Laggan Dam is a mass concrete gravity dam located on the River Spean south west of Loch Laggan in the Scottish Highlands. It forms the second reservoir for the Lochaber hydroelectric scheme.

Contents

History

The structure was built as part of the Lochaber hydroelectric scheme by Balfour Beatty for the British Aluminium Company and construction was finished in 1934. The supervising engineers were the firm of C S Meik and William Halcrow, now known as the Halcrow Group. [1]

The dam was designated a Category B listed building in 1985. It was upgraded to Category A listing in 2011, following a review as part of Hydroelectric Power Thematic Survey 2010. [1] [2]

Design

Water flowing over the spillway and the pipes in the centre of the dam Laggan Dam on 5 pipes - geograph.org.uk - 289875.jpg
Water flowing over the spillway and the pipes in the centre of the dam

The dam is about 700 feet (210 metres) long, [3] and 48 m (157 ft) high between the level of the foundations and the crest of the spillway. [4] It is curved upstream like an arch dam with a radius of curvature of 2,000 ft (610 m), but works purely on the principle of a gravity dam. [5]

The dam impounds Laggan Reservoir and Loch Laggan, which are connected via a short section of the River Spean. This was dredged and straightened over a length of approximately 1.3 miles (2 km) to the confluence of the Amhainn Ghuilbinn. [6] The reservoir has a capacity of 40,000,000 cubic metres (1.4 billion cubic feet), [4] between a top water level of 820 feet (250 m) OD and maximum drawdown level of 804 feet (245 m) OD, giving an operational range of 16 feet (4.9 m). [6]

The whole crest of the dam, except for a section in the middle that houses equipment, is a spillway broken into 29 bays by piers that support a roadway across the dam. [4] As well as the spillway, there are six self-priming siphons embedded into the centre of the dam, controlled automatically by system of air valves. [4] The siphons are set to operate in pairs, priming at 820.5, 821.0, and 821.25 feet OD (250.1, 250.2, 250.3 m OD), and discharge through 4′2″ (1.3 m) diameter Glenfield-Kennedy jet disperser pipes. Laggan Dam was the first large siphon spillway used in the UK, . [6]

The foundations are built on granite, and the dam was built in seven sections, with copper strip and hot poured asphalt water stops in the joints. [4]

Water from the dam is conveyed to Loch Treig through three miles (5 kilometres) of tunnel. From there, the waters travel through a further 15 miles (24 kilometres) of tunnel, 15 feet (4.6 metres) in diameter, before descending the hillside to a power house at Fort William through five steel pipes.

The dam can be found next to the A86 road from Fort William, however there is no public access over it. The catchment area of the dam was increased by an aqueduct which diverts flow from the River Mashie into the River Pattack. This can be seen at the side of the A86 road in Strath Mashie.

Between 1941 and 1943, the catchment was further expanded by constructing another dam across the headwaters of the River Spey, and diverting flow through a tunnel to Loch Laggan. This was constructed by the 1st Tunnelling Company of the Canadian Army. [7]

Related Research Articles

Sir William Halcrow was one of the most notable English civil engineers of the 20th century, particularly renowned for his expertise in the design of tunnels and for projects during the Second World War.

<span class="mw-page-title-main">Loch Laggan</span> Freshwater loch in Highland, Scotland

Loch Laggan is a freshwater loch situated approximately 6+12 mi (10.5 km) west of Dalwhinnie in the Scottish Highlands. The loch has an irregular shape, runs nearly northeast to southwest and is approximately 7 mi (11 km) in length. It has an average depth of 68 ft (21 m) and is 174 ft (53 m) at its deepest. The eastern end of the loch features the largest freshwater beach in Britain. Since 1934 Loch Laggan has been part of the Lochaber hydro-electric scheme. At the northeast end of the loch is the hamlet of Kinloch Laggan.

<span class="mw-page-title-main">Lochaber Narrow Gauge Railway</span>

The Lochaber Narrow Gauge Railway was a 3 ft narrow-gauge industrial railway. It was a relatively long line, built for the construction and subsequent maintenance of a 15-mile-long (24-kilometre) tunnel from Loch Treig to a factory near Fort William in Scotland. The tunnel was excavated to carry water for the Lochaber hydroelectric scheme in connection with aluminium production by British Aluminium. The railway came to be known colloquially as the 'Old Puggy Line'.

<span class="mw-page-title-main">River Conon</span> River in Scotland

The River Conon is a river in the Highlands of Scotland. It begins at Loch Luichart, and flows in a south-easterly direction to be joined by the River Meig at Scatwell before passing through Loch Achonachie. It is joined by the Black Water at Moy Bridge, and the River Orrin at Urray, before flowing past Conon Bridge and into the Cromarty Firth.

<span class="mw-page-title-main">Tummel hydro-electric power scheme</span> Power stations in Perth and Inverness

The Tummel hydro-electric power scheme is an interconnected network of dams, power stations, aqueducts and electric power transmission in the Grampian Mountains of Scotland. Roughly bounded by Dalwhinnie in the north, Rannoch Moor in the west and Pitlochry in the east it comprises a water catchment area of around 1,800 square kilometres and primary water storage at Loch Ericht, Loch Errochty, Loch Rannoch and Loch Tummel, in Perth and Kinross. Water, depending on where it originates and the path it takes, may pass through as many as five of the schemes nine power stations as it progresses from north-west to south-east. The scheme was constructed in the 1940s and 50s incorporating some earlier sites. It is managed by SSE plc.

<span class="mw-page-title-main">Affric-Beauly hydro-electric power scheme</span> Power stations on River Affric and River Beauly in Scottish Highlands

The Affric-Beauly hydro-electric power scheme for the generation of hydro-electric power is located in the western Highlands of Scotland. It is based around Glen Strathfarrar, Glen Cannich and Glen Affric, and Strathglass further downstream.

<span class="mw-page-title-main">Glendoe Hydro Scheme</span> Hydro-electric power scheme in Scotland

The Glendoe Hydro Scheme for the generation of hydro-electric power is located in the Monadhliath Mountains near Fort Augustus, above Loch Ness in the Highlands of Scotland. The change in financial incentives following the publication of the Renewables Obligation in 2001 caused Scottish and Southern Energy (SSE) to reconsider a number of schemes that had been mothballed in the 1960s by the North of Scotland Hydro-Electric Board, and plans for the Glendoe scheme were resurrected.

<span class="mw-page-title-main">Oker Dam</span> Dam

The Oker Dam is a dam in the Harz mountains in Lower Saxony, Germany. It is fed by the River Oker.

<span class="mw-page-title-main">River Garry, Inverness-shire</span> River and power stations in Scotland

The River Garry in Inverness-shire is a Scottish river punctuated by two long Lochs, in the region of Lochaber. It flows broadly west to east through Glen Garry, starting in a wilderness to the east of Knoydart and ending at Loch Oich in the Great Glen, which forms part of the Caledonian Canal. There are a few tiny settlements within Glen Garry, but the only village of any size near to the river is Invergarry, at its mouth. Loch Quoich at the western end of the watercourse is dammed by the largest mass earth fill dam in Scotland, and supplies water to Quoich hydroelectric power station. Loch Garry is dammed by a much smaller dam in the gorge where the river begins its descent to Invergarry, and supplies water to Invergarry hydroelectric power station, close to the mouth of the river. Both hydroelectric schemes were built in the 1950s, with the aim of stimulating economic regeneration in the area. They have altered the ecology of the river, as both lochs were made considerably bigger as a result of constructing the dams.

The Lochaber hydroelectric scheme is a hydroelectric power generation project constructed in the Lochaber area of the western Scottish Highlands after the First World War. Like its predecessors at Kinlochleven and Foyers, it was designed to provide electricity for aluminium production, this time at Fort William.

Deep Creek Dam is a major ungated concrete gravity dam across the Deep Creek in the Snowy Mountains of New South Wales, Australia. The dam's main purpose is for the diversion of water for generation of hydro-power and is the smallest of the sixteen major dams that comprise the Snowy Mountains Scheme, a vast hydroelectricity and irrigation complex constructed in south-east Australia between 1949 and 1974 and now run by Snowy Hydro.

Island Bend Dam is a major gated concrete gravity dam with a controlled spillway across the Snowy River in the Snowy Mountains region of New South Wales, Australia. The dam's main purpose is for the diversion of water for generation of hydro-power and is one of the sixteen major dams that comprise the Snowy Mountains Scheme, a vast hydroelectricity and irrigation complex constructed in south-east Australia between 1949 and 1974 and now run by Snowy Hydro.

The Kukule Ganga Dam is a 110 m (360 ft) gravity dam built across the Kukule River in Kalawana, Sri Lanka. The run-of-river dam feeds an underground hydroelectric power station located approximately 5 kilometres (3.1 mi) away, via tunnel.

<span class="mw-page-title-main">Breadalbane Hydro-Electric Scheme</span> Multiple power stations in Scotland

The Breadalbane Hydro-Electric Scheme is a hydroelectric scheme in the Breadalbane area of Perthshire, Scotland. It comprises seven power stations which generate 120MW of power from the dams around Loch Lyon, Loch Earn and Loch Tay.

<span class="mw-page-title-main">River Spean</span> River in the West Highlands of Scotland

The River Spean flows from Loch Laggan in a westerly direction to join the River Lochy at Gairlochy in the Great Glen in the West Highlands of Scotland. Major tributaries of the Spean include the left-bank Abhainn Ghuilbinn and River Treig, the right-bank River Roy and the left-bank river known as The Cour. The river is accompanied by the A86 road for almost its entire length, running from (upper) Loch Laggan west to Spean Bridge. The river is spanned by a bridge carrying the A82 road near its junction with the A86 at Spean Bridge. A minor road bridges the Spean just above the falls at Inverlair. Two further road crossings exist - a private estate road across the short stretch of river between upper Loch Laggan and the Laggan reservoir and a road traversing the top of Laggan Dam. The West Highland Line crosses the river near Tulloch Station and follows its north bank before re-crossing one mile east of Spean Bridge. A branch of the railway formerly continued west beside the river from Spean Bridge, crossing it once again to the west of the village.

<span class="mw-page-title-main">Pamba Dam</span> Dam in Kerala, India

Pamba Dam is a gravity dam built on the Pamba river in the Ranni forest area of Seethathodu panchayat in Pathanamthitta district of Kerala, India. It was built in 1967 as part of the Sabarigiri Hydroelectric Project. Sabarigiri Hydro Electric Project (IHEP) is the second largest hydro electric project in Kerala. Pamba dam's reservoir is connected to the nearby Kakki dam's reservoir by a 3.21 km (1.99 mi) long underground tunnel. The dam is 281 m (922 ft) long and 57.2 m (188 ft) high and is located at an elevation of 981.45 m (3,220.0 ft) above sea level. The dam is located in a forest area adjacent to the Periyar National Park. The water stored in the Pamba and Kakki dams is conveyed to the Sabarigiri powerhouse through penstock pipes. The dam was commissioned in 1967.

<span class="mw-page-title-main">Gavi Dam</span> Dam in Kerala

Gavi Dam or Gaviar Dam is a small, gravity dam constructed as a part of Sabarigiri hydro electric project on Gaviyar, which is a tributary of Pamba river at Seethathode village in Pathanamthitta district of Kerala, India. Taluks through which release flow are Ranni, Konni, Kozhencherry, Thiruvalla, Chengannur, Kuttanadu, Mavelikara and Karthikappally.

<span class="mw-page-title-main">Shira Hydro-Electric Scheme</span> Power stations near Loch Fyne, Scotland

The Shira Hydro-Electric Scheme is a project initiated by the North of Scotland Hydro-Electric Board to use the waters of the River Shira, the River Fyne and other small streams to generate hydroelectricity. It is located between Loch Fyne and Loch Awe in Argyll and Bute, western Scotland. It consists of three power stations and three impounding dams.

<span class="mw-page-title-main">Kilmelfort Hydro-Electric Scheme</span> Power station near Kilmelford, Scotland

Kilmelfort Hydro-Electric Scheme is a small-scale hydro-electric power station, built by the North of Scotland Hydro-Electric Board and commissioned in 1956. It is located near Kilmelford in Argyll and Bute, Scotland. It was originally designed to supply power to the local communities around Kilmelford, but is now connected to the National Grid.

<span class="mw-page-title-main">Kinlochleven hydroelectric scheme</span> Hydroelectric scheme for aluminium smelter in Scottish Highlands

The Kinlochleven hydroelectric scheme was built between 1905 and 1909 to supply power for an Aluminium smelter owned by British Aluminium. It was the second in Scotland after the 1896 Falls of Foyers scheme. The smelter and power house were constructed on the south bank of the River Leven in the village of Kinlochleven, in the south-west of the Scottish Highlands.

References

  1. 1 2 Historic Environment Scotland. "Lochaber Hydroelectric Scheme and Aluminium Smelter, Loch Laggan Dam (Category A Listed Building) (LB6835)" . Retrieved 27 March 2019.
  2. "Record Details - Loch Laggan Hydro Electric Dam". Highland Historic Environment Record. Highland Council. Retrieved 30 August 2013.
  3. "Transactions". International Commission on Large Dams: 79. 1936.
  4. 1 2 3 4 5 Wallis, R. P.; Morison, A . C.; Gunstensen, R. Remedial drainage to Laggan and Blackwater gravity dams (PDF) (Report).
  5. "Laggan Dam". International Commission on Large Dams of the World Power Conference: 145. 1964.
  6. 1 2 3 Naylor, A H (February 1937). "The Second-Stage Development of the Lochaber Water-Power Scheme (includes photographs and appendices)". Journal of the Institution of Civil Engineers. 5 (4): 3–48. doi:10.1680/ijoti.1937.14769. ISSN   0368-2455.
  7. Payne, Peter L. (1988). The Hydro: A study of the development of the major hydro-electric schemes undertaken by the North of Scotland Hydro-Electric Board. Aberdeen: Aberdeen Univ. Pr. p. 14. ISBN   978-0-08-036584-8.