Company type | Private |
---|---|
Industry | Energy |
Founded | 2004 |
Founder | Edward Krapels |
Headquarters | , |
Key people | Clarke Bruno (CEO) Janice Fuller (President, Mid-Atlantic) Peter Shattuck (President, New England) Bryan Sanderson (Partner, Project Manager) Howard Kosel (Partner, Project Manager) Luis Ortiz (Vice President, Storage) |
Products | Transmission battery storage |
Website | anbaric |
Anbaric Development Partners (Anbaric) is an American electric power transmission and storage development company located in Wakefield, Massachusetts. The company develops smart grid, [1] renewable energy, and large-scale electric transmission projects which use high-voltage direct current (HVDC) technology for clients in the United States and internationally.
Anbaric delivers power from energy producers to population centers through the use of underground and submarine transmission lines. [1] Anbaric specializes in the development stages of transmission projects including conceiving, designing, and leading projects' proposal processes, which can take years. [1] [2] Its customers include governments, investor-owned utilities, and public power generators. [1] The company's headquarters are located in Wakefield, Massachusetts. [1] [3]
Senior leadership includes Clark Bruno, President and CEO, Janice Fuller who is in charge of all mid-Atlantic development, Peter Shattuck who leads transmission development in New England, and project managers Bryan Sanderson, and Howard Kosel. Luis Ortiz head up electric battery storage development. [4] Edward N. Krapels Ph.D was the founder of Anbaric Holding, LLC, the parent company of Anbaric. [1] Krapels died in 2020.
Anbaric Transmission, LLC was incorporated in 2004 by founder Edward Krapels. [1] In 2001, Krapels began work as a market advisor for Atlantic Energy Partners on a project known as the Neptune Regional Transmission System, a submarine transmission connection between New Jersey and Long Island. [5] Krapels has stated that he obtained an ownership interest in the project, from which he founded Anbaric in order to focus on such transmission projects. [5] Anbaric was then part of the merchant group that developed the Neptune RTS project, which was completed in 2007. [6] In the late 2000s the company, along with other partners, completed additional projects including the Hudson Transmission System, which brings power from northern New Jersey to New York. [7]
In February 2015, Anbaric announced plans to develop a series of microgrids in New York State in response to New York’s call for more distributed generation resources and increased energy reliability. [8] [9] Anbaric has partnered with Exelon Corporation to build 10-200 megawatt microgrids in New York. [10]
In March 2017, Anbaric and Ontario Teachers' Pension Plan created a new development company, Anbaric Development Partners. [11] The partnership was formed to develop clean energy infrastructure projects in North America, with Anbaric's management team leading the new company and Ontario Teachers’ committing to funding development costs, projected to produce $2 billion in fully constructed assets. The announcement marked the largest financial commitment by an investor in the company’s 15-year history. [12]
Anbaric's projects include the design and development of power transmission and distributed generation energy projects. [1] [2] [13] Its completed projects include the Neptune Regional Transmission System and the Hudson Transmission System, while ongoing projects in development include the Bay State Offshore Wind Transmission System, Vermont Green Line, Maine Green Line, West Point Project, and Poseidon Project. [14]
The Neptune Cable, or the Neptune Regional Transmission System, is a 660-MW high-voltage direct current line that connects Sayreville, New Jersey (site of the Sayreville Energy Center) to Long Island. [6] Construction on the $600 million project began in fall 2005. [15] The 65-mile transmission line became operational in June 2007, and was developed by a merchant group including Anbaric. [6] As of 2007, the line was the largest source of imported electricity to Long Island. [15] In a 2007 report, the New York ISO noted that the Neptune cable reduced electricity prices in New York, and substantially reduced transmission congestion into Long Island and New York City. [16]
The Hudson Project, or the Hudson Transmission System, is project developed by a partnership including Anbaric. It consists of a 660-MW high-voltage direct current system which connects upstate New Jersey and Manhattan by traveling beneath the Hudson River. [17] [18] The cable carries power from an electrical substation in Ridgefield Park, New Jersey (site of the Bergen Generating Station) to one located on West 49th Street, New York and provides enough power for 400,000 homes. [7] The project was completed in 2013 and cost approximately $850 million. [7]
Anbaric’s target microgrid customers include real estate buildings, hospitals, industrial facilities, government buildings, and municipalities throughout New York. [19] In the summer of 2015, Anbaric was part of a team that received funding from New York State’s NY Prize program to conduct microgrid feasibility studies in the Village of Freeport and Staten Island University Hospital. [20] [21]
By November 2011, Anbaric had filed an interconnection request with ISO New England for the Bay State Offshore Wind Transmission System. The planned project consists of two 1,000-MW HVDC lines and, if approved, would be New England's first offshore transmission trunk line. [22] [17] [23]
West Point Partners, LLC, a subsidiary of Anbaric, submitted a proposal in June, 2013 to the New York Public Service Commission to create an 80-mile power line which would run beneath the Hudson River to bring power to the New York metro area. [24] [25] The line would carry 1,000-MW of power from wind, solar, and natural gas producers. [24] [26] Estimated costs of the project are around $900 million. [25] Anbaric's partner, PowerBridge LLC, is developing the line. [27] The project would have interconnected the grid from a substation in Athens, New York to a substation near the Indian Point Energy Center, but was tabled when the landowner where the southern converter station would be located, Con Edison, sold the land to the Village of Buchanan. The Village of Buchanan then sold the rights to use the land to the natural gas company Spectra for their new proposed natural gas pipeline. [28]
Anbaric subsidiary Poseidon Transmission, LLC, filed an application in October 2013 with the New York Public Service Commission to begin construction on the Poseidon Project. This project seeks to bring 500-MW of power to the Long Island power grid via an underground high-voltage direct current transmission cable which would connect the Deans Substation in South Brunswick, New Jersey to the Ruland Road Substation in Huntington, New York. [29]
As of May 2013, the Vermont Green Line has been proposed by GII Development LLC, a subsidiary of Anbaric Holdings LLC managing the project. The proposal followed an April 2013 Customer Open Solicitation carried out by GII Development as per new guidelines issued by the Federal Energy Regulatory Commission. [30] The solicitation received a strong response from energy producers with requests for transmission in excess of the lines potential capacity. [31] If approved, the line would travel under Lake Champlain and carry 400-MW of electricity from Plattsburgh, New York to a Vermont Electric Power Company substation located in New Haven, Vermont. [30] [32] The company has begun the process of seeking permits from New York, Vermont, and the United States Army Corps of Engineers, which could take up to two years. [33]
On December 9, 2014, Anbaric and National Grid announced the formation of Green Line Infrastructure Alliance. [34] The Alliance aims to provide benefits to New England's energy consumers by providing consumers with access to large-scale, cost-effective sources of renewable and zero-emission energy; diversifying the region’s energy portfolio, thereby easing the constraints on the natural gas pipeline system and providing access to affordable clean energy; enabling the New England states to meet all current clean energy targets by 2020 at affordable prices and enhancing the reliability and resilience of the region’s power grid.
The Alliance's first project will be Maine Green Line, a hybrid land-and-sea HVDC project that will initially deliver 1,000MW of wind from northern Maine, firmed up by imports of hydropower from eastern Canada, via a submarine cable to Massachusetts. Maine-based constructor Cianbro Development Corporation will be a part of this project. Connecticut-based PowerBridge has been part of the Maine Green Line Development team.
Anabaric has submitted a proposal to develop the New York-New Jersey Wind Energy Transmission Line [35] [36]
A variable-frequency transformer (VFT) is used to transmit electricity between two alternating current frequency domains. The VFT is a relatively recent development. Most asynchronous grid inter-ties use high-voltage direct current converters, while synchronous grid inter-ties are connected by lines and "ordinary" transformers, but without the ability to control power flow between the systems, or with phase-shifting transformer with some flow control.
The London Array is a 175-turbine 630 MW Round 2 offshore wind farm located 20 kilometres (12 mi) off the Kent coast in the outer Thames Estuary in the United Kingdom. It was the largest offshore wind farm in the world until Walney Extension reached full production in September 2018.
Greater Gabbard is a 504 MW wind farm, built on sandbanks 23 kilometres (14 mi) off the coast of Suffolk in England at a cost of £1.5 billion. It was completed on 7 September 2012 with all of the Siemens SWT3.6–107 turbines connected. Developed as a joint venture between Airtricity and Fluor, it is now jointly owned by SSE Renewables and Innogy.
TenneT is a transmission system operator in the Netherlands and in a large part of Germany.
The Burbo Bank Offshore Wind Farm is a 348 MW offshore wind farm located on the Burbo Flats in Liverpool Bay on the west coast of the UK in the Irish Sea. It consists of an original 90 MW wind farm commissioned in 2007 and a 258 MW extension completed in 2017.
An electrical grid is an interconnected network for electricity delivery from producers to consumers. Electrical grids consist of power stations, electrical substations to step voltage up or down, electric power transmission to carry power long distances, and lastly electric power distribution to individual customers, where voltage is stepped down again to the required service voltage(s). Electrical grids vary in size and can cover whole countries or continents. From small to large there are microgrids, wide area synchronous grids, and super grids.
The electricity sectors of the Republic of Ireland and Northern Ireland are integrated and supply 2.5 million customers from a combination of coal, peat, natural gas, wind and hydropower. In 2022, 34 TWh were generated. In 2018 natural gas produced 51.8%, while wind turbines generated 28.1%, coal 7%, and peat 6.8% of Ireland's average electricity demand. In 2020 wind turbines generated 36.3% of Ireland's electrical demand, one of the highest wind power proportions in the world. While the United Kingdom was one of the first countries in the world to deploy commercial nuclear power plants, the island of Ireland has never had a nuclear power plant built on either side of the Irish border. Nuclear power in Ireland was discussed in the 1960s and 1970s but ultimately never phased in, with legislation now in place explicitly forbidding its introduction.
As of November 2023, wind power in the Netherlands has an installed capacity of 11,602 MW, 40.9% of which is based offshore. In 2022, the wind turbines provided the country with 18.37% of its electricity demand during the year. Windmills have historically played a major part in the Netherlands by providing an alternative to water driven mills.
The Lincs Wind Farm is a 270 MW offshore wind farm 8 kilometres (5.0 mi) off Skegness on the east coast of England. The total cost of the project is estimated at £1 billion including electrical transmission links. The farm was completed in 2013. It is adjacent to the smaller Lynn and Inner Dowsing Wind Farm.
The Neptune Cable is a 500kV and 660 MW high-voltage direct current submarine power cable between Sayreville, New Jersey and New Cassel, New York, on Long Island. It carries 22 percent of Long Island's electricity. It was developed by Anbaric Development Partners.
The Champlain Hudson Power Express (CHPE) is a planned high-voltage direct current (HVDC) underwater and underground power cable project linking the Quebec area to the New York City neighborhood of Astoria, Queens. Following completion of a review by the New York State Public Service Commission, construction began in 2022. The line is permitted and expected to be operational in 2026.
Humber Gateway Wind Farm is an offshore wind farm 8 kilometres (5 mi) east of Spurn Point off the coast of North East Lincolnshire, in the North Sea, England; the wind farm is located in water depths around 15 metres (49 ft) and covers an area of approximately 25 square kilometres (9.7 sq mi). The wind farm became operational in June 2015.
Westermost Rough Wind Farm is an offshore wind farm 8 kilometres (5 mi) north east of Withernsea off the Holderness coast, in the North Sea, England. The farm covers an area of approximately 35 km2 (14 sq mi) with a generation capacity of approximately 210 MW. It became operational in May 2015.
Wind power in New Jersey is in the early stages of development. New Jersey has just six wind turbines, but the state has plans to develop several major offshore wind projects on the continental shelf of the Atlantic Ocean off the southern Jersey Shore. Legislation has been enacted to support the industry through economic incentives and to permit wind turbines on existing piers.
The Hudson Project is a 345 kV AC underground and submarine power cable system which supplies electric power to New York City from the Bergen Generating Station, in Ridgefield, New Jersey. The cable system was laid by Anbaric Development Partners.
Wind power in the Philippines accounts for a total of 443MW as of 2020 according to the Department of Energy, covering about 1.6% of the country's total installed capacity for both renewable and non-renewable energy sources. When it comes to existing renewable energy sources in the country, wind power has a total share of approximately 5.4%. Despite currently being a small contributor to the country's energy mix, wind power installations have increased from 33MW in 2012-2013 to 337MW in 2014, 427MW in 2015-2018, and 443MW in 2019-2021. Moreover, the Department of Energy's National Renewable Energy Plan (NREP) 2020-2040 aims to commission 2,345MW of total wind power capacity by 2030. There has been a setback, however, as the wind power industry was moderately affected by COVID, particularly in the import of wind turbines. Due to this, several projects such as the Aklan onshore wind project got delayed. To further drive the wind energy sector in the country, an increased demand for renewable energy, greater government commitments, and reduced wind power tariff are needed.
Ocean Wind was a proposed utility-scale 2,248 MW offshore wind farm to be located on the Outer Continental Shelf approximately 15 miles (24 km) off the coast of Atlantic City, New Jersey. It was being developed by Ørsted US Offshore Wind in conjunction with Public Service Enterprise Group (PSE&G). Construction and commissioning were planned for the mid-2020s. The closed Oyster Creek Nuclear Generating Station and B.L. England Generating Station would provide transmission points for energy generated by the wind farm.
South Fork Wind Farm is a utility-scale offshore wind farm project on the Outer Continental Shelf Offshore Rhode Island (RI) which will provide energy to New York state.
Empire Wind is a proposed utility-scale offshore wind farm on the Outer Continental Shelf Offshore New York. It will be located in Bureau of Ocean Energy Management (BOEM) lease area OCS-A 0512 in the New York Bight about 15 miles (24 km) south of Jones Beach, Long Island.