Transmission congestion

Last updated

In power engineering, transmission congestion occurs when overloaded transmission lines in an electrical grid are unable to carry additional electricity flow due to the risk of overheating. During grid congestion, the transmission system operator (TSO) has to direct the providers to adjust their dispatch levels to accommodate the constraint. [1] In an electricity market a power plant may be able to produce electricity at a competitive price but cannot transmit the power to a willing buyer. [2] Congestion increases the electricity prices for some customers. [3]

Contents

Definitions

There is no universally accepted definition of the transmission congestion. [2] Congestion is not an event, so it is frequently not possible to pinpoint its place and time (in this respect it is similar to traffic congestion [4] ). Regulators define congestion as a condition that prevents market transactions from being completed, [2] while a transmission system operator sees it as inability to maintain the security of the power system operation with the power flow scheduled for the grid. [3]

A congestion is a symptom of a constraint or a combination of constraints in a transmission system, [3] usually the limits on physical electricity flow are used to prevent the overheating, unacceptable voltage levels, and loss of system stability. Congestion can be permanent, an effect of the system configuration, or temporary, due to a fault in the transmission equipment. [5]

Congestion management

Avoiding the congestion is essential for a competitive electricity market and is "one of the toughest problems" of its design. The goal is to ensure that a power flow as defined by the wholesale market result does not violate the constraints during the normal operation of the grid and in the case of failure of any one particular component (so called n-1 criterion). [6]

The existing markets use a range of approaches to solve the problem. On one end of this range is "uniform pricing" that ignores the transmission constraints altogether and lets the market find a single price for all the locations ("nodes"). On the other end "locational marginal pricing" accommodates all the constraints by defining a separate pricing for each node (thus another name, "nodal pricing"). [6]

The uniform pricing has an advantage of transparent market design and quick clearing, so auctions can happen frequently, typically they start a day ahead of the delivery ("day-ahead" auction) and continue until the delivery (so called "intra-day" auctions).[ citation needed ] However, the market result might violate the congestion constraints and thus cannot be implemented at the time of delivery (in "real-time"). If this is the case, the TSO intervenes and uses so called system redispatch by changing the schedules of the generators in a way that the load can be served. [6] Redispatch payments are usually negotiated in advance and providers are paid as they bid in a "command and control" fashion, without creating a market. [7]

With nodal pricing all grid constraints are accounted for during the clearing and different prices are set for different nodes, this typically requires the independent system operator (ISO) to manage the market clearing. [8] The drawback of the nodal pricing is that the local markets might not have enough participants to efficiently function. In particular, in the load pockets (areas of the grid with concentrated load and lack of tie lines to the rest of the system) a large generator might exhibit significant market power, forcing the price for this node to be directly regulated on a cost basis.[ citation needed ]

The zonal pricing represents a compromise where the grid is split into relatively large zones, electricity price within each zone is uniform (and thus intra-zone congestion need to be resolved with a redispatch), but the inter-zone constraints are accounted for during the market clearing via different prices for different zones. [9]

The "discriminatory pricing" the providers in case of acceptance of their bids by the system operator are paid the amount of their bid ("pay-as-offered", [10] "pay-as-bid"). [11] The discriminatory pricing is also used in a market-based redispatch scenario (counter-trading). [7]

Transmission rights

To avoid congestion, it might be necessary to deny some transmission transactions. One way to do it is through the transmission rights. The owner of a transmission right is entitled to transport a predefined amount of electric power from a source location on the network to the destination. There are two types of transmission rights: [12]

Example of an FTR operation

In a simple example of FTR operation, [13] locations A and B are connected with a 1000 MW line. Location A has a load of 200 MW and two generation companies:

Location B has a load of 2500 MW and a single generator GB with 2000 MW capacity and marginal cost of $30/MW.

The electricity market with locational pricing will fully engage the 1000 MW line and settle on:

GA1, standing to gain most if the links between A and B are improved, decides to build another 1000-MW transmission line. Now there is no congestion, and the market will settle at the same price in both A and B ($30, since GA1 and GA2 cannot satisfy all demand, and the price will be determined by the cost of GB). GA1 will hold the FTR for 1000 MW, but will not collect anything from this right, instead pocketing the difference between its $10 cost and $30 price.

A new plant, GA3, is constructed in A with capacity of 1000 MW and marginal cost of $9/MW. Now the pricing in A is $15 again (determined by GA2), pricing at B is still $30. Although the line built by GA1 might now be effectively used by GA3, GA1 as a holder of FTR receives the congestion rent for electricity transmitted over the line that GA1 had invested into. The arrangement works as if GA1 had leased the line to GA3 for the full value of the line, so FTRs are similar to tradable securities, but with automated trading. [13]

Transmission access charge

Some transmission system operators offer the transmission rights owner to collect the transmission fees for them. For example, in California the California Independent System Operator (CAISO) offers the PTR owners a scheme where the owners hand over the operational control of their infrastructure to CAISO in exchange for the "Transmission Revenue Requirement" (TRR) that recoups the owner's costs. CAISO in turn collects the Transmission Access Charge (TAC) from the utilities based on the gross load, [14] and utilities bill TAC to their customers.

Related Research Articles

<span class="mw-page-title-main">Electric power transmission</span> Bulk movement of electrical energy

Electric power transmission is the bulk movement of electrical energy from a generating site, such as a power plant, to an electrical substation. The interconnected lines that facilitate this movement form a transmission network. This is distinct from the local wiring between high-voltage substations and customers, which is typically referred to as electric power distribution. The combined transmission and distribution network is part of electricity delivery, known as the electrical grid.

An electricity market is a system that enables the exchange of electrical energy, through an electrical grid. Historically, electricity has been primarily sold by companies that operate electric generators, and purchased by consumers or electricity retailers.

<span class="mw-page-title-main">Bonneville Power Administration</span> United States federal agency that provides power supply to the Pacific Northwest

The Bonneville Power Administration (BPA) is an American federal agency operating in the Pacific Northwest. BPA was created by an act of Congress in 1937 to market electric power from the Bonneville Dam located on the Columbia River and to construct facilities necessary to transmit that power. Congress has since designated Bonneville to be the marketing agent for power from all of the federally owned hydroelectric projects in the Pacific Northwest. Bonneville is one of four regional Federal power marketing agencies within the U.S. Department of Energy (DOE).

<span class="mw-page-title-main">National Grid (Great Britain)</span> High-voltage electric power transmission network in Great Britain

The National Grid is the high-voltage electric power transmission network serving Great Britain, connecting power stations and major substations, and ensuring that electricity generated anywhere on the grid can be used to satisfy demand elsewhere. The network serves the majority of Great Britain and some of the surrounding islands. It does not cover Northern Ireland, which is part of the Irish single electricity market.

<span class="mw-page-title-main">Regional transmission organization (North America)</span> Electric power coordinator

A regional transmission organization (RTO) in the United States is an electric power transmission system operator (TSO) that coordinates, controls, and monitors a multi-state electric grid. The transfer of electricity between states is considered interstate commerce, and electric grids spanning multiple states are therefore regulated by the Federal Energy Regulatory Commission (FERC). The voluntary creation of RTOs was initiated by FERC in December 1999. The purpose of the RTO is to promote economic efficiency, reliability, and non-discriminatory practices while reducing government oversight.

<span class="mw-page-title-main">Demand response</span> Techniques used to prevent power networks from being overwhelmed

Demand response is a change in the power consumption of an electric utility customer to better match the demand for power with the supply. Until the 21st century decrease in the cost of pumped storage and batteries, electric energy could not be easily stored, so utilities have traditionally matched demand and supply by throttling the production rate of their power plants, taking generating units on or off line, or importing power from other utilities. There are limits to what can be achieved on the supply side, because some generating units can take a long time to come up to full power, some units may be very expensive to operate, and demand can at times be greater than the capacity of all the available power plants put together. Demand response, a type of energy demand management, seeks to adjust in real-time the demand for power instead of adjusting the supply.

<span class="mw-page-title-main">Merit order</span> Ranking of available sources of energy

The merit order is a way of ranking available sources of energy, especially electrical generation, based on ascending order of price and sometimes pollution, together with amount of energy that will be generated. In a centralized management, the ranking is so that those with the lowest marginal costs are the first ones to be brought online to meet demand, and the plants with the highest marginal costs are the last to be brought on line. Dispatching generation in this way, known as economic dispatch, minimizes the cost of production of electricity. Sometimes generating units must be started out of merit order, due to transmission congestion, system reliability or other reasons.

<span class="mw-page-title-main">Load management</span> Process of balancing the supply of electricity on a network

Load management, also known as demand-side management (DSM), is the process of balancing the supply of electricity on the network with the electrical load by adjusting or controlling the load rather than the power station output. This can be achieved by direct intervention of the utility in real time, by the use of frequency sensitive relays triggering the circuit breakers, by time clocks, or by using special tariffs to influence consumer behavior. Load management allows utilities to reduce demand for electricity during peak usage times, which can, in turn, reduce costs by eliminating the need for peaking power plants. In addition, some peaking power plants can take more than an hour to bring on-line which makes load management even more critical should a plant go off-line unexpectedly for example. Load management can also help reduce harmful emissions, since peaking plants or backup generators are often dirtier and less efficient than base load power plants. New load-management technologies are constantly under development — both by private industry and public entities.

The electricity sector in New Zealand uses mainly renewable energy, such as hydropower, geothermal power and increasingly wind energy. As of 2021, the country generated 81.2% of its electricity from renewable sources. The strategy of electrification is being pursued to enhance the penetration of renewable energy sources and to reduce greenhouse gas (GHG) emissions across all sectors of the economy. In 2021, electricity consumption reached 40 terawatt-hours (TW⋅h), representing a 0.2% increase compared to the consumption levels in 2010.

Availability Based Tariff (ABT) is a frequency based pricing mechanism applicable in India for unscheduled electric power transactions. The ABT falls under electricity market mechanisms to charge and regulate power to achieve short term and long term network stability as well as incentives and dis-incentives to grid participants against deviations in committed supplies as the case may be.

<span class="mw-page-title-main">PJM Interconnection</span> Major electric grid coordinator in northeastern USA

PJM Interconnection LLC (PJM) is a regional transmission organization (RTO) in the United States. It is part of the Eastern Interconnection grid operating an electric transmission system serving all or parts of Delaware, Illinois, Indiana, Kentucky, Maryland, Michigan, New Jersey, North Carolina, Ohio, Pennsylvania, Tennessee, Virginia, West Virginia, and the District of Columbia.

<span class="mw-page-title-main">Super grid</span> Wide-area electricity transmission network

A super grid or supergrid is a wide-area transmission network, generally trans-continental or multinational, that is intended to make possible the trade of high volumes of electricity across great distances. It is sometimes also referred to as a "mega grid". Super grids typically are proposed to use high-voltage direct current (HVDC) to transmit electricity long distances. The latest generation of HVDC power lines can transmit energy with losses of only 1.6% per 1,000 km.

<span class="mw-page-title-main">California Independent System Operator</span> Non-profit Independent System Operator serving California

The California Independent System Operator (CAISO) is a non-profit Independent System Operator (ISO) serving California. It oversees the operation of California's bulk electric power system, transmission lines, and electricity market generated and transmitted by its member utilities. CAISO is one of the largest ISOs in the world, delivering 300 million megawatt-hours of electricity each year and managing about 80% of California's electric flow.

The unit commitment problem (UC) in electrical power production is a large family of mathematical optimization problems where the production of a set of electrical generators is coordinated in order to achieve some common target, usually either matching the energy demand at minimum cost or maximizing revenue from electricity production. This is necessary because it is difficult to store electrical energy on a scale comparable with normal consumption; hence, each (substantial) variation in the consumption must be matched by a corresponding variation of the production.

<span class="mw-page-title-main">Electricity sector in the Philippines</span> Overview of the electricity sector in the Philippines

The electricity sector in the Philippines provides electricity through power generation, transmission, and distribution to many parts of the country. The Philippines is divided into three electrical grids, one each for Luzon, the Visayas and Mindanao. As of June 2016, the total installed capacity in the Philippines was 20,055 megawatts (MW), of which 14,348 MW was on the Luzon grid. As of June, 2016, the all-time peak demand on Luzon was 9,726 MW at 2:00 P.M. on May 2, 2016; on Visayas was 1,878 MW at 2:00 P.M. on May 11, 2016; and on Mindanao was 1,593 MW at 1:35 P.M. on June 8, 2016. However, about 12% of Filipinos have no access to electricity. The Philippines is also one of the countries in the world that has a fully functioning electricity market since 2006 called the Philippine Wholesale Electricity Spot Market(WESM) and is operated by an independent market operator.

<span class="mw-page-title-main">Duck curve</span> Graph showing the timing imbalance between peak demand and renewable electricity production

The duck curve is a graph of power production over the course of a day that shows the timing imbalance between peak demand and solar power generation. The graph resembles a sitting duck, and thus the term was created. Used in utility-scale electricity generation, the term was coined in 2012 by the California Independent System Operator.

A load pocket is an area of electric grid that has limited ability to import electricity due to either very high concentration of demand or insufficient transmission capabilities and therefore cannot be entirely provided with power without participation of local electricity generation providers. A typical load pocket includes a major city. Load pocket's existence usually indicates difficulties with building of either new generation or new transmission, or both due to the area constraints or political pressure and despite the pocket being an attractive place for investment. The load pockets represent a problem for the deregulated electricity markets, as in the absence of regulation the captive customers are forced to accept the prices set by the local providers.

Power system operations is a term used in electricity generation to describe the process of decision-making on the timescale from one day to minutes prior to the power delivery. The term power system control describes actions taken in response to unplanned disturbances in order to provide reliable electric supply of acceptable quality. The corresponding engineering branch is called Power System Operations and Control. Electricity is hard to store, so at any moment the supply (generation) shall be balanced with demand. In an electrical grid the task of real-time balancing is performed by a regional-based control center, run by an electric utility in the traditional electricity market. In the restructured North American power transmission grid, these centers belong to balancing authorities numbered 74 in 2016, the entities responsible for operations are also called independent system operators, transmission system operators. The other form of balancing resources of multiple power plants is a power pool. The balancing authorities are overseen by reliability coordinators.

Resource adequacy in the field of electric power is the ability of the electric grid to satisfy the end-user power demand at any time. RA is a component of the electrical grid reliability. For example, sufficient unused generation capacity shall be available to the electrical grid at any time to accommodate major equipment failures and drops in variable renewable energy sources. The adequacy standard should satisfy the chosen reliability index, typically the loss of load expectation (LOLE) of 1 day in 10 years.

References

  1. "What is Electricity Congestion?". tcaptx.com. Texas Coalition for Affordable Power. Retrieved 14 October 2022.
  2. 1 2 3 Zimmerman 2004, p. 219.
  3. 1 2 3 Zimmerman 2004, p. 220.
  4. Zimmerman 2004, p. 218.
  5. ENSO 2001, p. 7.
  6. 1 2 3 Staudt 2019, p. 29.
  7. 1 2 Holmberg & Lazarczyk 2015, p. 147.
  8. Staudt 2019, pp. 29–30.
  9. Staudt 2019, p. 30.
  10. Rassenti, Smith & Wilson 2003.
  11. Holmberg & Lazarczyk 2015, p. 146.
  12. Lyons, Fraser & Parmesano 2000, pp. 32–33.
  13. 1 2 Lyons, Fraser & Parmesano 2000, p. 34.
  14. Alaywan, Ziad; Wu, Tong (2003). "Effects of Firm Transmission Rights on Transmission Revenue Allocation in California". IEEE - PES. p. 3. Retrieved 9 April 2024.

Sources