Cost contingency

Last updated

When estimating the cost for a project, product or other item or investment, there is always uncertainty as to the precise content of all items in the estimate, how work will be performed, what work conditions will be like when the project is executed and so on. These uncertainties are risks to the project. Some refer to these risks as "known-unknowns" because the estimator is aware of them, and based on past experience, can even estimate their probable costs. The estimated costs of the known-unknowns is referred to by cost estimators as cost contingency.

Contents

Contingency "refers to costs that will probably occur based on past experience, but with some uncertainty regarding the amount. The term is not used as a catchall to cover ignorance. It is poor engineering and poor philosophy to make second-rate estimates and then try to satisfy them by using a large contingency account. The contingency allowance is designed to cover items of cost which are not known exactly at the time of the estimate but which will occur on a statistical basis." [1]

The cost contingency which is included in a cost estimate, bid, or budget may be classified as to its general purpose, that is what it is intended to provide for. For a class 1 construction cost estimate, usually needed for a bid estimate, the contingency may be classified as an estimating and contracting contingency. This is intended to provide compensation for "estimating accuracy based on quantities assumed or measured, unanticipated market conditions, scheduling delays and acceleration issues, lack of bidding competition, subcontractor defaults, and interfacing omissions between various work categories." [2] Additional classifications of contingency may be included at various stages of a project's life, including design contingency, or design definition contingency, or design growth contingency, and change order contingency (although these may be more properly called allowances).

AACE International has defined contingency as "An amount added to an estimate to allow for items, conditions, or events for which the state, occurrence, or effect is uncertain and that experience shows will likely result, in aggregate, in additional costs. Typically estimated using statistical analysis or judgment based on past asset or project experience. Contingency usually excludes:

  1. Major scope changes such as changes in end product specification, capacities, building sizes, and location of the asset or project
  2. Extraordinary events such as major strikes and natural disasters
  3. Management reserves
  4. Escalation and currency effects

Some of the items, conditions, or events for which the state, occurrence, and/or effect is uncertain include, but are not limited to, planning and estimating errors and omissions, minor price fluctuations (other than general escalation), design developments and changes within the scope, and variations in market and environmental conditions. Contingency is generally included in most estimates, and is expected to be expended". [3]

A key phrase above is that it is "expected to be expended". In other words, it is an item in an estimate like any other, and should be estimated and included in every estimate and every budget. Because management often thinks contingency money is "fat" that is not needed if a project team does its job well, it is a controversial topic.

In general, there are four classes of methods used to estimate contingency. ." [4] These include the following:

  1. Expert judgment
  2. Predetermined guidelines (with varying degrees of judgment and empiricism used)
  3. Simulation analysis (primarily risk analysis judgment incorporated in a simulation such as Monte-Carlo)
  4. Parametric Modeling (empirically-based algorithm, usually derived through regression analysis, with varying degrees of judgment used).

While all are valid methods, the method chosen should be consistent with the first principles of risk management in that the method must start with risk identification, and only then are the probable cost of those risks quantified. In best practice, the quantification will be probabilistic in nature (Monte-Carlo is a common method used for quantification).

Typically, the method results in a distribution of possible cost outcomes for the project, product, or other investment. From this distribution, a cost value can be selected that has the desired probability of having a cost underrun or cost overrun. Usually a value is selected with equal chance of over or underrunning. The difference between the cost estimate without contingency, and the selected cost from the distribution is contingency. For more information, AACE International has catalogued many professional papers on this complex topic. [5]

Contingency is included in budgets as a control account. As risks occur on a project, and money is needed to pay for them, the contingency can be transferred to the appropriate accounts that need it. The transfer and its reason is recorded. In risk management, risks are continually reassessed during the course of a project, as are the needs for cost contingency.

See also

Related Research Articles

Risk management Set of measures for the systematic identification, analysis, assessment, monitoring and control of risks

Risk management is the identification, evaluation, and prioritization of risks followed by coordinated and economical application of resources to minimize, monitor, and control the probability or impact of unfortunate events or to maximize the realization of opportunities.

Real options valuation, also often termed real options analysis, applies option valuation techniques to capital budgeting decisions. A real option itself, is the right—but not the obligation—to undertake certain business initiatives, such as deferring, abandoning, expanding, staging, or contracting a capital investment project. For example, the opportunity to invest in the expansion of a firm's factory, or alternatively to sell the factory, is a real call or put option, respectively.

Cost–benefit analysis (CBA), sometimes called benefit costs analysis (BCA), is a systematic approach to estimating the strengths and weaknesses of alternatives used to determine options which provide the best approach to achieving benefits while preserving savings. A CBA may be used to compare completed or potential courses of actions, or to estimate the value against the cost of a decision, project, or policy. It is commonly used in commercial transactions, business or policy decisions, and project investments.

Monte Carlo methods are used in corporate finance and mathematical finance to value and analyze (complex) instruments, portfolios and investments by simulating the various sources of uncertainty affecting their value, and then determining the distribution of their value over the range of resultant outcomes. This is usually done by help of stochastic asset models. The advantage of Monte Carlo methods over other techniques increases as the dimensions of the problem increase.

A feasibility study is an assessment of the practicality of a proposed project or system. A feasibility study aims to objectively and rationally uncover the strengths and weaknesses of an existing business or proposed venture, opportunities and threats present in the natural environment, the resources required to carry through, and ultimately the prospects for success. In its simplest terms, the two criteria to judge feasibility are cost required and value to be attained.

Cost escalation can be defined as changes in the cost or price of specific goods or services in a given economy over a period. This is similar to the concepts of inflation and deflation except that escalation is specific to an item or class of items, it is often not primarily driven by changes in the money supply, and it tends to be less sustained. While escalation includes general inflation related to the money supply, it is also driven by changes in technology, practices, and particularly supply-demand imbalances that are specific to a good or service in a given economy. For example, while general inflation in the US was less than 5% in the 2003-2007 time period, steel prices increased (escalated) by over 50% because of supply-demand imbalance. Cost escalation may contribute to a project cost overrun but it is not synonymous with it.

A cost estimate is the approximation of the cost of a program, project, or operation. The cost estimate is the product of the cost estimating process. The cost estimate has a single total value and may have identifiable component values.

AACE International was founded in 1956 by 59 cost estimators and cost engineers during the organizational meeting of the American Association of Cost Engineering at the University of New Hampshire in Durham, New Hampshire. AACE International Headquarters is located in Morgantown, West Virginia, USA. AACE is a 501(c)(3) non-profit professional association. AACE International is a member of the Board of the Council of Engineering and Scientific Specialty Boards (CESB).

Event chain methodology

Event chain methodology is a network analysis technique that is focused on identifying and managing events and relationship between them that affect project schedules. It is an uncertainty modeling schedule technique. Event chain methodology is an extension of quantitative project risk analysis with Monte Carlo simulations. It is the next advance beyond critical path method and critical chain project management. Event chain methodology helps to mitigate the effect of motivational and cognitive biases in estimating and scheduling. It improves accuracy of risk assessment and helps to generate more realistic risk adjusted project schedules.

In project management, the Cone of Uncertainty describes the evolution of the amount of best case uncertainty during a project. At the beginning of a project, comparatively little is known about the product or work results, and so estimates are subject to large uncertainty. As more research and development is done, more information is learned about the project, and the uncertainty then tends to decrease, reaching 0% when all residual risk has been terminated or transferred. This usually happens by the end of the project i.e. by transferring the responsibilities to a separate maintenance group.

A building estimator or cost estimator is an individual that quantifies the materials, labor, and equipment needed to complete a construction project. Building cost estimating can concern diverse forms of construction from residential properties to hi-rise and civil works. Both estimators and quantity surveyors must have a background education in the construction industry. Representative professional bodies which regulate property professionals:

Applied information economics (AIE) is a decision analysis method developed by Douglas W. Hubbard and partially described in his book How to Measure Anything: Finding the Value of Intangibles in Business. AIE is a method for the practical application of several proven methods from decision theory and risk analysis including the use of Monte Carlo methods. However, unlike some other modeling approaches with simulations, AIE incorporates the following:

  1. Calibrated probability assessment. This is a method for training estimators and experts to be neutrally confident about their assigned probabilities. That is, their probabilities are neither overconfident nor underconfident.
  2. Computing the value of additional information. AIE uses information value calculations from decision theory such as the expected value of perfect information and the value of imperfect (partial) information. Often, this is done for a large number of uncertain variables in some type of decision model or business case. The result will reveal where efforts to reduce uncertainty by making further measurements are best spent.
  3. Empirical methods applied according to the information value of the measurement. This step is, in fact, the reason for the name of the method. Most Monte Carlo modeling experts stop modeling after the first (uncalibrated) probability estimates from experts and there is usually little emphasis on further measurements with empirical methods. Since AIE computes the value of additional information, measurement can be selective and focused. This step often results in a very different set of measurement priorities than would otherwise have been used.
  4. Various optimization methods including modern portfolio theory. MPT and other methods are applied to determine ideal risk and return positions for a set of alternatives.

Cost engineering is "the engineering practice devoted to the management of project cost, involving such activities as estimating, cost control, cost forecasting, investment appraisal and risk analysis." "Cost Engineers budget, plan and monitor investment projects. They seek the optimum balance between cost, quality and time requirements."

Total cost management (TCM) is the name given by AACE International to a process for applying the skills and knowledge of cost engineering. It is also the first integrated process or methodology for portfolio, program and project management. AACE first introduced the concept in the 1990s and published the full presentation of the process in the "Total Cost Management Framework" in 2006.

Reference class forecasting or comparison class forecasting is a method of predicting the future by looking at similar past situations and their outcomes. The theories behind reference class forecasting were developed by Daniel Kahneman and Amos Tversky. The theoretical work helped Kahneman win the Nobel Prize in Economics.

Construction cost estimating software is computer software designed for contractors to estimate construction costs for a specific project. A cost estimator will typically use estimating software to estimate their bid price for a project, which will ultimately become part of a resulting construction contract. Some architects, engineers, construction managers, and others may also use cost estimating software to prepare cost estimates for purposes other than bidding.

Project management triangle

The Project Management Triangle is a model of the constraints of project management. While its origins are unclear, it has been used since at least the 1950s. It contends that:

  1. The quality of work is constrained by the project's budget, deadlines and scope (features).
  2. The project manager can trade between constraints.
  3. Changes in one constraint necessitate changes in others to compensate or quality will suffer.

Probability bounds analysis (PBA) is a collection of methods of uncertainty propagation for making qualitative and quantitative calculations in the face of uncertainties of various kinds. It is used to project partial information about random variables and other quantities through mathematical expressions. For instance, it computes sure bounds on the distribution of a sum, product, or more complex function, given only sure bounds on the distributions of the inputs. Such bounds are called probability boxes, and constrain cumulative probability distributions.

The following is a glossary of terms relating to construction cost estimating.

References

  1. Frederic C. Jelen, James H. Black, Cost and Optimization Engineering, Third Edition, McGraw-Hill Book Company, 1983, pg 456-457
  2. Standard Estimating Practice Sixth Edition, American Society of Professional Estimators, Bni Publications, Inc, 2004, ISBN   1557014817, Pg 103
  3. "Cost Engineering Terminology", Recommended Practice 10S-90, AACE International, WV, rev. 2007
  4. Hollmann, John K., "The Monte-Carlo Challenge: A Better Approach", 2007 AACE International Transactions, AACE International, Morgantown, WV, 2007.
  5. Uppal, Kul (editor), Professional Practice Guide (PPG)#8, "Contingency", 2nd Edition, AACE International, Morgantown WV, 2007.
  6. Rameezdeen, R.; Palliyaguru, R.S; Amaratunga, D. "Financing Contractors in Developing Countries: Impact of Mobilization Advance Payment" (PDF). www.irbnet.de. Retrieved December 5, 2019.
  7. "Item 01699.1010 M – Site Mobilization" (PDF). www.dot.ny.gov. Retrieved December 5, 2019.