The Assiut Barrage | |
---|---|
Country | Egypt |
Location | Asyut |
Construction began | 1898 |
Opening date | 1903 |
Construction cost | £870,000 |
Built by | John Aird & Co. |
Dam and spillways | |
Type of dam | Barrage |
Impounds | Nile River |
Height (thalweg) | 48 feet (15 m) |
Spillways | 111 |
Reservoir | |
Maximum water depth | 33.5 feet (10.2 m) |
The Assiut Barrage is a dam on the Nile River in the city of Assiut in Upper Egypt (250 miles to the south of Cairo). It was completed in 1903.
It was designed by the famous British engineer Sir William Willcocks who also concurrently designed and built the Aswan Low Dam, the first Nile reservoir, about 350 miles (560 km) up-stream. The Assiut dam was constructed between 1898 and 1903, and in conjunction with the reservoir, provided for the diversion of river water into Egypt's largest irrigation canal, the Ibrahimiya Canal, during the low water season. The dam was estimated to cost £525,000 but by the time of its completion it actually cost £870,000. The main contractor for the project was the British contractor John Aird & Co. [1] The project's massive size involved 2,400,000 cubic yards of earthwork, 125,000 cubic yards of concrete, 85,000 cubic yards of masonry, 125,000 cubic yards of pitching and more than 4,000 tons of cast iron pipes. [2]
The dam consists of a masonry dam about 2,769 feet (844 m) long extended on both sides by earthen banks, making a total length of about 3,937 feet (1,200 m). There are 111 arched openings of 5 metres (16 feet 5 inches) span in the masonry dam. They can be closed by steel sluice-gates 16 feet (4.9 m) high. The piers and arches are founded upon a masonry platform 87 feet (27 m) wide by 10 feet (3.0 m) thick. This platform is protected on its up-stream and down-stream sides by a continuous and impermeable line of cast iron tongued and grooved sheet-piling with cemented joints. This piling extends into the sand bed of the river to a depth of 23 feet (7.0 m) below the upper surface of the platform and prevents it from being undermined. The river bed is protected against erosion for a width of 67 feet (20 m) upstream by a stone paving laid on a puddle clay blanket to check infiltration, and on the downstream side for the same width by a stone paving having an inverted filter bed underneath, so that any springs that may be caused by the water above the sluices shall not carry sand with them from beneath the paving.
The piers between the openings have a length of 51 feet (16 m) up and down stream and are 6.56 feet (2.00 m) wide with the exception of every thirtieth pier, which has double this width. The roadway is 41 feet (12 m) above the top of the masonry platform. The dam has a maximum height of about 48 feet (15 m), the maximum head of water retained being about 33.5 feet (10.2 m). It is constructed of granite, the foundation platform mentioned above being of concrete. A lock 262.5 feet (80.0 m) long by 52.8 feet (16.1 m) wide and capable of passing the largest Nile cargo ships and barges was constructed at the dam. [3]
The Ibrahimiya head regulator structure, which was built at the same time when the Assiut Barrage was being constructed, was of similar design to the barrage except having only nine 5 m wide sluices, and a 9 m wide lock.
Between 1934 and 1938 the Egyptian Government carried out extensive remodeling works at the barrage and the Ibrahimiya head regulator, principally extending the piers, grouting, extending the approach slabs and updating the hydro-mechanical equipment. The dam was remodeled in 1938 to increase the permissible head to 13.8-foot (4.2 m) from the 13.0-foot (4.0 m) head that was allowed under its original design. In 1956 works were carried out at the Ibrahimiya head regulator as a result of significant scour holes that developed downstream of the structure. Extensions to downstream concrete apron were completed as well as lengthening of the southern lock wall. Some further grouting works and replacement of the lock gates took place in the 1970s. In 1979 a reinforced concrete pedestrian footbridge was constructed on the downstream side of the head regulator. Between 1984 and 1986 a program of cement grouting works was undertaken at the barrage, though there are no records of the head regulator receiving similar treatment. After more than 100 years in service, the civil works have been affected by age and also by tailwater erosion as a consequence of a modified river regime after the construction of the Aswan High Dam.
Along with the Aswan Low Dam, the Assiut Dam today remains in service as the oldest dam on the Nile in Upper Egypt. The two other old dams (Naga Hamadi and Isna Barrages) were replaced with new dams in the 1990s. Between 2000 and 2005, the Egyptian government commissioned an extended Feasibility Study (FS) financed by the German government to investigate the options of rehabilitation of the existing Assiut Barrage and the Ibrahimiya head regulator against reconstruction of a new barrage with a hydro-power plant. German Consultants financed by the Kreditanstalt für Wiederaufbau (KfW) conducted the study and concluded that a new dam with power generating capabilities would be the most economic option. This new dam would provide an increase in the allowed head, allowing more water discharges into the Ibrahimiya Canal and will improve navigation conditions. The new dam will also include a low head hydropower plant providing about 40 Megawatts.
The decision taken upon the results of the feasibility study was to proceed with the project of constructing a new barrage 200-300m downstream of the existing barrage. The proposed dam components are:
There is a concern that the new maximum pool level will increase the groundwater levels in Assiut city and in some areas in the upstream. Dealing with this situation, different layouts of the project have been studied in the feasibility study and some mitigation measures have been suggested.
A dam is a barrier that stops or restricts the flow of surface water or underground streams. Reservoirs created by dams not only suppress floods but also provide water for activities such as irrigation, human consumption, industrial use, aquaculture, and navigability. Hydropower is often used in conjunction with dams to generate electricity. A dam can also be used to collect or store water which can be evenly distributed between locations. Dams generally serve the primary purpose of retaining water, while other structures such as floodgates or levees are used to manage or prevent water flow into specific land regions. The earliest known dam is the Jawa Dam in Jordan, dating to 3,000 BC.
The Aswan Dam, or more specifically since the 1960s, the Aswan High Dam, is one of the world's largest embankment dams, which was built across the Nile in Aswan, Egypt, between 1960 and 1970. Its significance largely eclipsed the previous Aswan Low Dam initially completed in 1902 downstream. Based on the success of the Low Dam, then at its maximum utilization, construction of the High Dam became a key objective of the government following the Egyptian Revolution of 1952; with its ability to better control flooding, provide increased water storage for irrigation and generate hydroelectricity, the dam was seen as pivotal to Egypt's planned industrialization. Like the earlier implementation, the High Dam has had a significant effect on the economy and culture of Egypt.
Richmond Lock and Footbridge is a lock, rising and falling low-tide barrage integrating controlled sluices and pair of pedestrian bridges on the River Thames in south west London, England and is a Grade II* listed structure. It is the furthest downstream of the forty-five Thames locks and the only one owned and operated by the Port of London Authority. It was opened in 1894 and is north-west of the centre of Richmond in a semi-urban part of south-west London. Downstream are Syon Park and Kew Gardens on opposite banks. It connects the promenade at Richmond with the neighbouring district of St. Margarets on the west bank during the day and is closed at night to pedestrians – after 19:30 GMT or after 21:30 when BST is in use. At high tide the sluice gates are raised and partly hidden behind metal arches forming twin footbridges.
The Merowe Dam, also known as Merowe High Dam, Merowe Multi-Purpose Hydro Project or Hamdab Dam, is a large dam near Merowe Town in northern Sudan, about 350 kilometres (220 mi) north of the capital Khartoum. Its dimensions make it the largest contemporary hydropower project in Africa. It is situated on the river Nile, close to and inundating the 4th Cataract where the river divides into multiple smaller branches with large islands in between. Merowe is a city about 40 kilometres (25 mi) downstream from the construction site at Hamdab. The main purpose for building the dam was the generation of electricity.
Nizam Sagar Dam is an Indian dam named after the Nizam of Hyderabad. It is a reservoir constructed across the Manjira River, a tributary of the Godavari River, between Achampet and BanjePally villages of the Kamareddy district in Telangana, India. It is located at about 144 km (89 mi) north-west of Hyderabad. Nizam Sagar is the oldest dam in the state of Telangana.
The flooding of the Nile has been an important natural cycle in Egypt since ancient times. It is celebrated by Egyptians as an annual holiday for two weeks starting August 15, known as Wafaa El-Nil. It is also celebrated in the Coptic Church by ceremonially throwing a martyr's relic into the river, hence the name, The Martyr's Finger. The flooding of the Nile was poetically described in myth as Isis's tears of sorrow for Osiris when killed by their brother Set.
Ghazi-Barotha Hydropower Project is a 1,450 MW run-of-the-river hydropower connected to the Indus River about 10 km (6.2 mi) west of Attock in Punjab and east of Swabi and Haripur districts in Khyber Pakhtunkhwa, Pakistan. Construction of the project that began in 1995 consists of 5 generators each with a maximum power generation capacity of 290MW. Inauguration of the plant on 19 August 2003 by President General Pervez Musharraf also saw the commissioning of the first 2 of the 5 generators i.e. Unit 1 and Unit 2. The last generator was commissioned on 6 April 2004 and the project was completed by that December. It cost US$2.1 billion with funding from Pakistan's Water and Power Development Authority, the World Bank, Asian Development Bank, Japan Bank for International Cooperation, Kreditanstalt für Wiederaufbau, European Investment Bank and Islamic Development Bank.
Sir William Willcocks was a British civil engineer during the high point of the British Empire. He was an irrigation engineer who proposed and built the first Aswan Dam, the scale of which had never been attempted previously. He later undertook other major irrigation projects in South Africa and in Arab regions of the dying Ottoman Empire.
The Rana Pratap Sagar Dam is a gravity masonry dam of 53.8 metres (177 ft) height built on the Chambal River at Rawatbhata in Rajasthan in India. It is part of integrated scheme of a cascade development of the river involving four projects starting with the Gandhi Sagar Dam in the upstream reach in Madhya Pradesh and the Jawahar Sagar Dam on the downstream with a terminal structure of the Kota Barrage in Rajasthan for irrigation.
Sir Murdoch MacDonald was a notable civil engineer and British politician. Born in Inverness, Scotland, MacDonald was educated at the Farraline Park Institution there, and would serve later as the constituency's MP from 1922 until 1950.
The Egyptian Department of Public Works was established in the early 19th century, and concentrates mainly on public works relating to irrigation and hydraulic engineering. These irrigation projects have constituted the bulk of work performed by this entity in Egypt. During its almost 200-year history, the Egyptian Department of Public Works employed many notable engineers and constructed massive public works projects throughout the country. It became the most respected engineering entity and was regarded as the 'best school' for civil engineers in modern Egypt. Its history can be broken into three periods:
The Ibrahimiyah Canal is an irrigation canal in Egypt built in 1873. It was the most important public work executed under the then newly established Ministry of Public Works. It was built during the reign of Ismail Pasha when he was Khedive of Egypt. It was commissioned by Bahgat Pasha, minister of public works, who designed it primarily to provide perennial irrigation to the Khedivial sugar estates in Middle Egypt. It supplied perennial irrigation to 580,000 acres (2,300 km2) and flood irrigation to another 420,000 acres (1,700 km2). The discharge of the canal varied between 30 and 80 cubic metres per second in summer and between 500 and 900 cubic metres per second in flood. Having its head on the left bank of the Nile, in Assiut, it runs northwards for 60 kilometres and then divides in Dairut into two main branches; one branch is the Bahr Yussef Canal, while the other is the Ibrahimiyah Canal proper.
Maraetai Power Station is a hydroelectric power station on the Waikato River, in the North Island of New Zealand. It is the fifth of the eight hydroelectric power stations on the Waikato River, and at 360 MW, is the largest hydroelectric station on the Waikato.
Water resources management in modern Egypt, is a complex process that involves multiple stakeholders who use water for irrigation, municipal and industrial water supply, hydropower generation and navigation. In addition, the waters of the Nile support aquatic ecosystems that are threatened by abstraction and pollution. Egypt also has substantial fossil groundwater resources in the Western Desert.
The Hindiya Barrage is a barrage on the Euphrates south of the town of Musayyib in Babil Governorate of Iraq. Located north of the Al-Hindiya District, it was designed by British civil engineer William Willcocks in response to the silting up of the Hillah branch of the Euphrates. Construction of the dam, with a length of over 250 metres (820 ft), lasted between 1911 and 1913. Between 1984 and 1989, a new dam was built several kilometres upstream as a replacement for the Hindiya Barrage.
Durgapur Barrage is built across the Damodar River at Durgapur in Paschim Bardhaman district and partly in Paschim Bardhaman district, in the Indian state of West Bengal. It was constructed by Damodar Valley Corporation mainly for the purpose of irrigation and also to supply water to Industrial township of Durgapur. The irrigation and canal system was transferred to the Government of West Bengal in 1964.
The Gileppe Dam is an arch-gravity dam on the Gileppe river in Jalhay, Liège province, Wallonia, Belgium. It was built in the 1870s to supply water for the wool industry in nearby Verviers. The monumental structure with its unusually thick profile played an important role in establishing an international standard for masonry gravity dams as a technology for major water supply systems. It was considered one of the strongest dams in Europe at the time, and it was the first dam built in modern Belgium. In the first decade of the 21st century, it was noted as supplying most of the drinking water for Verviers, as well as industrial water, and as producing hydroelectricity.
A barrage is a type of low-head, diversion dam which consists of a number of large gates that can be opened or closed to control the amount of water passing through. This allows the structure to regulate and stabilize river water elevation upstream for use in irrigation and other systems. The gates are set between flanking piers which are responsible for supporting the water load of the pool created. The term barrage is borrowed from the French word "barrer" meaning "to bar".
The Aswan Low Dam or Old Aswan Dam is a gravity masonry buttress dam on the Nile River in Aswan, Egypt. The dam was built at the former first cataract of the Nile, and is located about 1000 km up-river and 690 km south-southeast of Cairo. When initially constructed between 1899 and 1902, nothing of its scale had ever been attempted; on completion, it was the largest masonry dam in the world. The dam was designed to provide storage of annual floodwater and augment dry season flows to support greater irrigation development and population growth in the lower Nile. The dam, originally limited in height by conservation concerns, worked as designed, but provided inadequate storage capacity for planned development and was raised twice, between 1907 and 1912 and again in 1929–1933. These heightenings still did not meet irrigation demands and in 1946 it was nearly over-topped in an effort to maximize pool elevation. This led to the investigation and construction of the Aswan High Dam 6 kilometres (3.7 mi) upstream.
The Grand Ethiopian Renaissance Dam, formerly known as the Millennium Dam and sometimes referred to as the Hidase Dam, is a gravity dam on the Blue Nile River in Ethiopia under construction since 2011. The dam is in the Benishangul-Gumuz Region of Ethiopia, about 45 km (28 mi) east of the border with Sudan.