Contracts for Difference (CfD) are the main market support mechanism for low carbon electricity generation in the UK. The scheme replaced the Renewables Obligation which closed to new generation in March 2017. It is administered by the Low Carbon Contracts Company (LCCC), which is owned by the UK Government.
The scheme offers a fixed "Strike Price" to generators over a 15-year contract, which provides financial certainty, unlike the wholesale electricity market which can fluctuate significantly. With the contract for difference, if the market price for electricity drops below the Strike Price, LCCC pays the generator the shortfall, however if the market price rises, the generator must pay back the difference. The costs of the scheme are passed onto consumers via their electricity bills. [1]
The contracts are awarded using a reverse auction in annual "Allocation Rounds" (AR) where companies submit sealed bids for a project capacity and cost. Contracts are awarded to the lowest cost projects first, until a predefined budget or capacity cap is reached. The budget is split into different 'Pots' which different technologies can bid into, [2] although these have varied by auction.
Bids cannot be above a maximum "Administrative Strike Price" set before the auction. [3] To make comparison between years easier, all Strike Prices are quoted in 2012 prices, but projects are paid an inflation-adjusted amount linked to the Consumer Price Index (CPI). The projects also set out a delivery year, when the projects is expected to be commissioned, however this may slip for various reasons. [1]
In December 2010, the Government introduced plans to reform the electricity market. [4] The Electricity Market Reform (EMR) introduced both a capacity market to incentivise reliable generation and Contracts for Difference to provide revenue certainty to developers investing in low carbon and renewable energy, but at a lower cost that the Renewables Obligation. [5]
Prior to the first Allocation Round, there was a mechanism called Final Investment Decision Enabling for Renewables. [6] This awarded CfDs to five offshore wind projects, two biomass conversion projects, and one dedicated biomass with combined heat and power, with a total capacity of almost 4.5 GW. [6] [7]
Separately, the Government also awarded a CfD to Hinkley Point C nuclear power station, set at £92.50/MWh for a 35 year period. [8] This is 20 years longer than other CfD contracts. See §Cost to consumers of the Hinkley Point C article for further discussion on the costs.
Results of the first three auctions were announced in February 2015, September 2017, and October 2019. Starting with AR4 in 2022, subsequent auctions have been on an annual basis.
In 2024, the Department for Energy Security and Net Zero (DESNZ) consulted on proposed updates to the CfD starting in AR7. Two main changes to the scheme were published in October. Firstly, Adding support for repowering of onshore wind projects after 25 years of commercial operation. Support for repowering other technologies may be added in future. Secondly, extending the phased approach for fixed offshore wind projects to floating, allowing them to be built in up-to three phases to reduce construction risk. [9] [10]
The Clean Power 2030 Action Plan, published by DESNZ in December 2024, indicated further targeted reforms would be implemented before the AR7 auction, subject to further consultation. This includes reviewing the budgeting parameters for fixed offshore wind, and relaxing the eligibility criteria of requiring full planning permission for fixed offshore wind projects. [11]
In November 2024, the Clean Industry Bonus (CIB) was launched. This provides additional CfD support to offshore wind projects (both fixed and floating) that invest in more sustainable supply chains. However, to be applicable for AR7, offshore wind projects need a CIB. It will have a budget of £27m per GW of capacity in AR7, and the application process will run from 13 to 19 February 2025. The CIB was initially introduced as Sustainable Industry Rewards, but was later renamed. [12] [13]
The first Allocation Round auction started in October 2014, with results announced on 19 February 2015. [14] The maximum prices are given in the first table below. A total of 2.1 GW of contracts were awarded, primarily for two offshore wind projects, the 714 MW East Anglia 1 and the 448 MW Neart Na Gaoithe, plus 15 smaller onshore wind projects. [15]
Pot/Technology | 2014/15 | 2015/16 | 2016/17 | 2017/18 | 2018/19 |
---|---|---|---|---|---|
Pot 1 (established) | |||||
Onshore Wind (>5 MW) | 95 | 95 | 95 | 90 | 90 |
Solar photovoltaic (>5 MW) | 120 | 120 | 115 | 110 | 100 |
Energy from Waste (with CHP) | 80 | 80 | 80 | 80 | 80 |
Hydro (>5 MW and <50 MW) | 100 | 100 | 100 | 100 | 100 |
Landfill gas | 55 | 55 | 55 | 55 | 55 |
Sewage gas | 75 | 75 | 75 | 75 | 75 |
Pot 2 (less established) | |||||
Offshore wind | 155 | 155 | 1560 | 140 | 140 |
Tidal stream | 305 | 305 | 305 | 305 | 305 |
Wave | 305 | 305 | 305 | 305 | 305 |
Advanced Conversion Technologies (with or without CHP) | 155 | 155 | 150 | 140 | 140 |
Anaerobic digestion (with or without CHP) (>5 MW) | 150 | 150 | 150 | 140 | 140 |
Dedicated biomass (with CHP) | 125 | 125 | 125 | 125 | 125 |
Geothermal (with or without CHP) | 145 | 145 | 145 | 140 | 140 |
Pot 3 | |||||
Biomass conversion | 105 | 105 | 105 | 105 | 105 |
Pot/Technology | Capacity (MW) | № of projects | Strike Price (£2012/MWh) | ||||||
---|---|---|---|---|---|---|---|---|---|
2015/16 | 2016/17 | 2017/18 | 2018/19 | 2015/16 | 2016/17 | 2017/18 | 2018/19 | ||
Pot 1 (established) | |||||||||
Onshore Wind (>5 MW) | — | 45 | 77.5 | 626.05 | 15 | — | 79.23 | 79.99 | 82.50 |
Solar photovoltaic (>5 MW) | 32.88 | 38.67 | — | — | 5 | 50.00 | 79.23 | — | — |
Energy from Waste (with CHP) | — | — | — | 94.75 | 2 | — | — | — | 80.00 |
Pot 2 (less established) | |||||||||
Offshore wind | — | — | 714 | 448 | 2 | — | — | 119.89 | 114.39 |
Advanced Conversion Technologies | — | — | 36 | 26 | 3 | — | — | 119.89 | 114.39 |
Total | 32.88 | 83.67 | 827.50 | 1194.80 | 27 | — | — | — | — |
The second round ran from April to September 2017. [16] As announced in the 2016 budget, no funding was allocated in Pot 1 for the more established technologies of onshore wind, solar PV, hydro, energy from waste with CHP, landfill gas, and sewage gas. Instead, a Pot 2 budget of £290m for less established technologies, of which offshore wind was expected to form the majority. [17] Nearly 3.2 GW of contracts were awarded for three offshore wind farms: Triton Knoll (860 MW), Hornsea Project 2 (1386 MW), and Moray Offshore Windfarm (East) (950 MW). Several smaller projects for advanced conversion technologies and dedicated biomass with CHP were also funded. [18]
Pot/Technology | ASP (£2012/MWh) | Capacity (MW) | № of projects | SP (£2012/MWh) | |||
---|---|---|---|---|---|---|---|
2021/22 | 2022/23 | 2021/22 | 2022/23 | 2021/22 | 2022/23 | ||
Pot 2 (less established) | |||||||
Offshore wind | 105 | 100 | 860 | 2336 | 3 | 74.75 | 57.50 |
ACT (standard or advanced; with or without CHP) | 125 | 115 | 56.31 | 8 | 6 | 74.75 | 40.00 |
Anaerobic digestion (with or without CHP; >5MW) | 140 | 135 | — | — | — | — | — |
Dedicated biomass (with CHP) | 115 | 115 | 85.64 | — | 2 | 74.75 | — |
Wave | 310 | 300 | — | — | — | — | — |
Tidal stream | 300 | 295 | — | — | — | — | — |
Total | — | — | 1001.95 | 2344 | 11 | — | — |
The auction process for AR3 took place between May and September 2019, with results announced in October. Of the £265m annual budget, £200m was for offshore wind, £24m for floating offshore wind, and £10m for onshore wind, with the remaining £31m for other less established technologies including (onshore) remote island wind. [20] AR3 delivered record low prices for offshore wind, with contracts to deliver in 2023/24 came in at £39.650/MWh and those delivering in 2024/25 at £41.611/MWh. [21]
Pot/Technology | ASP (£2012/MWh) | Capacity (MW) | № of projects | SP (£2012/MWh) | |||
---|---|---|---|---|---|---|---|
2023/24 | 2024/25 | 2023/24 | 2024/25 | 2023/24 | 2024/25 | ||
Pot 2 (less established) | |||||||
Advanced Conversion Technologies | 113 | 111 | 27.5 | 6.1 | 2 | 39.65 | 41.611 |
Anaerobic digestion (>5 MW) | 122 | 121 | — | — | — | — | — |
Dedicated biomass with CHP | 121 | 121 | — | — | — | — | — |
Geothermal | 129 | 127 | — | — | — | — | — |
Offshore wind | 56 | 53 | 1212 | 2854 | 6 | 39.65 | 41.611 |
Remote island wind (>5 MW) | 82 | 82 | 225.72 | 49.5 | 4 | 39.65 | 41.611 |
Tidal stream | 225 | 217 | — | — | — | — | — |
Wave | 281 | 268 | — | — | — | — | — |
Total | — | — | 2865.22 | 2909.6 | 12 | — | — |
The auction for AR4 took place between December 2021 and July 2022, and re-introduced Pot 1 for established technologies. Of the total £285m budget, a £20m ringfence was set aside for tidal stream projects in Pot 2, [24] and for the first time four contracts totalling just over 40 MW were awarded CfDs, MeyGen, Magallanes Renovables, and two for Orbital Marine Power. [25] The first contract for a floating offshore wind turbine was also awarded, to Hexicon AB for their 32 MW TwinHub project. [26]
Pot/Technology | ASP (£2012/MWh) | Capacity (MW) | № of projects | SP (£2012/MWh) | ||||||
---|---|---|---|---|---|---|---|---|---|---|
All delivery years | 2023/24 | 2024/25 | 2025/26 | 2026/27 | 2023/24 | 2024/25 | 2025/26 | 2026/27 | ||
Pot 1 (established) | ||||||||||
Solar PV (>5 MW) | 47 | 251.38 | 1958.03 | — | — | 66 | 45.99 | 45.99 | — | — |
Onshore Wind (>5 MW) | 53 | — | 887.96 | — | — | 10 | — | 42.47 | — | — |
Energy from waste (with CHP) | 121 | — | 30 | — | — | 1 | — | 45.99 | — | — |
Pot 2 (less established) | ||||||||||
Tidal stream | 211 | — | — | 5.62 | 35.2 | 4 | — | — | 178.54 | 178.54 |
Floating offshore wind | 122 | — | — | — | 32 | 1 | — | — | — | 87.30 |
Remote Island Wind (RIW) | 62 | — | — | — | 597.6 | 6 | — | — | — | 46.39 |
Offshore Wind | 46 | — | — | — | 6994.34 | 5 | — | — | — | 37.35 |
Total | — | 251.38 | 2875.99 | 5.62 | 7659.14 | 93 | — | — | — | — |
The auction for AR5 took place between March and September 2023. The available budget was £170 million for Pot 1 (established technologies) and £35 million for Pot 2 (emerging technologies) including a minimum £10m ringfence for tidal stream. [28] Despite warnings from industry before the auction, there were no bids from offshore wind projects as the Administrative Strike Price was seen to be to low to cover the increases in supply chain and cost of capital. [29]
Pot/Technology | ASP (£2012/MWh) | Capacity (MW) | № of projects | SP (£2012/MWh) | ||
---|---|---|---|---|---|---|
All delivery years | 2025/26 | 2026/27 | 2027/28 | All delivery years | ||
Pot 1 (established) | ||||||
Energy from waste (with CHP) | 116 | — | — | — | — | — |
Hydro (>5MW and <50MW) | 89 | — | — | — | — | — |
Landfill gas | 62 | — | — | — | — | — |
Offshore wind | 44 | — | — | — | — | — |
Onshore wind (>5 MW) | 53 | 31.1 | 204.4 | 1245.24 | 24 | 52.29 |
Remote island wind (>5 MW)) | 53 | — | — | 223.6 | 1 | 52.29 |
Sewage gas | 148 | — | — | — | — | — |
Solar PV (>5 MW) | 47 | 393.96 | 150.74 | 1382.98 | 56 | 47.00 |
Pot 2 (less established) | ||||||
Advanced Conversion Technologies | 182 | — | — | — | — | — |
Anaerobic digestion (>5 MW) | 136 | — | — | — | — | — |
Dedicated biomass with CHP | 162 | — | — | — | — | — |
Floating offshore wind | 116 | — | — | — | — | — |
Geothermal | 119 | — | 7 | 5 | 3 | 119.00 |
Tidal stream | 202 | — | 4.5 | 48.54 | 11 | 198.00 |
Wave | 245 | — | — | — | — | — |
Total | — | 425.06 | 366.64 | 2905.36 | 95 | — |
The auction for AR6 took place between March and September 2024. The budget was initially set at just over £1bn. [32] [33] Following the election, at the end of July, the budget for AR6 was increased by 50% to £1.555bn. [34] [35] The budget was split into three pots by technology: [33]
The Administrative Strike Prices were significantly increased from AR5. The Contracts for Difference Allocation 6 results were announced on 3 September 2024, with 131 projects being awarded contracts. [36] [37]
Pot/Technology | ASP (£2012/MWh) | Capacity (MW) | № of projects | SP (£2012/MWh) | ||
---|---|---|---|---|---|---|
All delivery years | 2026/27 | 2027/28 | 2018/29 | All delivery years | ||
Pot 1 (established) | ||||||
Energy from waste (with CHP) | 181 | — | — | — | — | — |
Hydro (>5MW and <50MW) | 102 | — | — | — | — | — |
Landfill gas | 69 | — | — | — | — | — |
Onshore wind (>5 MW) | 64 | 272.58 | 717.79 | — | 22 | 50.90 |
Remote island wind (>5 MW)) | 64 | — | — | — | — | — |
Sewage gas | 162 | — | — | — | — | — |
Solar PV (>5 MW) | 61 | 1091.54 | 2196.77 | — | 93 | 50.07 |
Pot 2 (less established) | ||||||
Advanced Conversion Technologies | 210 | — | — | — | — | — |
Anaerobic digestion (>5 MW) | 144 | — | — | — | — | — |
Dedicated biomass with CHP | 179 | — | — | — | — | — |
Floating offshore wind | 176 | — | — | 400 | 1 | 139.93 |
Geothermal | 157 | — | — | — | — | — |
Tidal stream | 261 | — | 10 | 18 | 6 | 172.00 |
Wave | 257 | — | — | — | — | — |
Pot 3 (offshore wind) | ||||||
Offshore wind | 73 | — | — | 3363.07 | 2 | 58.87 |
Offshore wind permitted reduction* | n/a | — | 1578.51 | — | 7 | 54.23 |
Total | — | 1364.12 | 4503.07 | 3781.07 | 131 | — |
* offshore wind permitted reduction refers to projects that had a previously secured CfD, but have now been awarded a CfD at a higher price. The original contract allowed for up to 25% of the capacity to be withdrawn. [37]
The seventh Allocation Round auction is expected to happen in 2025. Prior to this, the Clean Industry Bonus applications will take place in February 2025.
Round | Nuclear | Solar PV | Onshore wind | Remote island wind | Offshore wind | Floating offshore wind | Tidal Stream | Biomass conversion | Dedicated biomass with CHP | Energy from waste with CHP | Advanced Conversion Technology | Geothermal | Total |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Pre-AR1 | 3277 | — | — | n/a | 3101 | — | — | 1052 | 299 | — | — | — | 7729 |
AR1 | n/a | 72 | 749 | n/a | 1162 | — | — | n/a | — | 95 | 62 | — | 2140 |
AR2 | n/a | n/a | n/a | n/a | 3196 | — | — | n/a | 86 | — | 64 | — | 3346 |
AR3 | n/a | — | — | 275 | 5466 | — | — | n/a | — | — | 34 | — | 5775 |
AR4 | n/a | 2209 | 888 | 598 | 6994 | 32 | 41 | n/a | — | 30 | — | — | 10792 |
AR5 | n/a | 1928 | 1481 | 224 | — | — | 53 | n/a | — | — | — | 12 | 3698 |
AR6 | n/a | 3288 | 990 | — | 3363 | 400 | 28 | — | — | — | — | — | 9648 |
Total | 3277 | 7497 | 4108 | 1096 | 23282 | 432 | 122 | 1052 | 385 | 125 | 160 | 12 | 43127 |
The Renewables Obligation (RO) is a market support mechanism designed to encourage generation of electricity from eligible renewable sources in the United Kingdom. There are three related schemes for the three legal jurisdictions of the UK. In April 2002 the Renewables Obligation was introduced in England and Wales, and in Scotland as the Renewables Obligation (Scotland). The RO was later introduced in Northern Ireland in April 2005. In all cases, the RO replaced the Non-Fossil Fuel Obligation which operated from 1990.
Iberdrola, S.A. is a Spanish multinational electric utility company based in Bilbao, Spain. It has around 40,000 employees and serves around 30 million customers.
The United Kingdom is the best location for wind power in Europe and one of the best in the world. The combination of long coastline, shallow water and strong winds make offshore wind unusually effective.
Denmark was a pioneer in developing commercial wind power during the 1970s, and today a substantial share of the wind turbines around the world are produced by Danish manufacturers such as Vestas—the world's largest wind-turbine manufacturer—along with many component suppliers. Furthermore, Denmark has—as of 2022—the 2nd highest amount in the world of wind power generation capacity installed per capita, behind only neighboring Sweden.
As of 2023, Estonia has a wind power installed capacity of about 376 MW. All operational wind farms in the country are on land. Offshore wind farms are planned on Lake Peipus and in the Baltic Sea near the island of Hiiumaa.
Wind power has a history in Canada dating back many decades, particularly on prairie farms. As of December 2021, wind power generating capacity was approximately 14,304 megawatts (MW). Combined with 2,399 MW of solar power generating capacity, this provided about 6.5% of Canada's electricity demand as of 2020. The Canadian Wind Energy Association (CanWEA) has outlined a future strategy for wind energy that would reach a capacity of 55 GW by 2025, meeting 20% of the country's energy needs.
Wind power generation capacity in India has significantly increased in recent years. As of 30 September 2024, the total installed wind power capacity was 47.36 gigawatts (GW). India has the fourth largest installed wind power capacity in the world. Wind power capacity is mainly spread across the southern, western, and northwestern states. The onshore wind power potential of India was assessed at 132 GW with minimum 32% CUF at 120 m above the local ground level (agl). Whereas, the estimated potential at minimum 25% CUF is 695 GW at 120 agl.
Wind power is the fastest-growing renewable energy technology in Scotland, with 16,648 megawatts (MW) of installed wind power capacity by Q2 2024. This included 9,756 MW from onshore wind in Scotland and 2,971 MW of offshore wind generators. The largest onshore wind farm in the UK is Whitelee, just south of Glasgow, with 215 turbines and a total capacity of 539 MW.
Renewable energy in the United Kingdom contributes to production for electricity, heat, and transport.
In 2021 France reached a total of 18,676 megawatts (MW) installed wind power capacity placing France at that time as the world's seventh largest wind power nation by installed capacity, behind the United Kingdom and Brazil and ahead of Canada and Italy. According to the IEA the yearly wind production was 20.2 TWh in 2015, representing almost 23% of the 88.4 TWh from renewable sources in France during that year. Wind provided 4.3% of the country's electricity demand in 2015.
Dogger Bank Wind Farm is a group of offshore wind farms under construction 130 to 200 kilometres off the east coast of Yorkshire, England in the North Sea. It is considered to be the world's largest offshore windfarm. It was developed by the Forewind consortium, with three phases envisioned - first phase, second phase and third phase. In 2015, the third phase was abandoned, while the first and second phases were granted consent. It was initially expected that the Dogger Bank development will consist of four offshore wind farms, each with a capacity of up to 1.2 GW, creating a combined capacity of 4.8 GW. As of 2024, a total of 8.1 GW generating capacity is expected to be installed on Dogger Bank.
The East Anglia Array is a proposed series of offshore wind farms located around 30 miles off the east coast of East Anglia, in the North Sea, England. It has begun with the currently operational East Anglia ONE, that has been developed in partnership by ScottishPower Renewables and Vattenfall. Up to six individual projects could be set up in the area with a maximum capacity of up to 7.2 GW. The first project, East Anglia ONE at 714 MW, received planning consent in June 2014 and contracts in April 2016. Offshore construction began in 2018 and the project was commissioned in July 2020. It is expected to cost £2.5 billion.
Hornsea Wind Farm is a Round 3 wind farm which began construction in 2018. Sited in the North Sea 120 km off the east coast of England, the eventual wind farm group is planned to have a total capacity of up to 6 gigawatt (GW).
MeyGen is a tidal stream energy plant in the north of Scotland. The project is located in the Pentland Firth, specifically the Inner Sound between the Island of Stroma and the Scottish mainland.
Orbital Marine Power is a Scottish renewable energy company focused on the development and global deployment of floating tidal stream turbine technology. The company was founded in 2002, and as of 2024 has build and tested three different turbines.
The United Kingdom became the world leader of offshore wind power generation in October 2008 when it overtook Denmark.
Morlais is a grid connected tidal stream energy project located in the Irish Sea just off the west coast of Holy Island, Anglesey, Wales. It is being developed by the social enterprise agency Menter Môn. The site has the potential for up to 240 MW of renewable energy to be harnessed from the tides, using a mixture of seabed mounted and floating tidal energy devices from different companies.
Magallanes Renovables, S.L. is a Spanish developer of floating tidal stream energy devices, set up in 2009. The company's head office is in Redondela, Galicia, with a UK subsidiary Magallanes Tidal Energy Ltd. based in Kirkwall.
Tidal power contributes a very small proportion of the electricity generation in the United Kingdom, but it could provide a meaningful amount of predictable renewable energy in future.