Mundra Ultra Mega Power Plant

Last updated

Mundra Ultra Mega Power Project (TATA POWER LIMITED)
Mundra Ultra Mega Power Plant
CountryIndia
LocationTunda village in Mundra, Kutch district, Gujarat
Coordinates 22°49′20″N69°31′56″E / 22.82222°N 69.53222°E / 22.82222; 69.53222 Coordinates: 22°49′20″N69°31′56″E / 22.82222°N 69.53222°E / 22.82222; 69.53222
StatusOperational
Construction began2007
Commission date 2012-2013
Owner(s) Tata Power
Operator(s)Coastal Gujarat Power Ltd.
Thermal power station
Primary fuel Subbituminous coal
Power generation
Units operational5 × 800 MW
Make and model Toshiba, Doosan
Nameplate capacity 4,000 MW

Mundra Ultra Mega Power Project or Mundra UMPP is a subbituminous coal-fired power plant in Tunda village at Mundra, Kutch district, Gujarat, India. It is the 3rd largest operational power plant in India. The coal for the power plant is imported primarily from Indonesia. The source of water for the power plant is sea water from Gulf of Kutch. The power plant is owned by Tata Power. The special purpose vehicle Coastal Gujarat Power Ltd (CGPL) was incorporated on 10 February 2006. [1]

Contents

Capacity

The capacity of the project is 4,000 MW with 5 units of 800 MW each.

StageUnit NumberInstalled Capacity (MW)Date of Commissioning
1st10800March 2012 [2]
2nd20800July 2012 [3]
3rd30800October 2012 [4]
4th40800January 2013 [5]
5th50800March 2013 [6]
TotalFive4000

Technology

The plant uses super-critical boiler technology. Compared to other sub-critical plants in India, Mundra UMPP would use 1.7 million tonnes of less coal per year while generating the same quantum of power. [4] Boilers are supplied by Doosan and turbines are supplied by Toshiba.

Buyers

Tata Power entered into a power purchase agreement for the sale of the 4,000 MW capacity of the plant. [7]

StateContracted Capacity (MW)
Gujarat 1,805
Maharashtra 760
Punjab 475
Rajasthan 380
Haryana 380
Non-PPA200
Total4000

In January 2013, the company terminated the PPA with the Rajasthan distribution companies - Jaipur Vidyut Vitaran Nigam, Jodhpur Vidyut Vitaran Nigam and Ajmer Vidyut Vitaran Nigam - due to non-compliance on payment security related issues and consistent failure on the part of the discoms as procurers to fulfill their obligations, including collateral arrangements. The company will now have to option of selling the power in the merchant market. [8]

Controversy over power tariff

Tata Power won the project through a competitive tariff based bidding route in 2006 by quoting 55% of the fuel cost as a non-scalable component and a levelised tariff of Rs 2.26 per kWh or unit. [9] The Indonesian government's decision in 2010 to change its mining law to bring coal price exported from Indonesia in line with the international market [10] caused an increase in coal price and under-recovery of costs at Mundra UMGPP (and similarly impacted Adani Power's 4620 MW Mundra plant). The loss led to an erosion of Tata Power's net worth by over 3800 crore in 3 years. [11] The company had accordingly petitioned the Central Electricity Regulatory Commission for compensatory tariff hike, and later for compensatory relief.

In December 2016 the Central Electricity Regulatory Commission allowed compensatory relief for Tata Power from the electricity procuring states under the Force Majeure clause after having awarded in February 2014 a compensatory tariff of 52 paise per unit; [12] however the orders are subject to the outcome of a pending appeal in the Supreme Court. The compensatory relief also is to be adjusted against profits made in sale of coal from the Indonesian mines where the companies have a stake.

In 2007, Tata Power had acquired a 30% stake in two Indonesian thermal coal companies owned by PT Bumi Resources—PT Kaltim Prima Coal (KPC) and PT Arutmin Indonesia— for about $1.1 billion [13] as part of a strategy to provide low cost coal for the Mundra UMPP.

In 2014, Tata Power agreed to sell a 30% stake it held in PT Arutmin Indonesia, to the Bakrie Group for a sale consideration of $510 million (later revised to $400 million). No date has been set for his sale closure, which is pending regulatory clearances from the authorities

The company had requested Central Electricity Regulatory Commission to allow a tariff hike to about Rs 3.00 per unit [14]

The company had petitioned the CERC to rule whether the company can claim relief under any/all of the following: [15]

The company stand is that the definition of law under the PPA is an inclusive (and not exhaustive) definition. The definition of law covers 'any law' and is not restricted to Indian law. The term 'law' is required to be interpreted in a contextual basis with a view to give business efficacy to the PPA since the project is based on imported coal and the fuel supply arrangements are a part of the Project Documents. The definition of Law must be given a plenary meaning and cannot be read down by confining it to Indian laws. The promulgation and enforcement of 'Regulation of Ministry of Energy and Mineral Resources No. 17 of 2010 regard procedure for Setting Mineral and Coal Benchmark Selling Price' dated 23.09.2010 by Government of Indonesia ("Indonesian Regulations") led to an unprecedented, uncontrollable and unforeseeable rise in coal prices which constitutes a 'Change in Law' under the PPA.

The definition of Force Majeure under Article 12.3 of the PPA covers "any event or circumstance or combination of events or circumstances that wholly or partly prevents or unavoidably delays an Affected Party in performing its obligations under the PPA to the extent such events or circumstances are not within the reasonable control, directly or indirectly of the Affected Party and could not have been avoided if the Affected Party had taken reasonable care". Tata Power is arguing that the promulgation of the Indonesian Regulation is an event which is beyond its control and has made it impossible for the company to perform its obligations as per the contracted price. So this is covered as a Force Majeure event under Article 12.3 of the PPA.

Tata Power is arguing that CERC has the power under Section 79(1)(b) of the Electricity Act, 2003 to revisit/restructure the tariff for a power project if the project has lost its viability and it has become commercially impossible for the project owner to perform its contractual obligations.

On 18 July 2012 the Central Electricity Regulatory Commission deferred a decision on Tata Power's petition. Central Electricity Regulatory Commission has asked the company to go back and take recourse to the dispute resolution provisions of the power purchase agreement (PPA) before seeking relief from the Central Electricity Regulatory Commission. [16]

On 25 October 2012 the CERC admitted the petition for hearing since the consultative process under Article 17.3 of the Power Purchase Agreement (PPA) between Coastal Gujarat Power Ltd and the lead procurer, Gujarat Urja Vikas Nigam Limited (GUVNL) had failed. The petition will now be renotified for hearing on 4 December 2012. [17]

See also

Related Research Articles

<span class="mw-page-title-main">Electricity sector in India</span> Electricity generation and distribution in India

India is the third largest producer of electricity in the world. During the fiscal year (FY) 2019–20, the total electricity generation in the country was 1,598 TWh, of which 1,383.5 TWh generated by utilities. The gross electricity consumption per capita in FY2019 was 1,208 kWh.

<span class="mw-page-title-main">Tata Power</span> Indian electric utility company

Tata Power Company Limited is an Indian electric utility company based in Mumbai, Maharashtra, India and is part of the Tata Group. The core business of the company is to generate, transmit and distribute electricity. With an installed electricity generation capacity of 10,577 MW, it is India's largest integrated power company. Tata Power has been ranked 3rd in 2017 Responsible Business Rankings developed by IIM Udaipur. In February 2017, Tata Power became the first Indian company to ship over 1 GW solar modules.

<span class="mw-page-title-main">Adani Group</span> Indian conglomerate

Adani Group is an Indian multinational conglomerate, headquartered in Ahmedabad. It was founded by Gautam Adani in 1988 as a commodity trading business, with the flagship company Adani Enterprises. The Group's diverse businesses include port management, electric power generation and transmission, renewable energy, mining, airport operations, natural gas, food processing and infrastructure. Adani Group employs over 100,000 people worldwide.

Ultra Mega Power Projects (UMPP) are a series of ambitious power stations planned by the Government of India. This would entail the creation of an additional capacity of at least 100,000 MW by 2022. Ultra Mega Power projects, each with a capacity of 4000 MW or above, are being developed with the aim of bridging this gap.

<span class="mw-page-title-main">Solar power in India</span>

Solar power is a fast developing industry in India. The country's solar installed capacity was 63.303 GWAC as of 31 December 2022. Solar power generation in India ranks fourth globally in 2021.

<span class="mw-page-title-main">Availability-based tariff</span>

Availability Based Tariff (ABT) is a frequency based pricing mechanism applicable in India for unscheduled electric power transactions. The ABT falls under electricity market mechanisms to charge and regulate power to achieve short term and long term network stability as well as incentives and dis-incentives to grid participants against deviations in committed supplies as the case may be.

<span class="mw-page-title-main">Economy of Gujarat</span> Economy of the Indian state of Gujarat

The economy of Gujarat, a state in Western India, has significant agricultural as well as industrial production within India. Major agricultural produce of the state includes cotton, groundnuts (peanuts), dates, sugar cane, milk and milk products. Gujarat is one of the most industrialised states, with significant presence in pharma, chemicals, refining and petrochemicals, ceramics, textiles, automobile etc. sectors. Gujarat recorded the lowest unemployment rate in India in 2015, with 1.2% of the labour force being unemployed.

Uttar Pradesh Rajya Vidyut Utpadan Nigam Limited (UPRVUNL) was constituted on dated 25.08.1980 under the Companies' Act 1956 for construction of new thermal power projects in the state sector. On 14 January 2000, in accordance to U.P. State Electr Reforms Acts 1999 and operation of U.P. Electricity Reforms Transfer Scheme 2000, U.P. State Electricity Board (U.P.S.E.B.), till then responsible for generation, transmission and distribution of power within the state of Uttar Pradesh, was unbundled and operations of the state sector thermal power stations were handed over to UPRVUNL. Unchahar Thermal Power Station - 420 MW (2X210) & Tanda Thermal Power Station 440 MW (4X110) were transferred to NTPC in year 1992 & year 2000 respectively before unbundling of U.P. State Electricity Board (U.P.S.E.B.) into;

  1. Uttar Pradesh Rajya Vidyut Utpadan Nigam Limited (UPRVUNL),
  2. Uttar Pradesh Power Corporation Limited (UPPCL),
  3. UP Power Transmission Corporation Limited (UPPTCL),
  4. UP Jal Vidyut Nigam Limited (UPJVNL).

Central Electricity Regulatory Commission (CERC), a key regulator of power sector in India, is a statutory body functioning with quasi-judicial status under sec – 76 of the Electricity Act 2003. CERC was initially constituted on 24 July 1998 under the Ministry of Power's Electricity Regulatory Commissions Act, 1998 for rationalization of electricity tariffs, transparent policies regarding subsidies, promotion of efficient and environmentally benign policies, and for matters connected Electricity Tariff regulation. CERC was instituted primarily to regulate the tariff of Power Generating companies owned or controlled by the government of India, and any other generating company which has a composite scheme for power generation and interstate transmission of energy, including tariffs of generating companies.

<span class="mw-page-title-main">Adani Power</span> Electricity company in Ahmedabad, India

Adani Power is an Indian power and energy company which is a part of Adani Group. Based in Khodiyar in Ahmedabad, it is a private thermal power producer, with a capacity of 12,450 MW and operates a mega solar plant of 40 MW at Naliya, Bitta, Kutch, Gujarat.

<span class="mw-page-title-main">NTPC Limited</span> Central Public Sector Undertaking

NTPC Limited, formerly known as National Thermal Power Corporation Limited, is an Indian central public sector undertaking under the ownership of the Ministry of Power, Government of India which is engaged in generation of electricity and allied activities. The headquarters of the psu is situated at New Delhi. NTPC's core function is the generation and distribution of electricity to State Electricity Boards in India. The body also undertakes consultancy and turnkey project contracts that involve engineering, project management, construction management, and operation and management of power plants.

Mithapur Solar Power Plant is a 25 MW solar power plant located in Mithapur, Gujarat. It is expected to produce 40,734 MWh/year. 108,696 230 Wp panels were used.

<span class="mw-page-title-main">Mundra Thermal Power Station</span>

Mundra Thermal Power Station is located at Mundra in Kutch district in the Indian state of Gujarat. The power plant is one of the coal-based power plants of Adani Power. The coal for the power plant is imported primarily from Bunyu, Indonesia. Source of water for the power plant is sea water from the Gulf of Kutch.

<span class="mw-page-title-main">Bihar State Power Holding Company Limited</span> Electricity board in Bihar, India

Bihar State Power Holding Company Limited (BSPHCL), formerly Bihar State Electricity Board (BSEB) is a state-owned electricity regulation board operating within the state of Bihar in India. BSEB was established in 1958 as a statutory corporation under the Electricity (Supply) Act, 1948. As of November 2012, BSEB has nearly 1,700 officers and 14,850 employees. The derated capacity comes to just 530 MW. The BSEB was unbundled on 2 August 2011. Power Finance Corporation was the main consultant for BSEB's restructuring.

<span class="mw-page-title-main">Barauni Thermal Power Station</span> Building in India

NTPC, Barauni Or Barauni Thermal Power Station is an existing 720 megawatt coal-fired power station earlier owned by Bihar State Electricity Board (BSEB)and currently by NTPC Limited. The power station is located at Barauni in Begusarai district, Bihar, India. Barauni thermal power station in Bihar came into existence in association with the Russian collaboration and came into operation in the year 1962. Bihar Government was mulling over the idea to hand over Barauni Thermal Power Station to NTPC Limited. On 17 April 2018, Bihar state cabinet, headed by chief minister Nitish Kumar, gave its nod to handing over of Barauni Thermal Power Station to National Thermal Power Corporation. On 15 May 2018, Bihar Government signed a memorandum of understanding (MoU) to hand over the thermal plant to National Thermal Power Corporation for a 33- years lease. East Central Railway will provide uninterrupted supply of coal to thermal power station. NTPC completed the acquisition of 720 MW Barauni thermal power plant with effect from 15 December 2018. The units of Barauni power station will be progressively put under commercial operation. On 27 November 2021, Bihar CM Nitish Kumar inaugurated 250 Megawatts Powerhouse Unit in Barauni Thermal Power Station.

Sasan Ultra Mega Power Plant or Sasan UMPP is one of the four Ultra Mega Power Projects awarded by the Ministry of Power, Government of India. It is located in Sasan village near Waidhan in Singrauli district of Madhya Pradesh. Sasan UMPP is India's largest integrated power generation and coal mine project with 3,960 MW power plant and 20 MT per year coal mining capacity. It is presently the 4th largest electricity generation power plant in India after NTPC Vindhyachal, Mundra Thermal Power and Mundra UMPP. The total project value of Sasan UMPP is ₹25,186 crores.

Uttar Pradesh Power Corporation Limited (UPPCL) is the company responsible for electricity transmission and distribution within the Indian state of Uttar Pradesh. The incumbent chairman is Shri M. Devraj.

The Nabinagar Thermal Power Station Project (NTPS) of Bhartiya Rail Bijlee Company Limited is a wholly owned subsidiary of the Indian Railways, Ministry of Railways, Government of India. It installs a 4X 250 MW thermal power plant at Nabinagar in Aurangabad district, Bihar, India. Nearly 90 per cent of the electricity generated from the plant is supplied to the railways to meet nationwide requirements and remaining 10 per cent is given to Bihar.

References

  1. "Coastal Gujarat Power Ltd (CGPL)". Tata Power. Retrieved 9 January 2012.{{cite web}}: CS1 maint: url-status (link)
  2. "Tata Power commissions Mundra UMPP's first 800 MW unit". Business Standard. Press Trust of India. 9 March 2012. Retrieved 9 January 2013.
  3. Shankar Subramaniam. "Business Line : Companies News : Tata Power's Mundra plant Unit II becomes operational". Business Line. Retrieved 9 January 2013.
  4. 1 2 "Tata Power synchronises third 800 MW unit at Mundra UMPP - PTI". Moneycontrol.com. Retrieved 9 January 2013.
  5. Vora, Rutam (7 January 2013). "Tata Power synchronises unit 4 of Mundra UMPP". Business Standard. Retrieved 9 January 2013.
  6. "Tata Power commissions Mundra UMPP 5th unit".
  7. "Tata Power sees Rs 3,000 crore equity erosion in Mundra UMPP project: Sources - Economic Times". The Economic Times. Press Trust of India. 7 October 2012. Retrieved 9 January 2013.
  8. Kumar, Abhineet (5 January 2013). "Rajasthan break to put Tata's Mundra power in open market". Business Standard. Retrieved 9 January 2013.
  9. "Mundra braces for CERC order". The Financial Express. Retrieved 9 January 2013.
  10. DNA India (3 July 2012). "On Mundra UMPP, great confusion, no clear solution - Money - DNA". Daily News and Analysis. Retrieved 9 January 2013.
  11. "Mundra UMPP has eroded Tata Power's net worth by Rs 3,800 crore in three years: Anil Sardana". The Financial Express. 25 March 2016. Retrieved 10 December 2016.
  12. Debapriya Mondal (8 December 2016). "Major relief for Tata Power, Adani in compensatory tariff case". ET EnergyWorld. Retrieved 10 December 2016.
  13. Live Mint (1 December 2016). "Tata Power cuts sale consideration for Arutmin mine in Indonesia to $246 mn". Live Mint. Retrieved 10 December 2016.
  14. "Tata Power seeks higher tariff for Mundra UMPP". Business Standard. Press Trust of India. 17 July 2012. Retrieved 9 January 2013.
  15. Central Electricity Regulatory Commission India (4 December 2012). "Record of Proceedings in Petition No. 159 of 2012" (PDF). cercind.gov.in. Retrieved 9 January 2013.
  16. "CERC defers decision on Tata Power plea". The Financial Express. Retrieved 9 January 2013.
  17. http://www.cercind.gov.in/2012/orders/Signed_Order_159_2012.pdf [ bare URL PDF ]