Akhori Dam

Last updated
Akhori Dam
Country Pakistan
Location Akhori, Attock district, Punjab
Coordinates 33°42′23″N72°26′34″E / 33.70639°N 72.44278°E / 33.70639; 72.44278
PurposePower, water storage
StatusProposed
Construction cost$1.6 Billion Est.
Operator(s) Wapda
Dam and spillways
Impounds Haro River
Height122 m
Length5.16 km
Reservoir
CreatesAkhori reservoir
Total capacity9.4 km3
Power Station
Installed capacity 600 MW
Annual generation 2,155 GWh
Website
AKHORI DAM

The Akhori Dam project is a proposed multipurpose dam in Pakistan, about 60 km west of Islamabad. Developed by Pakistani Water and Power Development Authority (WAPDA) as part of its Water Vision 2025, it has been proposed by the former Pakistan Muslim League (Q)'s Government.

Contents

The dam will be able to store about 8.6 billion cubic metres of water that is split filling the Tarbela reservoir during the monsoon season. [1] It will also host a 600 MW hydropower plant, expected to generate an estimated 2,155 GWh/year. [2]

Controversy

The local people of this area may be opposed to the proposal because they are small land holder agriculturalists, but the government continues to press on. Government officials claim locals though are willing to give up their land for the better of the nation. With the construction of the dam, as many as 49,320 persons would be displaced and the government would have to bear an environmental and resettlement cost of $0.3 billion. More than thirty villages including Daurdad, Akhori, Humak, Boota, Jabbi Shareef, and Bathou would be inundated. [3]

Related Research Articles

<span class="mw-page-title-main">Mangla Dam</span> Multipurpose dam in Azad Kashmir, Pakistan

The Mangla Dam is a multipurpose dam situated on the Jhelum River in the Mirpur District of Azad Kashmir, Pakistan. It is the sixth-largest dam in the world. The village of Mangla, which sits at the mouth of the dam, serves as its namesake. In November 1961, the project's selected contractors were revealed; it was announced that Binnie & Partners, a British engineering firm, was going to serve as the lead designers, engineers, and inspectors for the construction of the dam. The project was undertaken by a consortium known as the Mangla Dam Contractors, which consisted of eight American construction firms sponsored by the Guy F. Atkinson Company based in South San Francisco, California.

Topi is a town in the eastern part of the Swabi District of Khyber Pakhtunkhwa province of Pakistan. The administrative division of Topi unfolds into two Union councils: Topi East and Topi West. Notably, the Tarbela Dam, largest earth-filled dam in the world, is located only 9 kilometres (5.6 mi) east of Topi.

<span class="mw-page-title-main">Tarbela Dam</span> Dam in Khyber Pakhtunkhwa, Pakistan

Tarbela Dam is an earth-filled dam along the Indus River in Pakistan's Khyber Pakhtunkhwa province. It is located mainly in the Haripur District of the province. It is about 20 km (10 mi) from the city of Haripur, 105 km (65 mi) northwest of Islamabad, and 125 km (80 mi) east of Peshawar. It is the largest earth-filled dam in the world. The dam is 143 metres (470 ft) high above the riverbed and its reservoir, Tarbela Lake, has a surface area of approximately 250 square kilometres (97 sq mi).

The Kalabagh Dam is a proposed hydroelectric dam on the Indus River at Kalabagh in the Mianwali District, Punjab, Pakistan, which has been intensely debated along ethnic and regional lines for over 40 years.

<span class="mw-page-title-main">Gomal Zam Dam</span> Dam in Khyber Pakhtunkhwa, Pakistan

Gomal Zam Dam is a multi-purpose gravity dam in South Waziristan Tribal District of Khyber Pakhtunkhwa, Pakistan. The dam impounds the Gomal River, a tributary of the Indus River, at Khjori Kach, where the Gomal River passes through a narrow ravine. The purpose of the dam is irrigation, flood control, and hydroelectric power generation. Construction of the dam began in August 2001 and was completed in April 2011. The powerhouse was completed in March 2013 and electricity production started in August 2013. The dam was officially inaugurated on 12 September 2013 by Minister for Water and Power Khawaja Muhammad Asif, along with US Ambassador Richard G. Olson and Khyber Pakhtunkhwa Governor Shaukatullah Khan.

Diamer-Bhasha Dam is a concreted-filled gravity dam, in the preliminary stages of construction, on the River Indus between Kohistan district in Khyber Pakhtunkhwa and Diamer district in Gilgit Baltistan, Pakistan administered Kashmir. Its foundation stone was laid by the then Prime Minister of Pakistan in 1998. The dam site is situated near a place called "Bhasha", hence the name which is 40 km downstream of Chilas town and 315 km from Tarbela Dam. The eight million acre feet (MAF) reservoir with 272-metre height will be the tallest roller compact concrete (RCC) dam in the world.

<span class="mw-page-title-main">Ghazi-Barotha Hydropower Project</span> Dam in Punjab and Haripur, KP

Ghazi-Barotha Hydropower Project is a 1,450 MW run-of-the-river hydropower, connected to the Indus River. It is located about 10 km (6.2 mi) west of Attock in the Punjab province and east of Haripur in the Khyber Pakhtunkhwa province of Pakistan. Construction of the project began in 1995. It consists of five generators, each possessing a maximum power generation capacity of 290 MW. The inauguration of the plant took place on 19 August 2003, presided over by the then President General Pervez Musharraf. It also saw the commissioning of the first two of the five generators i.e. Unit 1 and Unit 2. The last generator was commissioned on 6 April, 2004, and the project was completed by December the same year. It costed US$2.1 billion with funding from Pakistan's Water and Power Development Authority, the World Bank, Asian Development Bank, Japan Bank for International Cooperation, Kreditanstalt für Wiederaufbau, European Investment Bank and Islamic Development Bank.

<span class="mw-page-title-main">Water & Power Development Authority</span> Government agency of Pakistan

The Pakistan Water & Power Development Authority is a government-owned public utility maintaining power and water in Pakistan, although it does not manage thermal power. WAPDA includes Tarbela and Mangla dams among its resources. Its headquarters are in Lahore.

Mohmand Dam is an under construction multi-purpose concrete-faced rock-filled dam located on the Swat River approximately 37 km north of Peshawar and 5 km upstream of Munda Headworks in Mohmand District, Khyber Pakhtunkhwa, Pakistan.

Hingol Dam is a proposed small, low-head, Central Core Zone, hydroelectric power generation dam of 3.5 megawatt (MW) generation capacity, located in the Lasbela District across the Hingol River in the Balochistan province of Pakistan. It is located at a distance of 260 km (162 mi) northwest of Karachi and about 16 km (10 mi) north of bridge across the Hingol River on the Makran Coastal Highway and about 8 km (5 mi) north of Kund Malir where the river falls into the sea.

Bara Dam is a proposed small, low-head, earth core rockfill, hydroelectric dam with a capacity of 5.8 megawatts, located across Bara River at the confluence of Mastura River in Tirah Valley, Khyber Agency, FATA, Pakistan. It is part of a wider plan that consists in remodeling the Bara River, to promote agriculture.

Bunji Dam is proposed large hydro-power project on Indus River in Bunji, Gilgit Baltistan, Pakistan. If built it would be Pakistan's second largest hydropower project.

Mangi Dam is located near Ziarat in Balochistan, Pakistan. The dam was constructed in 1982 and has a height of 18 m (59 ft) and storage capacity of 130,000 m3 (105 acre⋅ft). It was constructed at a cost of US$36.88 million. It was made to stop the fish from leaving the fishing area. In 2015 it is announced that the dam will also produce electricity and the shortage of load shedding will also reduce.

Water Vision 2025 is a National Water resource and Hydropower Development Program being undertaken by WAPDA to tackle the severe water and energy crisis in Pakistan. Since the construction of Mangla Dam, the country's population has risen to 180 million and is estimated to reach 280 million by 2025, resulting in a severe energy and water crisis.

The Dasu Dam is a large hydroelectric gravity dam currently under construction on the Indus River near Dasu in Kohistan District, Khyber Pakhtunkhwa Province, Pakistan. It is developed by Pakistan Water and Power Development Authority (Wapda), as a key component of the company's Water Vision 2025. The project was started in 2019 but faced a delay due to funds and land acquisition disputes. Work resumed in 2020 after land acquisition and arrangements of funding facility, the World Bank agreed to contributed $700 million of the $4.2 billion as the government of Imran Khan decided to proceed ahead with the construction of the project, as part of his vision of reducing Pakistan's reliance on non-renewable energy.

<span class="mw-page-title-main">Kundal Dam</span> Dam in Swabi, Khyber Pakhtunkhwa

Kundal Dam is located in District Swabi, Khyber Pakhtunkhwa. The kundal dam will supply water for irrigation to fertile the barren land and control the floods as well as to fulfill water scarcity in the area. It will irrigate about 13340 acres of land. The Dam is sponsored by the Ministry of Water and Power and Directorate General Small Dams, Irrigation Department, Government of Khyber Pakhtunkhwa are executing agencies of the kundal project.

Murunj Dam is a proposed dam located in Rajanpur District, Punjab, Pakistan. The Project is proposed to be built across Kaha Nullah at about 116 km West of Rajanpur District. Nearest village is Marri, which is about 15 km from dam site. The commencement date is June 2020 and expected completion date is June 2023. The available water resources are very scarce in Rajanpur and adjoining areas facing acute shortage of fresh water for drinking and agriculture. The annual monsoon rains give rise to flashy hill torrents causing inundation of thousands of acres land in the adjoining foothills and rendering damages to public property and cultivated land each year.

Lieutenant General Muzammil Hussain (Retired) is a former senior officer in the Pakistan Army and former Chairman of the Water and Power Development Authority (WAPDA) in Pakistan.

References

  1. Akhori dam and the Tarbela links
  2. "Akhori Dam Project". www.wapda.gov.pk. Retrieved 2020-04-10.
  3. Ministry recommends $1.6b for Akhroi Dam