Chicago Region Environmental and Transportation Efficiency Program

Last updated
CREATE project status as of 2022 CREATE program rail project status.pdf
CREATE project status as of 2022

The Chicago Region Environmental and Transportation Efficiency (CREATE) Program is a $4.6 billion program to improve the efficiency and effectiveness of freight, commuter and intercity passenger rail and to reduce highway delay in the Chicago region. The Program consists of 70 projects, which includes constructing grade separations, flyovers and other rail projects to ease both rail and roadway congestion. The status of each of the 70 projects varies, with many having been completed, others in design or construction and some not yet started. Costs for the projects are covered by public and private funding from the Program's partners: the United States Department of Transportation, the Illinois Department of Transportation, Cook County, the City of Chicago, and public and private railroads (represented by the Association of American Railroads).

Contents

History

The CREATE Program was formally announced on June 16, 2003. It began as a task force convened by the federal Surface Transportation Board in the early 2000s in recognition of the growing urgency of the Chicago region's rail capacity needs. That task force included representatives from the railroad industry, the State of Illinois and the City of Chicago.

Today, the CREATE Program is a unique collaboration whose members include railroads and municipal leaders working together to increase the efficiency of Chicago's unique rail network. Six of the seven Class 1 railroads operating in North America serve Chicago; each of those six is a CREATE partner alongside the State of Illinois, City of Chicago, and Cook County.

The CREATE Program is supported by public and private funding and enjoys widespread support from community, civic and elected leaders. Its work and operations are governed by a Joint Statement of Understandings that the partners developed, approved and regularly affirm. [1]

Purpose

Chicago is considered the railroad hub of North America. The region dominates the U.S. rail market in both market share and total volume, handling 47% of the nation's intermodal rail containers and 28% of rail cars, carrying a total of $641 billion worth of goods each year. [2] Twenty-seven percent of all jobs in Cook County are freight-dependent industries that produce 56% of the county's economic output. [3]

The Chicago region's rail infrastructure was largely configured to serve transportation needs and demands at the time it was originally built more than a century ago. By the 1990s, many decades of modernization and consolidation within the freight and passenger railroad industries had drastically changed the operational demands being placed on this network. Train lengths, routing patterns, capacity needs, rail-highway grade crossing conflicts and control technologies had all evolved over the years, but the region's rail infrastructure had not been sufficiently modernized to accommodate the new demands. This resulted in serious delays, which had cascading effects across the nation's rail network. Oftentimes, shared control of rail facilities within the Chicago region had created institutional challenges to implementing needed modernization. Under direction from the Surface Transportation Board and various elected officials and following several years of cooperative study and analysis by public agencies and private railroads, the CREATE Program was initiated in 2003 to identify, prioritize and address these infrastructure modernization needs. The closely related Chicago Transportation Coordination Office was also established at that time to address rail operations coordination needs in the region. [4]

Because delays in the Chicago region's rail network can have impacts nationwide, the benefits to the CREATE Program also extend nationwide. A 2015 study showed that the economic benefits of full implementation of the CREATE Program are $31.5 billion. [5]

Projects

Project status as of 2022 CREATE Program Status Chart.png
Project status as of 2022

The program currently comprises 70 separate projects. [6] As of February 2023, a total of 33 had been fully completed, four were under construction, nine were in final design and another six were in the preliminary design and environmental review process. The remaining 18 were awaiting identification of funding to enter preliminary design and environmental review. [7]

Major projects

75th Street Corridor Improvement Project

The 75th Street Corridor Improvement Project (75th St. CIP) is the largest project in the CREATE Program. [8] The project is located in the Chicago neighborhoods of Ashburn, Englewood, Auburn Gresham and West Chatham along two passenger and four freight rail lines. It will eliminate the most congested rail chokepoint in the Chicago region, Belt Junction, where 30 Metra and 90 freight trains per day cross each other's paths. It is broken out into four projects:

  • Forest Hill Flyover (CREATE project P3) [9]
    • This project consists of a new CSX north–south rail flyover structure to eliminate conflicts between north–south and east–west train movements at Forest Hill Junction (75th Street and Western Avenue). Final design (Phase II) began in 2019 and is expected to last through 2021. Construction (Phase III) began at the end of 2020 and will continue through 2024.
  • 71st Street Grade Separation (CREATE project GS19) [10]
    • This project consists of a road-rail grade separation of 71st Street and the CSX railroad tracks near Bell Avenue. Final design (Phase II) work began in 2019. Construction (Phase III) began in 2022. [11]
  • Rock Island Connection (CREATE project P2) [12]
    • This project will build a flyover structure to connect the Metra SouthWest Service (SWS) mainline tracks to the Metra Rock Island Line. Final design (Phase II) work began in 2020 and is expected to continue until 2022. CREATE Program partners are seeking construction (Phase III) funding for this project. The improvements will allow Metra to route all SWS trains to the LaSalle Street Station rather than Union Station, which will free up valuable capacity at Union Station for increased service on other passenger and/or commuter rail lines there.
  • 80th Street Junction and Belt Junction Replacements (CREATE project EW2) [13]
    • This project will reconfigure the east–west tracks at Forest Hill Junction (near 75th Street and Western Avenue), add and realign tracks to remove the bottleneck at Belt Junction (near 75th Street and Loomis Avenue), realign track and signal systems between Belt Junction and the Dan Ryan (Interstate 94) Expressway, reconstruct 80th Street Junction (near 80th Street and Wallace Street), relocate Union Pacific tracks to a currently unused Norfolk Southern alignment and add positive train control (PTC) along this stretch of tracks. EW2 also includes a new Metra mainline track and improvements to several existing railroad viaducts over city streets. Final design (Phase II) work began in 2020 and is expected to continue until 2022. CREATE Program partners are seeking construction (Phase III) funding for this project.

Englewood Flyover

The Englewood Flyover (CREATE project P1), completed July 2016, eliminated conflict between 78 Metra Rock Island trains and approximately 60 freight and Amtrak trains that previously crossed at grade through the Englewood interlocking daily. [14] The $140 million project relieved a significant source of delay for Amtrak trains from Michigan and points east, as well as for NS freight trains. By eliminating many of these delays, the project reduced locomotive engine idling, resulting in reduced emissions and improved air quality. P1's completion was needed before two adjacent CREATE projects could progress, as they would add additional trains to the lines at the Englewood Flyover location. Without the Englewood Flyover in place first, implementation of these other projects would have greatly increased delays at the Englewood interlocking.

Funding

The CREATE Program is a public-private partnership currently estimated to cost $4.6 billion to fully implement. Funding commitments come from the Program's partners and include a mix of public and private funds. The Program has received $1.6 billion from a variety of public and private commitments so far. An estimated $3 billion is needed to complete the full Program of projects. From 1998 to 2018, the private railroads invested $6.9 billion in the Chicago Terminal beyond CREATE Program investments. Currently, these railroads invest about $450 million per year in the Chicago Terminal beyond CREATE investments. [15]

Related Research Articles

<span class="mw-page-title-main">Northeast Corridor</span> Electrified railroad line in the Northeastern U.S.

The Northeast Corridor (NEC) is an electrified railroad line in the Northeast megalopolis of the United States. Owned primarily by Amtrak, it runs from Boston in the north to Washington, D.C. in the south with major stops in Providence, New Haven, Bridgeport, Stamford, New York City, Trenton, Philadelphia, Wilmington, and Baltimore. The NEC closely parallels Interstate 95 for most of its length, and is the busiest passenger rail line in the United States both by ridership and by service frequency as of 2013. The NEC carries more than 2,200 trains daily.

<span class="mw-page-title-main">Metra</span> Suburban railroad operator in the Chicago, Illinois metropolitan area, in the US

Metra is the commuter rail system in the Chicago metropolitan area serving the city of Chicago and its surrounding suburbs via the Union Pacific Railroad, BNSF Railway, and other railroads. The system operates 242 stations on 11 rail lines. It is the fourth busiest commuter rail system in the United States by ridership and the largest and busiest commuter rail system outside the New York City metropolitan area. In 2022, the system had a ridership of 23,726,400, or about 116,200 per weekday as of the first quarter of 2023. The estimated busiest day for Metra ridership occurred on November 4, 2016—the day of the Chicago Cubs 2016 World Series victory rally.

<span class="mw-page-title-main">Red Line (CTA)</span> Rapid transit line in Chicago

The Red Line is a rapid transit line in Chicago, run by the Chicago Transit Authority (CTA) as part of the Chicago "L" system. It is the busiest line on the "L" system, with an average of 93,457 passengers boarding each weekday in 2022. The route is 26 miles (42 km) long with a total of 33 stations. It runs elevated from the Howard station in the Rogers Park neighborhood on the North Side, through a subway on the Near North Side, Downtown, and the South Loop, and then through the Dan Ryan Expressway median to 95th/Dan Ryan in the Roseland neighborhood on the South Side.

<i>Lincoln Service</i> Amtrak service between Chicago, IL and St. Louis, MO

The Lincoln Service is a 284-mile (457 km) higher-speed rail service operated by Amtrak that runs between Chicago, Illinois and St. Louis, Missouri. The train is a part of the Illinois Service and is partially funded by the Illinois Department of Transportation. The train uses the same route as the long-distance Texas Eagle, which continues to San Antonio and Los Angeles. A connection with the Kansas City-bound Missouri River Runner is available in St. Louis.

<span class="mw-page-title-main">South Shore Line</span> Rail line in Indiana and Illinois, United States

The South Shore Line is an electrically powered interurban commuter rail line operated by the Northern Indiana Commuter Transportation District (NICTD) between Millennium Station in downtown Chicago and the South Bend International Airport in South Bend, Indiana, United States. The name refers to both the physical line and the service operated over that route. The line was built in 1901–1908 by predecessors of the Chicago South Shore and South Bend Railroad, which continues to operate freight service. Passenger operation was assumed by the NICTD in 1989. The South Shore Line is one of the last surviving interurban trains in the United States. In 2022, the system had a ridership of 1,406,400, or about 4,600 per weekday as of the first quarter of 2023.

<span class="mw-page-title-main">Milwaukee District North Line</span> Commuter rail service in Illinois

The Milwaukee District North Line (MD-N) is a Metra commuter rail line in Chicago, Illinois and its northern suburbs, running from Union Station to Fox Lake. Although Metra does not refer to any of its lines by color, the timetable accents for the Milwaukee District North line are pale "Hiawatha Orange" in honor of the Milwaukee Road's Hiawatha passenger trains.

<span class="mw-page-title-main">SouthWest Service</span> Metra route to Manhattan, Illinois

The SouthWest Service (SWS) is a Metra commuter rail line, running southwest from Union Station in downtown Chicago, Illinois, to Manhattan, Illinois. Metra does not refer to its lines by color, but the timetable accents for the SouthWest Service line are "Banner Blue," for the Wabash Railroad's Banner Blue passenger train. The trackage is owned by Metra north of a junction with the Belt Railway of Chicago at Loomis Boulevard, and is leased from Norfolk Southern Railway south of the junction.

<span class="mw-page-title-main">Rock Island District</span> Commuter rail line between Chicago and Joliet, Illinois

The Rock Island District (RI) is a Metra commuter rail line from Chicago, Illinois, southwest to Joliet. Metra does not refer to its lines by color, but the timetable accents for the Rock Island District line are "Rocket Red" in honor of the Chicago, Rock Island and Pacific Railroad's Rocket passenger trains.

<span class="mw-page-title-main">Metra Electric District</span> Electric commuter rail line in Chicago, Illinois, USA

The Metra Electric District is an electrified commuter rail line owned and operated by Metra which connects Millennium Station, in downtown Chicago, with the city's southern suburbs. As of 2018, it is the fifth busiest of Metra's 11 lines, after the BNSF, UP-NW, UP-N, and UP-W Lines with nearly 7.7 million annual riders. While Metra does not explicitly refer to any of its lines by color, the timetable accents for the Metra Electric District are printed in bright "Panama orange" to reflect the line's origins with the Illinois Central Railroad (IC) and its Panama Limited passenger train. Apart from the spots where its tracks run parallel to other main lines, it is the only Metra line running entirely on dedicated passenger tracks, with no freight trains operating anywhere on the actual route itself. The line is the only one in the Metra system with more than one station in Downtown Chicago, and also has the highest number of stations (49) of any Metra line.

<span class="mw-page-title-main">LaSalle Street Station</span> Train station in Chicago

LaSalle Street Station is a commuter rail terminal at 414 South LaSalle Street in downtown Chicago. First used as a rail terminal in 1852, it was a major intercity rail terminal for the New York Central Railroad until 1968, and for the Chicago, Rock Island and Pacific Railroad until 1978, but now serves only Metra's Rock Island District. The present structure became the fifth station on the site when its predecessor was demolished in 1981 and replaced by the new station and the One Financial Place tower for the Chicago Stock Exchange. The Chicago Board of Trade Building, Willis Tower and Harold Washington Library are nearby.

<span class="mw-page-title-main">St. Charles Air Line</span> Rail corridor in Chicago

The St. Charles Air Line is a rail line in Chicago, Illinois, partially owned by the BNSF Railway, Union Pacific Railroad, and Canadian National Railway.

<span class="mw-page-title-main">High-speed rail in the United States</span> Overview of the high-speed rail system in the United States of America

Plans for high-speed rail in the United States date back to the High-Speed Ground Transportation Act of 1965. Various state and federal proposals have followed. Despite being one of the world's first countries to get high-speed trains, it failed to spread. Definitions of what constitutes high-speed rail vary, including a range of speeds over 110 mph (180 km/h) and dedicated rail lines. Inter-city rail with top speeds between 90 and 125 mph is sometimes referred to in the United States as higher-speed rail.

The Northern Branch Corridor Project is a proposed extension of the Hudson-Bergen Light Rail (HBLR) from its northern terminus into eastern Bergen County, New Jersey, initially proposed in 2001. If built, the new service would use the right-of-way of the Northern Branch on which the Erie Lackawanna Railroad ran passenger service until October 3, 1966, and is currently a lightly used, stub-ended freight rail line owned by CSX Transportation. The Northern Branch Corridor is at the foot of the west side of the Hudson Palisades in the Hackensack River valley, running for much of its length parallel to Overpeck Creek. After mixed reactions and extensive community input to a draft environmental impact statement (EIS), it was decided in 2013 to terminate the line at the Englewood Hospital and Medical Center. In March 2017 the Supplementary Draft Environmental Impact Statement was approved by the Federal Transit Administration allowing for a period of public reaction. A separately-conceived and funded bridge at 69th St. in North Bergen, necessary for operation of the system, has been completed. In 2017 NJ Transit estimated that the line would open in 2029.

<span class="mw-page-title-main">Brighton Park crossing</span>

The Brighton Park crossing is a major railroad crossing in Chicago, Illinois, hosting three major freight railroads. The crossing is northwest of the intersection of Western Avenue and Archer Avenue, in the Brighton Park neighborhood of Chicago, Illinois. The railroads involved in the crossing are CSX, Canadian National and Norfolk Southern. The crossing consists of the CN's two-track Joliet Subdivision in a roughly east–west orientation intersecting five north–south tracks operated by NS and CSX. Collectively, these railroads operate approximately 80 trains per day through the crossing. The junction is visible from the CTA Orange Line trains that pass on an elevated structure immediately southeast of the crossing.

<span class="mw-page-title-main">Joliet Union Station</span> Train station in Joliet, Illinois, U.S.

Joliet Union Station was a train station in Joliet, Illinois that served Amtrak long-distance and Metra commuter trains. It was replaced by the new Joliet Transportation Center in 2018, a train station that was constructed adjacent to the Union Station's location. Train service to Joliet Union Station permanently ceased in September 2014. The station is 37.0 miles (59.5 km) from Chicago Union Station on the Heritage Corridor, and 40.1 miles (64.5 km) from Chicago LaSalle St. Station on the Rock Island District.

<span class="mw-page-title-main">Crescent Corridor</span> Railroad corridor in eastern USA

The Crescent Corridor is a railroad corridor operated by the Norfolk Southern Railway (NS). The project, first proposed in 2007, and scheduled for completion by 2020, spans 13 states from New York to Louisiana. It is a private-public partnership between Norfolk Southern and the various state and federal governments.

<span class="mw-page-title-main">South Coast Rail</span>

South Coast Rail is a project to build a new southern line of the MBTA Commuter Rail system along several abandoned and freight-only rail lines. The line has been planned to restore passenger rail service between Boston and the cities of Taunton, Fall River, and New Bedford, via the towns of Berkley, and Freetown, on the south coast of Massachusetts. It would restore passenger service to some of the southern lines of the former Old Colony Railroad and the New York, New Haven and Hartford Railroad.

<span class="mw-page-title-main">North Bergen Yard</span>

The North Bergen Yard is freight rail yard and intermodal terminal in North Bergen, New Jersey parallel to Tonnelle Avenue between 49th and 69th Streets. Located within the North Jersey Shared Assets Area, the facility is part of CSX Transportation (CSXT) and the origination point of its CSX River Subdivision at the southern end of the Albany Division. On its west side, the New York, Susquehanna and Western Railway (NYSW) runs the length of the yard and operates a bulk transloading operation immediately adjacent to it.

69th Street is a proposed interchange station in North Bergen in Hudson County, New Jersey. It would serve passengers on two lines under consideration by NJ Transit, the Passaic–Bergen–Hudson Transit Project and the Northern Branch Corridor Project, the latter of which is an extension of the Hudson–Bergen Light Rail. The station would located at-grade west the North Bergen Yard and Tonnelle Avenue.

William Walter Hay (1908–1998) was an American civil engineer and professor remembered with the annual American Railway Engineering and Maintenance-of-Way Association (AREMA) Hay Award recognizing outstanding achievements in railway engineering.

References

  1. "History". CREATE Program. Retrieved 2021-07-07.
  2. Annual carloads and value; 2017 Surface Transportation Board confidential waybill sample
  3. "Connecting Cook County Freight Plan". October 2018. p. 5. Archived from the original on 2020-04-23.
  4. Council, Metropolitan Planning. "CREATE: Past, Present, and Future". Metropolitan Planning Council. Archived from the original on 2023-02-02. Retrieved 2021-07-06.
  5. CREATE Economic Benefits Study conducted by Cambridge Systematics, 2015
  6. "CREATE Projects". CREATE Program. Archived from the original on 2021-07-09. Retrieved 2021-07-06.
  7. "CREATE Program Overall Project Status Summary August 2022" (PDF).
  8. "CREATE 75th". www.75thcip.org. Retrieved 2021-07-06.
  9. "Forest Hill Flyover (75th Street Corridor Improvement Project)". CREATE Program. Retrieved 2021-07-06.
  10. "71st Street Grade Separation (75th Street Corridor Improvement Project)". CREATE Program. Archived from the original on 2021-07-09. Retrieved 2021-07-06.
  11. "Rail News - CREATE partners break ground on Forest Hill Flyover, 71st Street grade separation projects. For Railroad Career Professionals". Progressive Railroading. Archived from the original on 2023-01-08. Retrieved 2023-01-08.
  12. "Rock Island Connection (75th Street Corridor Improvement Project)". CREATE Program. Archived from the original on 2021-07-09. Retrieved 2021-07-06.
  13. "80th Street Junction Replacements (75th Street Corridor Improvement Project)". CREATE Program. Archived from the original on 2021-07-09. Retrieved 2021-07-06.
  14. "Englewood Flyover". CREATE Program. Retrieved 2021-07-06.
  15. Chicago Region Environmental and Transportation Efficiency Program Presentation. Slide 40.