Electricity sector in Macau

Last updated
Electricity sector of Macau
Data
Average electricity use (2016)5,255 GWh
Institutions
Responsibility for transmission Companhia de Electricidade de Macau
Responsibility for regulation Companhia de Electricidade de Macau
CEM Office Macau PowerHouse.jpg
CEM Office
Coloane A Power Station, Macau's largest power station Coloane A Power Station.JPG
Coloane A Power Station, Macau's largest power station
System Dispatch Center CEM System Dispatch Center.JPG
System Dispatch Center
Overhead distribution line in Cotai Macau Overhead Line.JPG
Overhead distribution line in Cotai

The electricity sector in Macau ranges from generation, transmission, distribution and sales of electricity in Macau, China.

Contents

Regulator

Electricity sector in Macau is regulated by its electric power utility company Companhia de Electricidade de Macau (CEM), established in 1972 during the Portuguese rule. [1]

Generation

Electricity generation in Macau

CEM's generation facility consists of two power stations, which are located on Coloane Island: Coloane A Power Station (CCA) and Coloane B Power Station (CCB). Together, CEM has a total installed capacity of 407.8 MW.

The predominant types of generation technology deployed are the low speed diesel generator using heavy fuel oil for CCA and the combined cycle gas turbine using natural gas for CCB.

Electricity import from Mainland China

In 2012, CEM produced 376 GWh to supply 8% of Macau's 4,344 GWh gross energy demand, while the remaining 3,968 MW (92%) was imported from Mainland China through Guangdong Power Grid under China Southern Power Grid Company. [2] [3] In 2013, CEM generated 7.2% electricity for Macau, while the electricity import from Mainland China rose to 92.8%. [4]

Transmission and distribution

The Macau electrical transmission network comprises 20 primary substations with a total installed capacity of 1,260 MVA in 220/110 kV, 1,500 MVA in 110/66 kV and 1,752 MVA in 66/11 kV.

As of December 2012, the high voltage transmission network consists of 281 km line made up of 220 kV, 110 kV and 66 kV cables. The 11 kV medium voltage distribution network is composed of 35 switching stations and 1,245 customer substations (11/0.4 kV) connected by cables with a total length of 617 km. The low voltage distribution network is made up of 780 km of cables. Almost all CEM's power network is constituted by underground cables which mainly come from Europe, United States and South Korea.

Electrical grid in Macau has been linked to electrical grid of Guangdong since 1984. [5]

In 2015, CEM announced that over the next three years, CEM will build another five new substations to power up the upcoming Macau Light Rail Transit, hospitals and Ilha Verde. [6]

Interconnection grid with Mainland China

Macau has also interconnection grids with Mainland China in Guangdong with Guangdong Power Grid of the China Southern Power Grid Company.

The first interconnection commissioned in June 2008 are the three 220 kV circuits connected at the 220/110 kV Canal dos Patos substation, with the importation capacity of 1,050 MVA. The second interconnection commissioned in June 2012 are the two 220 kV circuits connected at the 220/110 kV Lotus substation, with the importation capacity of 700 MVA. These five interconnection circuits give a total of 1,750 MVA importation electric capacity for Macau from Guangdong in Mainland China. [7]

Load, demand and customers

As of 2017, Macau has been experiencing an average 2.3% annual growth rate for their electricity demand. [8] [9] Their maximum daily electricity demand is 756.7 MW. As of 2016, total Macau power consumption reached 5,255 GWh. [10] Macau's utility frequency is 50 Hz and at 400 V (three-phase) and 230 V (single-phase).

By the end of 2007, CEM was providing electricity to 211,238 customers, in which 75% of them are in the Macau Peninsula, while the remaining 21.9% are in Taipa and 3.1% in Coloane. Electricity reaches every individual in Macau. [11]

In 2016, there are 71 charging stations for electric vehicles across 18 public car parks in Macau. [12]

Performances

CEM's power supply reliability maintains at world leading performance. The Average System Availability Index (ASAI) reached 99.9998% in 2010. In 2014, the System Average Interruption Duration Index was as low as 1.34 minutes. CEM has five mobile equipment units as contingency measures to deal with electricity blackouts. All of the underground installed cables undergo regular routine inspection and diagnosis every five years. [6]

CEM has established and implemented an Integrated Management System with all three Management System Certifications ISO 9001, ISO 14001 and OHSAS 18001]. CEM was the first public utility company in Macau and the first power company in Hong Kong and Macau to obtain the certification ISO 14064-1 Greenhouse Gases Management System by taking systematic and genuine actions against greenhouse gases emissions.

Environmental protection

In order to cope with the growing concern on environmental issues, CEM has invested more than MOP 450 million to improve CEM environmental performance, including investment in Selective Catalytic Reduction Systems, Natural Gas Conversion, Air Quality Monitoring Systems, Scrap Yard, Noise Control Facilities etc. [11]

Power sector safety

Every year, CEM holds fire alarm and evacuation drills at different locations of its premises to test and evaluate the effectiveness of their contingency plans, further enhance the emergency response abilities of all the participating staffs and ensure the safety of the employees and facilities. [13]

See also

Related Research Articles

Directlink (Terranora)Interconnector is a buried 59 kilometre High Voltage Direct Current (HVDC) electricity transmission cable route from near Lavertys Gap, 5 kilometres (3.1 mi) Southwest of Mullumbimby, New South Wales and Bungalora & connected via a 3.5km (2.2mi) AC Overhead Transmission Line to the NorthEast to the Terranora Electrical Substation @ Terranora, New South Wales New South Wales in Eastern Australia.

The East–West Interconnector is a 500 MW high-voltage direct current submarine and subsoil power cable which connects the Irish and British electricity markets. The project was developed by the Irish national grid operator EirGrid.

The electricity sector in New Zealand uses mainly renewable energy; such as hydropower, geothermal power and increasingly wind energy. As of 2019, 82% of electricity is generated from renewable sources, making New Zealand one of the countries with the lowest carbon dioxide emissions from electricity generation. Electricity demand grew by an average of 2.1% per year from 1974 to 2010 but decreased by 1.2% from 2010 to 2013.

Companhia de Transmissão de Energia Elétrica Paulista is one of transmission system operators of electric power grid in Brazil. The company is headquartered in São Paulo.

Electricity sector in China

China's electric power industry is the world's largest electricity producer, passing the United States in 2011 after rapid growth since the early 1990s. In 2019, China produced more electricity than the next three countries—U.S., India, and Russia—combined.

Electrical grid Interconnected network for delivering electricity from suppliers to consumers

An electrical grid is an interconnected network for electricity delivery from producers to consumers. Electrical grids vary in size and can cover whole countries or continents. It consists of:

National Grid (New Zealand)

The National Grid is the nationwide system of electric power transmission in New Zealand. The national electricity transmission grid is owned, operated, and maintained by state-owned enterprise Transpower New Zealand, although some lines are owned by local distribution companies and leased to Transpower. In total, the national grid contains 11,803 kilometres (7,334 mi) of high-voltage lines and 178 substations.

Whakamaru to Brownhill Road transmission line

The Whakamaru to Brownhill Road transmission line is a double-circuit 400 kV-capable transmission line constructed by Transpower to increase the capacity of the National Grid between the southern Waikato and the city of Auckland. The line runs from the Whakamaru sub-station near the Whakamaru Power Station, over a distance of 186 kilometres (116 mi) to the new Brownhill Road substation near Whitford in southeastern Auckland. The line will initially be operated at 220 kV. From Brownhill Road, 220 kV underground cables connect the line to the Pakuranga sub-station in eastern Auckland. The project was the subject of considerable controversy and protest during the planning and approval stages. Construction of the line started in February 2010, and the line was commissioned on 30 October 2012. The transmission line forms the major part of a wider North Island Grid Upgrade project with a forecast cost to completion of $894 million.

Companhia de Electricidade de Macau

Companhia de Electricidade de MacauCEM, S.A. known simply as CEM or Chinese: 澳電 is a private public utility company with a sole concession to transmit, distribute, sell high, medium and low voltage of electricity in Macau. Besides, CEM owns an installed generation capacity of 408 MW.

The North Auckland and Northland (NAaN) grid upgrade project reinforced transmission into the Auckland Region and across the harbour to North Auckland and the Northland Region. It added new 220 kV transmission capacity to the National Grid by providing 37 km of underground cable between the Pakuranga, Penrose, and Albany substations.

EA Networks New Zealand electricity distribution company

Electricity Ashburton Limited, trading as EA Networks is a co-operatively-owned electricity distribution company, based in Ashburton, New Zealand.

Bihar State Power Holding Company Limited Electricity board in Bihar, India

Bihar State Power Holding Company Limited (BSPHCL), formerly Bihar State Electricity Board (BSEB) is a state-owned electricity regulation board operating within the state of Bihar in India. BSEB was established in 1958 as a statutory corporation under the Electricity (Supply) Act, 1948. As of November 2012, BSEB has nearly 1,700 officers and 14,850 employees. The derated capacity comes to just 530 MW. The BSEB was unbundled on 2 August 2011. Power Finance Corporation was the main consultant for BSEB's restructuring.

Electricity sector in Taiwan Overview of the electricity sector in Taiwan

The electricity sector in Taiwan ranges from generation, transmission, distribution and sales of electricity, covering Taiwan island and its offshore islands.

Macau Power Station Former power station in Nossa Senhora de Fátima, Macau, China

The Macau Power Station was a gas and diesel-fired power station in Nossa Senhora de Fátima, Macau, China. Commissioned in 1973 for its first two units, it was the first power station in Macau. It was decommissioned in 2016.

Coloane A Power Station Power plant in Coloane, Macau, China

The Coloane A Power Station is a low-speed diesel-fired power station in Coloane, Macau, China. With an installed capacity of 271.4 MW, it is the largest power station in Macau.

Coloane B Power Station Power station in Coloane, Macau, China

The Coloane B Power Station is a combined cycle gas-fired power station in Coloane, Macau, China. It is the latest power station in Macau.

Electricity sector in Hong Kong Electricity sector in Hong Kong, China

Electricity sector in Hong Kong ranges from generation, transmission, distribution and sales of electricity covering Hong Kong. There are two main providers of electricity in Hong Kong.

Events from the year 2010 in Macau, China.

The high-voltage electricity substations in the United Kingdom are listed in the following tables. The substations provide entry points to, and exit points from, the National Grid (GB) or Northern Ireland Electricity Network. Entry points include power stations, major wind farms and inter-connectors from other countries and regions. Exit points are to lower voltage transmission and distribution substations which are also shown in the tables.

References

  1. "[CEM - Companhia de Electricidade de Macau] Business Overview". cem-macau.com. Retrieved 2014-08-23.
  2. "[CEM - Companhia de Electricidade de Macau] Generation". Cem-macau.com. Retrieved 2014-04-21.
  3. "Electricity company CEM calls for more production rather than sector liberalisation". Macau News. 2008-11-21. Archived from the original on 2013-12-25. Retrieved 2014-04-21.
  4. "Electricity fare could drop by 1 cent: CEM". Macau Business Daily. Archived from the original on 2013-12-25. Retrieved 2014-04-21.
  5. "Macau: Electricity company CEM doubles electricity import capacity from China". Macauhub English. 2008-06-24. Retrieved 2014-04-21.
  6. 1 2 "CEM - Cable maintenance strengthened to avoid blackouts". 9 April 2015.
  7. "[CEM - Companhia de Electricidade de Macau] Transmission and Distribution". cem-macau.com. Retrieved 2014-08-23.
  8. "CEM - Companhia de Electricidade de Macau".
  9. "CEM: Electricity Rates may Decrease". Macau Daily Times. 2 March 2016. Retrieved 14 April 2017.
  10. "Power Consumption Hits Record High". Macau Daily Times. 24 February 2017. Retrieved 14 April 2017.
  11. 1 2 (PDF) https://web.archive.org/web/20131015110537/http://cepsi2012bali.org/backup/asieap/goldbook2009/s4/Macau.pdf. Archived from the original (PDF) on 2013-10-15.{{cite web}}: Missing or empty |title= (help)
  12. "Power consumption hits record high".
  13. Cesar Tordesillas (13 September 2012). "CEM conducts fuel oil leakage drill at Coloane Power Station". Asian Power. Retrieved 2014-04-21.