Sapperton Railway Tunnel

Last updated

Sapperton tunnel
Sapperton.jpg
Railway tunnels with cutting
Overview
Line Golden Valley Line
Location Sapperton, Gloucestershire
Statusoperational
Technical
Length1 mi 104 yd (1.704 km)
Track gauge 4 ft 8+12 in (1,435 mm)

The Sapperton Railway Tunnel is a railway tunnel near Sapperton, Gloucestershire in the United Kingdom. It carries the Golden Valley Line from Stroud to Swindon through the Cotswold escarpment. It was begun by the Cheltenham and Great Western Union railway in 1839 and taken over by the Great Western Railway in 1843, being completed in 1845. [1] There are actually two tunnels, the main one at 1 mi 104 yd (1.704 km) in length, [2] and separated by a short gap, a second at 353 yd (323 m). [3]

Contents

Construction, engineering, and maintenance difficulties

The initial plans for the tunnel, dating from 1835, were unusual in that it was proposed to construct the tunnel on a curve, but this seems to have been abandoned before any construction was done; some works remain which are thought to relate to the approach route for the original line, but no excavations were made on that line for the tunnel itself. In 1836 "Mr Brunel" was appointed as engineer for the project; [4] this refers to Isambard, but the involvement of "Mark (sic) Brunel" is also recorded. [5] Brunel promised to get rid of the "objectionable" curve, and plans of the revised straight alignment were deposited in 1838. Preliminary shafts were dug, the work beginning in 1837, to ascertain the geological conditions, on the same straight alignment on which the tunnel was eventually built. In 1841 work began on four additional shafts of a larger diameter, quoted as 3[ which? ] or 6 metres [6] by different sources, plus a trial heading along the tunnel alignment. The line was opened in 1845.

Geological cross-section of Sapperton railway tunnel Sapperton-tunnel-cross-section.png
Geological cross-section of Sapperton railway tunnel

It was found that the intended route passed through a layer of fuller's earth, which was not sufficiently stable to allow construction of a tunnel. [5] The plans were therefore revised to situate the tunnel in more stable strata at a shallower depth, at the expense of steeper gradients on the approaches. This also reduced the length of the tunnel from 2,830 yd (2,590 m), on a 1 in 352 gradient in the 1836 plan, or 2,730 yd (2,500 m) on 1 in 330 in the 1838 plan (1 in 90 in the main tunnel, as built, and 1 in 57 on the approach to it), and so reduced construction costs; a 1950 article, based on the original contract and specification, quoted the directors as saying it would, "considerably diminish its length and expense" and asserted that this was the actual reason for the change to the shallower depth, rather than simply an effect of it. The 1950 article said that the drainage through the oolite was so good that construction was probably started from the foot of each shaft without drainage. Brunel was quoted as reporting in October 1841 that, "the drainage of the water is obtained into the lower oolite, without pumping, at one of the intermediate shafts" [7] Therefore, although it included the geological cross-section (drawn by GWR engineer, Mr. R. P. Brereton), [8] it made no mention of fuller's earth problems. [4] Later articles say the section shows that the header, on the originally-proposed deeper level, passes through a much greater length of fuller's earth than the tunnel as built, and that it also makes it clear that information gained from digging the shafts would have made it apparent that this would be the case. [5]

This diagram also casts doubt on the unsupported assertions which are sometimes made [9] [10] that the gap between the two tunnels is the result of a roof collapse in the early days of the tunnel. [11] This gap coincides precisely with the level section at the summit of the line, and also with a dip in the contours of the ground above which brings the ground level below the depth at which the transition from tunnel to cutting is made at the outer ends of the tunnels. It is unlikely that a chance collapse would have taken place to correspond with these features with such convenient precision. The gap is also shown to be in the more stable oolitic strata rather than the unstable stretches of fuller's earth which are more liable to collapse. [12]

The lateral alignment of the revised tunnel route was the same as the planned deeper route, and this left the ten exploratory shafts intersecting the tunnel and continuing as pits up to 6 metres deep below the tunnel floor. The pits were capped with timber to support the track and ballast. [13] However, no records were left as to whether or not the pits had been filled in.

In 1950 a train driver noticed a void beneath the tracks and it became apparent that work was required to stabilise the pits. [14] The original timbers were removed and the pits spanned with prefabricated concrete beams reinforced with bullhead rail and shear links. One more beam was fabricated than was required for the work and this was stored in a nearby yard. Again it was not recorded whether the pits were filled.

In November 2000, heavy flooding caused the collapse of one of the capped shafts. Emergency work over a period of four weeks was carried out to stabilise the collapsed shaft and similar preventative work was carried out on some of the other shafts; [15] the four larger shafts, however, were left untouched. An erroneous report attributes the damage to the collapse of the canal tunnel running underneath; [16] in reality the canal tunnel is to the north of the rail tunnel and does not pass underneath it.[ citation needed ]

In 2001 it was decided to test the redundant beam remaining from the 1950 operations to destruction in order to determine its strength, as part of surveys intended to discover whether the route would support the loadings required for a route availability index of 8. It was found that the concrete had deteriorated and would not support the loads required for an index of more than 5.[ citation needed ] Further stabilisation was therefore required as a matter of urgency.

The operation was carried out under a complete possession over a period of seven days by over 100 people working 12-hour shifts, many of whom were accommodated in temporary buildings at the site. Road-rail plant was used, standing on one track of the double-track tunnel to remove the other track and replace the beams underneath. The 1950 beams were cut into three sections using a diamond-tipped saw blade to facilitate removal. Each pit was then spanned with new prefabricated beams, one main support beam under each rail plus additional spacer beams to fill the gap between them. The new beams were fabricated in three sections to avoid exceeding the working load of the plant, which were joined once the beams were in place using stainless steel bolts. After work on the one track was completed, the road-rail plant was put into road mode and driven onto the new beams from where it could work on the other track.[ citation needed ]

Not until the old beams were removed did it become known that the pits had indeed been backfilled in the course of earlier work and the fears of falling into a six-metre hole were unfounded.[ citation needed ]

The seven-day possession did not give enough time to fully stabilise all four large shafts. Priority was given to the two least stable ones and the work on those was completed, but the remaining two were only partially stabilised, the beams under the up line being replaced but those under the down line being left alone. A further operation was scheduled for Easter 2002 to perform these final replacements. [5] [6] [17]

A roof collapse occurred in October 2009, necessitating the closure of the line for relining work. [18] [19]

Accidents

A collision took place near Sapperton Tunnel (mis-spelt as "Salperton") on 4 December 1851. A goods train approaching the tunnel from the Swindon direction was overcome by the gradient after passing Tetbury Road station, and the driver decided to divide the train, taking the front portion forward and returning later to collect the rear portion. Unfortunately the brakes on the rear portion failed and it ran back down the gradient to collide with a following train. The goods vehicles were destroyed and the driver and passengers of the following train sustained injuries, but there were no fatalities. [20]

A minor accident occurred at the tunnel on 29 October 1855 also involving a train becoming divided and one portion running away. There were no injuries or deaths and it is thought that no investigation was carried out. [21]

Four platelayers were killed in the tunnel on 14 April 1896. This is mentioned in Hansard for 27 April 1896 (the report mis-spells "Stroud" as "Strood") but no details are given. [22]

On 9 December 2009 a door on an HST came open in the vicinity of the tunnel and a passenger attempted to close it, without success but at some personal risk. A local newspaper attempted to sensationalise the incident by stating that the passenger concerned was "almost thrown from the train" as the door "flew" open. In fact nobody was near the door when it opened, and any risk to the passenger concerned arose entirely as a result of his decision to attempt to close it. [23]

Local councillor Andrew Gravells is quoted as saying that trains should be fitted with devices to prevent departure from stations if doors are open. This requirement already exists, [24] and older slam-door stock such as the HST was retrofitted with a central door locking system in which a power-operated bolt, activated by the guard, prevents the doors from opening while the train is in motion; however this system is not interlocked with the driving controls. [25] It is not clear how the system failed on this occasion; the RAIB was informed of the incident but no report appears to exist on their website.

Disruption to train services was caused on 17 January 2011 when a huntsman and twenty fox-hounds trespassed on the line near the east end of the tunnel. One of the hounds was struck by a train and killed. The train was cancelled and other trains suffered delays. The trespassers had disappeared by the time British Transport Police officers arrived, and no hunt admitted responsibility. [26]

See also

Related Research Articles

<span class="mw-page-title-main">Bristol Temple Meads railway station</span> Major railway station for the city of Bristol, England

Bristol Temple Meads is the oldest and largest railway station in Bristol, England. It is located 118 miles 31 chains away from London Paddington. It is an important transport hub for public transport in the city; there are bus services to many parts of the city and surrounding districts, with a ferry to the city centre. Bristol's other major station, Bristol Parkway, is a more recent station on the northern outskirts of the conurbation.

<span class="mw-page-title-main">Great Western Railway</span> British railway company (1833–1947)

The Great Western Railway (GWR) was a British railway company that linked London with the southwest, west and West Midlands of England and most of Wales. It was founded in 1833, received its enabling Act of Parliament on 31 August 1835 and ran its first trains in 1838 with the initial route completed between London and Bristol in 1841. It was engineered by Isambard Kingdom Brunel, who chose a broad gauge of 7 ft —later slightly widened to 7 ft 14 in —but, from 1854, a series of amalgamations saw it also operate 4 ft 8+12 in standard-gauge trains; the last broad-gauge services were operated in 1892.

<span class="mw-page-title-main">Box Tunnel</span> Railway tunnel in western England

Box Tunnel passes through Box Hill on the Great Western Main Line (GWML) between Bath and Chippenham. The 1.83-mile (2.95 km) tunnel was the world's longest railway tunnel when it was completed in 1841.

<span class="mw-page-title-main">Tunnel</span> Underground passage made for traffic

A tunnel is an underground passageway, dug through surrounding soil, earth or rock, and enclosed except for the entrance and exit, commonly at each end. A pipeline is not a tunnel, though some recent tunnels have used immersed tube construction techniques rather than traditional tunnel boring methods.

<span class="mw-page-title-main">Severn Tunnel</span> Tunnel linking the South of England and Wales

The Severn Tunnel is a railway tunnel in the United Kingdom, linking South Gloucestershire in the west of England to Monmouthshire in south Wales under the estuary of the River Severn. It was constructed by the Great Western Railway (GWR) between 1873 and 1886 for the purpose of dramatically shortening the journey times of their trains, passenger and goods alike, between South Wales and Western England. It has often been regarded as the crowning achievement of GWR's chief engineer Sir John Hawkshaw.

<span class="mw-page-title-main">Thames Tunnel</span> Tunnel crossing under the River Thames in London

The Thames Tunnel is a tunnel beneath the River Thames in London, connecting Rotherhithe and Wapping. It measures 35 ft (11 m) wide by 20 ft (6.1 m) high and is 1,300 ft (400 m) long, running at a depth of 75 ft (23 m) below the river surface measured at high tide. It is the first tunnel known to have been constructed successfully underneath a navigable river. It was built between 1825 and 1843 by Marc Brunel, and his son, Isambard, using the tunnelling shield newly invented by the elder Brunel and Thomas Cochrane.

<span class="mw-page-title-main">Great Western Main Line</span> Important railway corridor in England, UK

The Great Western Main Line (GWML) is a main line railway in England that runs westwards from London Paddington to Bristol Temple Meads. It connects to other main lines such as those from Reading to Penzance and Swindon to Swansea. Opened in 1841, it was the original route of the first Great Western Railway which was merged into the Western Region of British Railways in 1948. It is now a part of the national rail system managed by Network Rail with the majority of passenger services provided by the current Great Western Railway franchise.

<span class="mw-page-title-main">Standedge Tunnels</span> Tunnels between Marsden and Diggle in northern England

The Standedge Tunnels are four parallel tunnels through the Pennine hills at the Standedge crossing between Marsden in Kirklees, West Yorkshire and Diggle in Oldham, Greater Manchester in northern England. Three are railway tunnels and the other is a canal tunnel. Before boundary changes in 1974, both ends of the tunnels were in the West Riding of Yorkshire.

<span class="mw-page-title-main">Calder Valley line</span> Railway line in England

The Calder Valley line is a railway route in Northern England between the cities of Leeds and Manchester as well as the seaside resort of Blackpool. It is the slower of the two main rail routes between Leeds and Manchester, and the northernmost of the three main trans-Pennine routes.

<span class="mw-page-title-main">Golden Valley line</span> Railway line in England

The Golden Valley line is the popular name given to the railway line between Swindon, Gloucester and Cheltenham Spa in England.

<span class="mw-page-title-main">South Wales Main Line</span> Railway from Bristol to Swansea

The South Wales Main Line, originally known as the London, Bristol and South Wales Direct Railway or simply as the Bristol and South Wales Direct Railway, is a branch of the Great Western Main Line in Great Britain. It diverges from the core London-Bristol line at Royal Wootton Bassett beyond Swindon, first calling at Bristol Parkway, after which the line continues through the Severn Tunnel into South Wales.

<span class="mw-page-title-main">Swindon railway station</span> Railway station in Wiltshire, England

Swindon railway station is on the Great Western Main Line in South West England, serving the town of Swindon, Wiltshire. It is 77 miles 23 chains down the line from the zero point at London Paddington and is situated between Didcot Parkway and Chippenham on the main line. It is managed by Great Western Railway, which also operates all of the services from the station.

<span class="mw-page-title-main">Sapperton Canal Tunnel</span> Tunnel on the Thames and Severn Canal near Cirencester in Gloucestershire, England

The Sapperton Canal Tunnel is a tunnel on the Thames and Severn Canal near Cirencester in Gloucestershire, England. With a length of 3,817 yards (3,490 m), it was the longest tunnel of any kind in England from 1789 to 1811.

Clifton Hall Tunnel, also called (locally) the Black Harry Tunnel, was a railway tunnel passing beneath much of Swinton and Pendlebury, in Greater Manchester, England. It was located on the Patricroft and Clifton branch of the London and North Western Railway line, linking Patricroft with Molyneux Junction.

The Cheltenham and Great Western Union Railway was a railway company intended to link Cheltenham, Gloucester and Swindon, in England. It was authorised in 1836 but it found it very hard to raise money for the construction, and it opened only a part of its line, between Swindon and Cirencester, in 1841. It sold its business to the Great Western Railway, which quickly built the line through to Gloucester in 1845 and Cheltenham in 1847; part of that route was shared with other companies.

<span class="mw-page-title-main">Rail profile</span> Cross sectional shape of a railway rail

The rail profile is the cross sectional shape of a railway rail, perpendicular to its length.

The Midland and South Western Junction Railway (M&SWJR) was an independent railway built to form a north–south link between the Midland Railway and the London and South Western Railway in England, allowing the Midland and other companies' trains to reach the port of Southampton. The M&SWJR was formed in 1884 from the amalgamation of the Swindon, Marlborough and Andover Railway and the Swindon and Cheltenham Extension Railway. The line was absorbed by the Great Western Railway at the 1923 grouping of the railways, and became part of British Railways on nationalisation in 1948. The railway closed to passengers in 1961, and to goods between 1964 and 1970. A small part of it has been reopened as the heritage Swindon and Cricklade Railway.

<span class="mw-page-title-main">Kolkata Metro Line 2</span> Transit line in Kolkata, India

Kolkata Metro Line 2, also known as the East-West Metro and Green Line, is a rapid transit line of the Kolkata Metro in the Indian state of West Bengal. It currently consists of an operational section between Salt Lake and Sealdah, and will eventually connect Howrah by going underneath the Hooghly River, with an eastern extension also planned for Teghoria. It would consist of 17 stations from Teghoria (Haldiram) in the east to Howrah Maidan in the west, of which 11 would be elevated and 6 would be underground, with a total distance of 22 km (14 mi). It is expected to derive a very high ridership since it will connect India's two largest commuter railway and long-distance railway terminals (Howrah and along with two of its largest business districts. It will also be connecting the industrial hub of Kolkata i.e. Howrah and the IT hub of Kolkata i.e. Sector 5. Line 2 has India's biggest underwater metro tunnel along with the deepest metro shaft. In the deepest metro shaft, Howrah metro station will be the deepest metro station in India, which will be 33 meters deep.The first phase between Salt Lake Sector V and Salt Lake Stadium was inaugurated by Union Railway Minister Piyush Goyal on 13 February 2020 and commercial services started from 14 February 2020.

The Bristol and Gloucestershire Railway was an early mineral railway, opened in two stages in 1832 and 1834, which connected collieries near Coalpit Heath with Bristol, at the river Avon. Horse traction was used. It was later taken over by the Bristol and Gloucester Railway, and much of the route became part of the main line between Birmingham and Bristol, though that was later by-passed and closed. Part of it now forms the Bristol and Bath Railway Path.

<span class="mw-page-title-main">Cockett railway station</span> Former railway station in Wales

Cockett railway station was a former station on the West Wales Line from Swansea to Gowerton and onwards to Llanelli.

References

Map all coordinates using: OpenStreetMap
  1. 'Sapperton: Introduction', A History of the County of Gloucester: Volume 11. Bisley and Longtree Hundreds. 1976. pp. 87–90. Archived from the original on 16 May 2009. Retrieved 31 August 2009.
  2. 51°43′25″N2°6′6″W / 51.72361°N 2.10167°W to 51°42′59.5″N2°4′48″W / 51.716528°N 2.08000°W
  3. 51°42′58.5″N2°4′44.5″W / 51.716250°N 2.079028°W to 51°42′54″N2°4′30″W / 51.71500°N 2.07500°W
  4. 1 2 "The Approaches to Sapperton Railway Tunnels" (PDF). 1998. Archived (PDF) from the original on 1 February 2014. Retrieved 28 May 2013.
  5. 1 2 3 4 "The Rail Engineer - Featured Articles". December 2009. Archived from the original on 3 July 2013. Retrieved 28 May 2013.
  6. 1 2 "Network Rail Media Centre - Victorian Shafts at Sapperton Get Strengthened". 22 October 2009. Archived from the original on 7 July 2013. Retrieved 28 May 2013.
  7. Household, Humphrey (February 1950). "Sapperton Tunnel, Western Region". Railway Magazine. Retrieved 22 May 2017.
  8. "Full text of "Proceedings of the Cotteswold Naturalists' Field Club"". archive.org. May 1870. Archived from the original on 12 July 2013. Retrieved 22 May 2017.
  9. "The Cheltenham Flyer". Archived from the original on 2 July 2013. Retrieved 29 May 2013.
  10. "Diesel multiple unit, 1950s". 10 January 2013. Archived from the original on 26 June 2014. Retrieved 29 May 2013.
  11. "The Cheltenham Flyer - Railway Wonders of the World". railwaywondersoftheworld.com. Archived from the original on 28 June 2019. Retrieved 10 September 2018.
  12. "Early History of the Sapperton Railway Tunnels" (PDF). Gloucestershire Local History Association. Retrieved 15 July 2020.
  13. "Victorian Shafts at Sapperton get strengthened". Network Rail. Retrieved 15 July 2020.
  14. "Accidents". Bygone Transport. Retrieved 15 July 2020.
  15. "Cheltenham-Swindon Rail Line". Hansard. 22 November 2000. Archived from the original on 26 October 2016. Retrieved 28 May 2013.
  16. "Chaos over as rail track is reopened". 25 November 2000. Archived from the original on 3 February 2014. Retrieved 28 May 2013.
  17. "Sapperton Tunnel, Gloucestershire, UK". Archived from the original on 6 December 2013. Retrieved 28 May 2013.
  18. "Swindon to Kemble Railway". 27 October 2009. Archived from the original on 4 March 2016. Retrieved 29 May 2013.
  19. "Rail Travel Disruption Monday 26th to Friday 30th October". October 2009. Archived from the original on 27 February 2013. Retrieved 29 May 2013.
  20. "The Great Western Rail Crash". The Cotswold History Blog. 30 May 2011. Archived from the original on 4 June 2011. Retrieved 15 July 2020.
  21. "Accident at Sapperton Tunnel on 29th October 1855". Archived from the original on 13 January 2016. Retrieved 28 May 2013.
  22. "PLATELAYERS KILLED (SAPPERTON TUNNEL)". Parliamentary Debates (Hansard) . HC Deb 27 April 1896 vol 39 cc1732-3. 27 April 1896. Archived from the original on 23 December 2012. Retrieved 28 May 2013.{{cite web}}: CS1 maint: location (link)
  23. "Call for inquiry after train door incident". 30 December 2009. Archived from the original on 21 February 2014. Retrieved 15 July 2020.
  24. "Railway Group Standard GM/RT2473 section B7.4" (PDF). February 2003. Retrieved 28 May 2013.[ permanent dead link ]
  25. "From "USER GUIDE for the operation of CENTRAL DOOR LOCKS on InterCity Slam Door Coaching Stock"". Archived from the original on 13 January 2016. Retrieved 28 May 2013.
  26. "Hunt in Cotswolds strayed on rail line claim". 2 February 2011. Archived from the original on 17 March 2011. Retrieved 29 May 2013.