A cost estimate is the approximation of the cost of a program, project, or operation. The cost estimate is the product of the cost estimating process. The cost estimate has a single total value and may have identifiable component values.
A problem with a cost overrun can be avoided with a credible, reliable, and accurate cost estimate. A cost estimator is the professional who prepares cost estimates.
There are different types of cost estimators, whose title may be preceded by a modifier, such as building estimator, or electrical estimator, or chief estimator.
Other professionals such as quantity surveyors and cost engineers may also prepare cost estimates or contribute to cost estimates. In the US, according to the Bureau of Labor Statistics, there were 185,400 cost estimators in 2010. [1] There are around 75,000 professional quantity surveyors working in the UK.
The U.S. Government Accountability Office (GAO) defines a cost estimate as "the summation of individual cost elements, using established methods and valid data, to estimate the future costs of a program, based on what is known today". The GAO reports that "realistic cost estimating was imperative when making wise decisions in acquiring new systems." [2] A cost estimate is often needed to support evaluations of project feasibility or funding requirements in support of planning. A cost estimate is often used to establish a budget as the cost constraint for a project or operation.
In project management, project cost management is a major functional division. Cost estimating is one of three activities performed in project cost management. [3]
In cost engineering, cost estimation is a basic activity. A cost engineering reference book has chapters on capital investment cost estimation and operating cost estimation. The fixed capital investment provides the physical facilities. The working capital investment is a revolving fund to keep the facilities operating. [4]
In system, product, or facility acquisition planning, a cost estimate is used to evaluate the required funding and to compare with bids or tenders.
In construction contracting, a cost estimate is usually prepared to submit a bid or tender to compete for a contract award.
In facility maintenance and operation, cost estimates are used to establish funding or budgets.
In an attempt to manage liability risk, some firms avoid the use of the word estimate and instead refer to the estimate as an "Opinion of Probable Cost." [5]
Various projects and operations have distinct types of cost estimating, which vary in their composition and preparation methods. Some of the major areas include:
Common cost estimate classifications historically used are
These correspond to modern published classes 5, 3, and 1, respectively. The U.S. Department of Energy and many others use a system of five classes of estimates:
Estimate class | Name | Purpose | Project definition level |
---|---|---|---|
Class 5 | Order of magnitude | Screening or feasibility | 0% to 2% |
Class 4 | Intermediate | Concept study or feasibility | 1% to 15% |
Class 3 | Preliminary | Budget, authorization, or control | 10% to 40% |
Class 2 | Substantive | Control or bid/tender | 30% to 70% |
Class 1 | Definitive | Check estimate or bid/tender | 50% to 100% |
Methods used to prepare the estimates range from stochastic or judgment at early definition to deterministic at later definition. Some estimates use mixed methods. [6]
Cost estimate classifications have been published by ASTM [7] and AACE International. [8] The American Society of Professional Estimators (ASPE) defines estimate levels in the reverse order as Level 1 – Order (Range) of Magnitude, Level 2 – Schematic/Conceptual Design, Level 3- Design Development, Level 4 – Construction Document, and Level 5 – Bid.>.” [9] ACostE defines a Class I Estimate as definitive, a Class II Estimate as semi-detailed, and a Class III Estimate as pre-budget. [10]
Other names for estimates of different classes include:
Class 1 | Class 3 | Class 5 |
---|---|---|
Detailed estimate | Semi-detailed estimate | Conceptual estimate |
Final estimate | Scope estimate | Pre-design estimate |
Control estimate | Sanction estimate | Preliminary estimate |
As-bid estimate | Pre-budget estimate | |
As-sold estimate | Evaluation estimate | |
CD estimate | DD estimate | SD estimate |
Parametric estimate | ||
Rough order-of-magnitude (ROM) estimate | ||
Very rough order-of-magnitude (VROM) estimate | ||
SWAG (scientific, wild-ass guess) estimate | ||
PIDOOMA (pulled-it-directly out-of-my-[thin Air]) estimate |
This article contains too many or overly lengthy quotations .(December 2015) |
Estimate quality refers to the delineation of quality requirements for the estimate. These requirements are set out in accordance with official quality assurance standards. There may also be other expectations for the estimate which are not specific requirements, but may affect the perceived quality of the estimate. Published quality requirements generally have to do with credibility, accuracy, confidence level, precision, risk, reliability, and validity of the estimate, as well as thoroughness, uniformity, consistency, verification, and documentation. [11] [12] [13] [14] [9]
“The result of bidding without good estimates is certain: jobs that end up with less profit, no profit, or a loss. The bidder ultimately will go out of business; the only question is how long will it take.” [15]
Since a cost estimate is the approximation of the cost of a project or operation, then estimate accuracy is a measure of how closely the estimate is able to predict the actual expenditures for the project or operation. This can only be known after the project is completed. If, for example, a project estimate was $1,252,000 for a specific scope and conditions, and at completion the records showed that $1,172,451.26 was expended, the estimate was 6.8% too high. If the project ended up having a different scope or conditions, an unadjusted computation does not fairly assess the estimate accuracy. Predictions of the estimate accuracy may accompany the estimate. Typically this is expressed as a range higher or lower as compared with the point estimate with an expected probability that the actual cost will fall in the range. [16] An example for a definitive estimate might be that the estimate has a -5/+10% range of accuracy with a 90% confidence that the final value will fall in that range. The accuracy of an early estimate relates to the estimate quality. Factors affecting the quality of the estimate include the people who prepared the estimate, how the estimate was prepared, and what was known about the project. [13] For the same project, the range of uncertainty about the total estimate decreases over time, as illustrated in the cone of uncertainty diagram.
High-quality cost estimates can be produced by following a rigor of 12 steps [17] outlined by the U.S. GAO. Detailed documentation is recommended to accompany the estimate. “The documentation addresses the purpose of the estimate, the program background and system description, its schedule, the scope of the estimate (in terms of time and what is and is not included), the ground rules and assumptions, all data sources, estimating methodology and rationale, the results of the risk analysis, and a conclusion about whether the cost estimate is reasonable. Therefore, a good cost estimate—while taking the form of a single number—is supported by detailed documentation that describes how it was derived and how the expected funding will be spent in order to achieve a given objective.” [18] This documentation is often titled Basis of Estimate (or BOE). Additional documentation may accompany the estimate, including quantity takeoff documentation and supporting calculations, quotes, etc.
Although the pursuit of cost estimate accuracy should always be encouraged, a study in 2002 found that the estimates used to determine whether important infrastructure should be built were "highly and systematically misleading." [19]
A contingency may be included in an estimate to provide for unknown costs which are indicated as likely to occur by experience, but are not identifiable. When using an estimate which has no contingency to set a budget or to set aside funding, a contingency is often added to increase the probability that the budget or funding will be adequate to complete the project. The estimate or budget contingency is not intended to compensate for poor estimate quality, and is not intended to fund design growth, owner changes, or anything else unrelated to delivering the scope as defined in the estimate documentation. Generally, more contingency is needed for earlier estimates due to the higher uncertainty of estimate accuracy.
Estimating methods may vary by type and class of estimate. The method used for most definitive estimates is to fully define and understand the scope, take off or quantify the scope, and apply costing to the scope, which can then be summed to a total cost. Proper documentation and review are also important. Pricing transforms the cost estimate into what the firm wishes to charge for the scope. Early estimates may employ various means of cost modeling. The basic characteristics of effective estimating include: clear identification of task, broad participation in preparing estimates, availability of valid data, standardized structure for the estimate, provision for program uncertainties, recognition of inflation, recognition of excluded costs, independent review of estimates, and revision of estimates for significant program changes. [20] Application of best practices helps ensure a high-quality estimate. “Certain best practices should be followed if accurate and credible cost estimates are to be developed. These best practices represent an overall process of established, repeatable methods that result in high-quality cost estimates that are comprehensive and accurate and that can be easily and clearly traced, replicated, and updated.” [21]
Tools that may be part of costs estimation are cost indexes. These factors promote time adjustment of capital costs, following changes in technology, availability of materials and labor, and inflation. [22] Due to the inherent unavailability of up-to-date Chemical Process Engineering cost literature, several inflation or cost indexes are available. [23]
Estimates for the cost of facility construction are a major part of the cost estimate domain. A construction general contractor or subcontractor must normally prepare definitive cost estimates to prepare bids in the construction bidding process to compete for award of the contract. Although many estimators participate in the bidding and procurement processes, those are not a necessary function of cost estimate preparation. Earlier estimates are prepared by differing methods by estimators and others to support the planning process and to compare with bids. One way to make those estimates is by determining the resources needed (e.g., the amount of construction material quantities that are required) and then multiplying the estimated construction material quantities by the corresponding unit cost. One advantage of making estimates in this way is that it allows for the segregation of quantities and costs. This way they can be updated separately as new information becomes available. They can also be tracked separately allowing decision makers to make better decisions about the project during its conceptual phase. [24]
A definitive estimate is prepared from fully designed plans and specifications (or nearly so), preferably what are called contract documents (CD). The contract documents also establish the Scope of Work (SOW). The standard method is to review and understand the design package and take off (or perform a quantity survey of) the project scope by itemizing it into line items with measured quantities. RSMeans refers to this as, "Scope out the project," and, "Quantify." [25] Some jurisdictions or areas of practice define the itemization and measuring in certain terms, such as RICS and may have specific rules for development of a bill of quantities. The ASPE proposes a best practice standard method for the quantity survey. This includes using the Construction Specifications Institute Uniform Numbering System (MasterFormat) to ensure that all work is accounted for. [26]
Then costs are applied to the quantified line items. This may be called costing or pricing. In estimating for contracting, the cost is what something costs you to build, and price is what you charge another party for building it. RSMeans refers to this as, "Price the quantities." [25] ASPE recommends the "quantity times material and labor costs format" [27] for the compilation of the estimate. This format is illustrated in the handwritten spreadsheet sample. For labor, the estimator should, "Determine basic production rates and multiply them by the units of work to determine total hours for the work." [28] and then multiply the hours by the per hour average labor cost. [29] Labor burdens, material costs, construction equipment costs, and, if applicable, subcontractor costs are also extended on the estimate detail form. [30] Other costs and pricing are added, such as overhead, profit, sales or use taxes, payment and performance bonds, escalation, and contingency. [31]
The costs which are applied to the line-item quantities may come from a cost book (either internal or external) or cost database. For construction contractors or construction managers it is important to track and compile past data of trends, completed projects, production factors, equipment changes, and various labor markets. [32]
The labor requirements are often the most variable and are a primary focus of construction cost estimators. The labor hours required to construct each installation item are calculated by using a man-hour rate times the take-off quantity (a similar method is to divide the take-off quantity by the production rate). Many estimators use a man-hour norm reference for standard man-hours and apply an adjustment factor for project or task conditions, location, methods, equipment, labor skill, etc. to adjust for the anticipated effect on labor.
Direct costs are itemized for all necessary parts of the project. Direct costs are all of the costs which can be attributed directly to the project. Direct costs include costs for general requirements (Division 1 of MasterFormat), which includes such items as project management and coordination, quality control, temporary facilities and controls, cleaning and waste management. [33] Direct costs may also include the costs of project planning, investigation, studies, and design; land or right of way acquisition, and other non-construction costs. Usually, a subtotal of total direct costs is provided in the estimate.
Provisions are made for Indirect costs in addition to the direct costs. Indirect costs include overhead, profit, sales or use taxes, payment and performance bonds, escalation, and contingency. Profit is cost to the buyer, but is not a cost to the provider, rather a projection of anticipated income.
A well documented cost estimate includes a Basis of Estimate (BOE), which describes the scope basis, pricing basis, methods, assumptions, inclusions, and exclusions.
An order-of-magnitude estimate is prepared when little or no design information is available for the project. It is called order of magnitude because that may be all that can be determined at an early stage. In other words, perhaps we can only determine that it is of a 10,000,000 magnitude as opposed to a 1,000,000 magnitude. Various techniques are employed for these estimates, including experience and judgment, historical values and charts, rules of thumb, and simple mathematical calculations. [34] Factor estimating is one of the more popular methods. This involves taking the known cost of a similar facility and factoring the cost for size, [35] place, and time. Cost modeling is another common technique. In cost modeling the estimator models the various parameters of the facility and applies costs to the derived scope.
Building estimators or architects may use the Uniformat system of breaking down the building into functional systems or assemblies during the schematic design (SD) phase of planning and design. [36] The RSMeans Square Foot Costs book organizes building costs according to the 7 divisions of the UNIFORMAT II classification system. [37] The 7 divisions are:
Federal Acquisition Regulation 48 CFR § 36.203 requires the preparation of an independent government cost estimate (IGCE) for construction projects. [38]
Project management is the process of supervising the work of a team to achieve all project goals within the given constraints. This information is usually described in project documentation, created at the beginning of the development process. The primary constraints are scope, time and budget. The secondary challenge is to optimize the allocation of necessary inputs and apply them to meet pre-defined objectives.
In project management, a schedule is a listing of a project's milestones, activities, and deliverables. Usually dependencies and resources are defined for each task, then start and finish dates are estimated from the resource allocation, budget, task duration, and scheduled events. A schedule is commonly used in the project planning and project portfolio management parts of project management. Elements on a schedule may be closely related to the work breakdown structure (WBS) terminal elements, the Statement of work, or a Contract Data Requirements List.
Construction management (CM) aims to control the quality of a project's scope, time, and cost to maximize the project owner's satisfaction. It uses project management techniques and software to oversee the planning, design, construction and closeout of a construction project safely, on time, on budget and within specifications.
A bill of quantities is a document used in tendering in the construction industry in which materials, parts, and labor are itemized. It also (ideally) details the terms and conditions of the construction or repair contract and itemizes all work to enable a contractor to price the work for which he or she is bidding. The quantities may be measured in number, area, volume, weight or time. Preparing a bill of quantities requires that the design is complete and a specification has been prepared.
Indirect costs are costs that are not directly accountable to a cost object. Like direct costs, indirect costs may be either fixed or variable. Indirect costs include administration, personnel and security costs. These are those costs which are not directly related to production. Some indirect costs may be overhead, but other overhead costs can be directly attributed to a project and are direct costs.
In project management, the cone of uncertainty describes the evolution of the amount of best case uncertainty during a project. At the beginning of a project, comparatively little is known about the product or work results, and so estimates are subject to large uncertainty. As more research and development is done, more information is learned about the project, and the uncertainty then tends to decrease, reaching 0% when all residual risk has been terminated or transferred. This usually happens by the end of the project i.e. by transferring the responsibilities to a separate maintenance group.
A building estimator or cost estimator is an individual that quantifies the materials, labor, and equipment needed to complete a construction project. Building cost estimating can concern diverse forms of construction from residential properties to hi-rise and civil works. Both estimators and quantity surveyors must have a background education in the construction industry. Representative professional bodies which regulate property professionals:
Cost engineering is "the engineering practice devoted to the management of project cost, involving such activities as estimating, cost control, cost forecasting, investment appraisal and risk analysis". "Cost Engineers budget, plan and monitor investment projects. They seek the optimum balance between cost, quality and time requirements."
When estimating the cost for a project, product or other item or investment, there is always uncertainty as to the precise content of all items in the estimate, how work will be performed, what work conditions will be like when the project is executed and so on. These uncertainties are risks to the project. Some refer to these risks as "known-unknowns" because the estimator is aware of them, and based on past experience, can even estimate their probable costs. The estimated costs of the known-unknowns is referred to by cost estimators as cost contingency.
A glossary of terms relating to project management and consulting.
Construction cost estimating software is computer software designed for contractors to estimate construction costs for a specific project. A cost estimator will typically use estimating software to estimate their bid price for a project, which will ultimately become part of a resulting construction contract. Some architects, engineers, construction managers, and others may also use cost estimating software to prepare cost estimates for purposes other than bidding such as budgeting and insurance claims.
Direct costs, in accounting, are costs directly accountable to a cost object. The equivalent nomenclature in economics is specific cost. Direct costs may be either fixed or variable, but typically comprise materials, labour, and specific expenses such as, e.g. a royalty payment to a patent holder for a given production process, all, directly attributable to a cost object. Thus by industry:
The project management triangle is a model of the constraints of project management. While its origins are unclear, it has been used since at least the 1950s. It contends that:
The following outline is provided as an overview of and topical guide to project management:
Pre-construction services are services that are offered to support owners, architects, and engineers in making decisions. They are used in planning a construction project before the actual construction begins. The stage where these services are offered is called pre-construction or "pre-con".
Estimation is the process of finding an estimate or approximation, which is a value that is usable for some purpose even if input data may be incomplete, uncertain, or unstable. The value is nonetheless usable because it is derived from the best information available. Typically, estimation involves "using the value of a statistic derived from a sample to estimate the value of a corresponding population parameter". The sample provides information that can be projected, through various formal or informal processes, to determine a range most likely to describe the missing information. An estimate that turns out to be incorrect will be an overestimate if the estimate exceeds the actual result and an underestimate if the estimate falls short of the actual result.
A cost database is a computerized database of cost estimating information, which is normally used with construction estimating software to support the formation of cost estimates. A cost database may also simply be an electronic reference of cost data.
The following is a glossary of terms relating to construction cost estimating.
Quantity take-offs(QTO) are a detailed measurement of materials and labor needed to complete a construction project. They are developed by an estimator during the pre-construction phase. This process includes breaking the project down into smaller and more manageable units that are easier to measure or estimate. The level of detail required for measurement may vary. These measurements are used to format a bid on the scope of construction. Estimators review drawings, specifications and models to find these quantities. Experienced estimators have developed procedures to help them quantify their work. Many programs have been developed to aid in the efficiency of these processes. With BIM quantity take-off can be conducted almost automatically given that the type of materials, their quantity and price is included in the model. It is known that construction projects often run overtime and over budget and one of the reasons is lack of accuracy in quantity takeoff and estimates.
Subsurface utility engineering (SUE) refers to a branch of engineering that involves managing certain risks associated with utility mapping at appropriate quality levels, utility coordination, utility relocation design and coordination, utility condition assessment, communication of utility data to concerned parties, utility relocation cost estimates, implementation of utility accommodation policies, and utility design.