Project cost management

Last updated

Project Cost Management (PCM) is the dimension of project management which aims to ensure that a project is completed within its approved budget. [1] [2] It encompasses several specific project management activities including estimating, job controls, field data collection, scheduling, accounting and design, and uses technology to measure cost and productivity through the full life-cycle of enterprise level projects.[ citation needed ]

According to the Project Management Body of Knowledge (PMBOK), PCM's primary concern is the cost of the resources needed to complete the project. However, PMBOK also notes that PCM should also consider the impact of project management decisions on customers' wider or life-cycle costs such as the use of the building or IT system generated by the project. [1] :73

Beginning with estimating, a vital tool in PCM, actual historical data is used to accurately plan all aspects of the project. As the project continues, job control uses data from the estimate with the information reported from the field to measure the cost and production in the project. From project initiation to completion, project cost management has an objective to simplify and cheapen the project experience. [3]

This technological approach has been a big challenger to the mainstream estimating software and project management industries. [4] [5]

Related Research Articles

Earned value management (EVM), earned value project management, or earned value performance management (EVPM) is a project management technique for measuring project performance and progress in an objective manner.

Project management is the process of leading the work of a team to achieve all project goals within the given constraints. This information is usually described in project documentation, created at the beginning of the development process. The primary constraints are scope, time, and budget. The secondary challenge is to optimize the allocation of necessary inputs and apply them to meet pre-defined objectives.

<span class="mw-page-title-main">Work breakdown structure</span> A deliverable-orientated breakdown of a project into smaller components.

A work-breakdown structure (WBS) in project management and systems engineering is a deliverable-oriented breakdown of a project into smaller components. A work breakdown structure is a key project management element that organizes the team's work into manageable sections. The Project Management Body of Knowledge defines the work-breakdown structure as a "hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables."

A project plan, according to the Project Management Body of Knowledge (PMBOK), is: "...a formal, approved document used to guide both project execution and project control. The primary uses of the project plan are to document planning assumptions and decisions, facilitate communication among project stakeholders, and document approved scope, cost, and schedule baselines. A project plan may be sumarized or detailed."

<span class="mw-page-title-main">Project Management Body of Knowledge</span> Body of knowledge for project management

The Project Management Body of Knowledge (PMBOK) is a set of standard terminology and guidelines for project management. The body of knowledge evolves over time and is presented in A Guide to the Project Management Body of Knowledge, a book whose seventh edition was released in 2021. This document results from work overseen by the Project Management Institute (PMI), which offers the CAPM and PMP certifications.

Project management software (PMS) can help plan, organize, and manage resource tools and develop resource estimates. Depending on the sophistication of the software, it can manage estimation and planning, scheduling, cost control and budget management, resource allocation, collaboration software, communication, decision-making, quality management, time management and documentation or administration systems. Numerous PC and browser-based project management software and contract management software products and services are available.

<span class="mw-page-title-main">Project manager</span> Professional in the field of project management

A project manager is a professional in the field of project management. Project managers have the responsibility of the planning, procurement and execution of a project, in any undertaking that has a defined scope, defined start and a defined finish; regardless of industry. Project managers are first point of contact for any issues or discrepancies arising from within the heads of various departments in an organization before the problem escalates to higher authorities, as project representative.

<span class="mw-page-title-main">Product lifecycle</span> Duration of processing of products from inception, to engineering, design & manufacture

In industry, product lifecycle management (PLM) is the process of managing the entire lifecycle of a product from its inception through the engineering, design and manufacture, as well as the service and disposal of manufactured products. PLM integrates people, data, processes, and business systems and provides a product information backbone for companies and their extended enterprises.

In organizational studies, resource management is the efficient and effective development of an organization's resources when they are needed. Such resources may include the financial resources, inventory, human skills, production resources, or information technology (IT) and natural resources.

<span class="mw-page-title-main">V-model</span> Graphic of a systems development lifecycle

The V-model is a graphical representation of a systems development lifecycle. It is used to produce rigorous development lifecycle models and project management models. The V-model falls into three broad categories, the German V-Modell, a general testing model, and the US government standard.

In the context of software engineering, software quality refers to two related but distinct notions:

<span class="mw-page-title-main">Risk register</span> Document used as risk management tool, acting as a repository for all identified risks

A risk register (PRINCE2) is a document used as a risk management tool and to fulfill regulatory compliance acting as a repository for all risks identified and includes additional information about each risk, e.g., nature of the risk, reference and owner, mitigation measures. It can be displayed as a scatterplot or as a table.

Trend analysis is the widespread practice of collecting information and attempting to spot a pattern. In some fields of study, the term has more formally defined meanings.

<span class="mw-page-title-main">Burndown chart</span> Diagram of work left versus time

A burndown chart or burn down chart is a graphical representation of work left to do versus time. The outstanding work is often on the vertical axis, with time along the horizontal. A burn down chart is a run chart of remaining work. It is useful for predicting when all of the work will be completed. It is often used in agile software development methodologies such as Scrum. However, burn down charts can be applied to any project containing measurable progress over time.

Budgeted cost of work performed (BCWP) also called earned value (EV), is the budgeted cost of work that has actually been performed in carrying out a scheduled task during a specific time period. The BCWP is the sum of the budgets for completed work packages and completed portions of open work packages, plus the applicable portion of the budgets for level of effort and apportioned effort.

A glossary of terms relating to project management and consulting.

<span class="mw-page-title-main">Project management triangle</span> Model of the constraints of project management

The project management triangle is a model of the constraints of project management. While its origins are unclear, it has been used since at least the 1950s. It contends that:

  1. The quality of work is constrained by the project's budget, deadlines and scope (features).
  2. The project manager can trade between constraints.
  3. Changes in one constraint necessitate changes in others to compensate or quality will suffer.

Within project management, risk management refers to activities for minimizing project risks, and thereby ensuring that a project is completed within time and budget, as well as fulfilling its goals.

The following outline is provided as an overview of and topical guide to project management:

In software engineering, cycle time is a software metric which estimates development speed in (agile) software projects. The cycle time measures how long it takes to process a given job - whether it's a client request, an order, or a defined production process stage. The crucial aspect of measuring the cycle time is considering only the active, operating processing time and discarding any idle, waiting, or service times occurring mid-process.

References

  1. 1 2 Project Management Institute, A Guide to the Project Management Body of Knowledge, PMI Standards Committee, 1996 edition, archived 1 January 2020, accessed 31 August 2023
  2. College, Kathy Schwalbe, Ph.D., PMP, Augsburg (2012). Information technology project management (Seventh ed.). Boston, MA: Course Technology. ISBN   9781133526858.{{cite book}}: CS1 maint: multiple names: authors list (link)
  3. Rad, P.F. (2002). Project Estimating and Cost Management. Management Concepts. ISBN   9781567261448 . Retrieved 2015-09-14.
  4. "Magic Quadrant for IT Project and Portfolio Management". gartner.com. Retrieved 2015-09-14.
  5. "Practical Project Cost Management with Twproject | Twproject's blog". 2013-06-03. Retrieved 2015-09-14.