydroelectric Plant, also known as the Delio Hydroelectric Plant, is located 3 kilometres (1.9 mi) north of Maccagno in the Province of Varese, Lombardy, Italy. Using the pumped-storage hydroelectric method, the power plant has an installed capacity of 1,016 megawatts (1,362,000 hp). The power plant was complete in 1971 and the last generator operational in 1973. During construction, the upper reservoir, Lago Delio, was expanded in capacity with two gravity dams; a northern and southern, 28.5 metres (94 ft) and 36 metres (118 ft) in height, respectively. The lower reservoir, Lago Maggiore, already existed. The power plant itself is located underground in between Delio and Maggiore. To produce electricity, water is released from the upper reservoir to the power plant via two 1,100 metres (3,600 ft) long penstocks. At the power plant, eight four-stage Pelton turbine-generators generate electricity. Power generation occurs during periods of high energy demand and when energy demand is low, pumping usually occurs. The pumps are on the same shaft as the Pelton turbines and send water from the lower to the upper reservoir to serve as stored energy. Later on, this water will be sent back down to the power station and the process will repeat. The difference in elevation between the upper and lower reservoirs affords a hydraulic head of 736.25 m (2,416 ft) and Lago Delio has a usable storage capacity of 10,000,000 cubic metres (8,100 acre⋅ft).

<span class="mw-page-title-main">Esch-sur-Sûre Dam</span> Dam in Esch-sur-Sûre, Wiltz

The Esch-sur-Sûre Dam is an arch dam on the River Sauer just upstream of Esch-sur-Sûre in the Wiltz canton of Luxembourg. The primary purpose of the dam and its reservoir, Upper Sûre Lake, is to provide municipal water supply and hydroelectric power generation. The dam is operated jointly by the Administration of Roads and Bridges and the Syndicate des Eaux du Barrage d'Esch-sur-Sûre (SEBES) while the power station is operated by Société Electrique de l'Our (SEO).

References

  1. 1 2 "Vianden Pumped Storage Plant - Unit 11". Lahmeyer International. Archived from the original on 14 June 2012. Retrieved 14 February 2012.
  2. 1 2 "Pumped-Storage Plants in Europe - other countries". IndustCards. Retrieved 14 February 2012.
  3. 1 2 "Vianden PSW - History" (in German). Société électrique de l'Our. Retrieved 14 February 2012.
  4. "Pumped Storage Plant Vianden". Lahmeyer International. Archived from the original on 14 June 2012. Retrieved 14 February 2012.
  5. 1 2 "Vianden Pumped Storage Plant Unit 11". Active Communications International. 28 February 2011. Archived from the original on 6 February 2013. Retrieved 14 February 2012.
  6. "Vianden pump storage plant" (in German). Jäger Bau GmbH. Retrieved 14 February 2012.
  7. 1 2 3 4 "Vianden PSW - Technical Data" (in German). Société électrique de l'Our. Retrieved 14 February 2012.
  8. "Visit the Vianden pumped storage power plant" (PDF) (in German). University of Bochum. Archived from the original (PDF) on 4 September 2014. Retrieved 15 February 2012.