GKK Etzenricht

Last updated
GKK Etzenricht GKK Etzenricht.jpg
GKK Etzenricht
Sign in front of the inverter hall, photographed in spring 1999, 3.5 years after shut-down Schild GKK Etzenricht.jpg
Sign in front of the inverter hall, photographed in spring 1999, 3.5 years after shut-down
Harmonics filter of HVDC back-to-back station in Etzenricht Oberwellenfilter etzenricht.GIF
Harmonics filter of HVDC back-to-back station in Etzenricht
Impedance of AC filter used at GKK Etzenricht in dependence of frequency. Power grid frequency and their 11th, 13th, 23rd and 25th harmonics are marked GKK Etzenricht Filter Impedance Graph.gif
Impedance of AC filter used at GKK Etzenricht in dependence of frequency. Power grid frequency and their 11th, 13th, 23rd and 25th harmonics are marked

GKK Etzenricht, an abbreviation of Gleichstromkurzkupplung Etzenricht, meaning Etzenricht HVDC-back-to-back station, was an HVDC back-to-back facility near Etzenricht in the district of Neustadt an der Waldnaab in Bavaria, Germany.[ citation needed ] It was built on the site of the Etzenricht substation, a 380 kV/220 kV/110 kV-substation, which went into service in 1970 and expanded afterwards several times. The facility was used between 1993 and 1995 for the exchange of power between Germany and the Czech Republic, operated by Bayernwerk AG (now part of TenneT). [1]

Contents

History

Construction started April 26, 1991 and was completed September 1991. First power was achieved in May 1992 and a powerline to Hradec, Czech Republic was completed September 3, 1992.

Trial operation started January 27, 1993 with official opening July 9, 1993. It was shut down after synchronisation of the German and the Czech Power Grid on October 18, 1995.

After the synchronization of the power grids between Germany and Czech, the maximum amount of power which can be transmitted between Etzenricht and Hradec increased from 600 MW to 1316 MW. The inauguration of the second 380 kV-interconnection to Prestice substation on July 29, 1997 increased the transmission capacity from Etzenricht to Czech to further 1579 MW, so via Etzenricht substation today a maximum power exchange of 2895 MW between Czechia and Germany is possible.

In 1997, after inauguration of the second 380 kV-powerline to Czechia, which ends at Prestice substation, most external components of GKK Etzenricht were dismantled and stored on the area of the facility. Since beginning of this dismantling, the facility was not in working condition any more. Only the transformers, the smoothing reactor and one harmonic filter remained on their original sites. Since shutdown of the static inverter, it was planned to sell the installation to eastern Europe, where it would have allowed the construction of an HVDC back-to-back station for exchanging power between eastern Europe and the former Soviet Union. As the static inverter went more and more out of date and one was meanwhile able to build static inverters like that of GKK Etzenricht much simpler by using photo thyristors, no such deal ever took place. In 2006 the facility was sold to IDPC, an Austrian recycling company, which wanted first to sell the installation completely and as this did not work, part by part. However, only a few components were sold. In spring 2009 all remaining components of GKK Etzenricht were dismantled and scrapped.

Technical features

GKK Etzenricht had a maximum transmission power of 600  megawatts (MW) and worked with a DC voltage of 160 kV. The two static inverters are in a 13 metres (43 ft) high hall with 430 square metres (4,630 sq ft) of surface area, which was built in a combination of local and finished concrete building method. Each static inverter consists of 432  thyristors, which are put in six thyristor towers arranged in a row. Each thyristor tower has 2 valve functions and consist of 8 thyristor modules, which are arranged one on top of the other. Each thyristor module consists of 9 thyristors switched in series and the necessary auxiliary equipment as the saturation coils, which are in series with the thyristors. Parallel to each thyristor a series combination of a resistor and a capacitor is switched, which limits the speed of current grow. From this combination the power for the supply of the electronic used for thyristor steering is gained. The electronic used for thyristor steering has at operation a high voltage potential against ground. It is connected to the main control electronic on ground potential by fiber-optic cables, which allow a bidirectional data transmission. Parallel to each thyristor module a capacitor and parallel to each valve function a varistor is switched. As thyristors the model U78 S346 S34 manufactured by Siemens, which has a maximum power rating of 4100 amperes and which was when GKK Etzenricht was built the most powerful thyristor in the world. At both ends of the hall there are three bays for the accommodation of the static inverter transformers, which are built as single-phase units.

Pictures

Images of August 2008

Pictures of June 2009

Power transmission line to the Czech Republic

Etzenricht-Hradec powerline
Powerline Border Crossing.JPG
Location
Country Germany, Czech
Coordinates 49°37′52″N12°06′57″E / 49.63111°N 12.11583°E / 49.63111; 12.11583 (GKK Etzenricht)
49°38′56″N12°10′34″E / 49.64889°N 12.17611°E / 49.64889; 12.17611 (First pylon carrying also circuits of 110 kV-powerline Weiden-Eslarn)
49°38′28″N12°19′22″E / 49.64111°N 12.32278°E / 49.64111; 12.32278 (110 kV-branch to Vohenstrauss Substation)
49°36′07″N12°27′42″E / 49.60194°N 12.46167°E / 49.60194; 12.46167 (Last pylon carrying also circuits of 110 kV-powerline Weiden-Eslarn)
49°38′33″N12°31′13″E / 49.64250°N 12.52028°E / 49.64250; 12.52028 (Crossing of border between Germany and Czech)
49°40′49″N12°47′05″E / 49.68028°N 12.78472°E / 49.68028; 12.78472 (380 kV-Branch to Hradec)
50°20′47″N13°19′36″E / 50.34639°N 13.32667°E / 50.34639; 13.32667 (Hradec Substation)
General directionwest–east; north-south
From Etzenricht, Germany
Passes throughBorder of Czech
To Hradec, Czech
Construction information
Construction started1992
Commissioned1993
Technical information
TypeOverhead transmission line
Type of currentHVAC
Total length163 km (101 mi)
No. of transmission towers471
Power rating1,316 MW
AC voltage380 kV
No. of circuits1 ( 1 Etzenricht-Prestice)
Etzenricht-Prestice powerline
Powerline Border Crossing.JPG
Location
Country Germany, Czech
Coordinates 49°37′52″N12°06′57″E / 49.63111°N 12.11583°E / 49.63111; 12.11583 (GKK Etzenricht)
49°38′56″N12°10′34″E / 49.64889°N 12.17611°E / 49.64889; 12.17611 (First pylon carrying also circuits of 110 kV-powerline Weiden-Eslarn)
49°38′28″N12°19′22″E / 49.64111°N 12.32278°E / 49.64111; 12.32278 (110 kV-branch to Vohenstrauss Substation)
49°36′07″N12°27′42″E / 49.60194°N 12.46167°E / 49.60194; 12.46167 (Last pylon carrying also circuits of 110 kV-powerline Weiden-Eslarn)
49°38′33″N12°31′13″E / 49.64250°N 12.52028°E / 49.64250; 12.52028 (Crossing of border between Germany and Czech)
49°40′49″N12°47′05″E / 49.68028°N 12.78472°E / 49.68028; 12.78472 (380 kV-Branch to Hradec)
49°35′22″N13°20′06″E / 49.58944°N 13.33500°E / 49.58944; 13.33500 (Prestice Substation)
General directionwest–east
From Etzenricht, Germany
Passes throughBorder of Czech
To Prestice, Czech
Construction information
Construction started1997
Commissioned1997
Technical information
TypeOverhead transmission line
Type of currentHVAC
Total length110 km (68 mi)
No. of transmission towers300
Power rating1,579 MW
AC voltage380 kV
No. of circuits1

GKK Etzenricht was used in connection with the power transmission line between Germany and the Czech Republic. The single-circuit 380kV power transmission link runs from the (Ex) GKK Etzenricht to the Czech substations at Hradec u Kadaně. In 1997 a second single-circuit 380 kV-interconnection from Etzenricht to Přeštice substation was realized. Its conductors, which are of the same type as that used for the line to Hradec, are between Etzenricht and Straz installed on the same pylons. For overvoltage protection the whole powerline is equipped with two ground conductors, which are installed on a separate crossbar on the top of the pylons. One conductor contains a fiber optic cable for data transmission.

The link from Etzenricht to Hradec has a maximum power transmission capacity of 1639 MW at an operating voltage of 380 kV. However it is limited by substation equipment to 1316 MW. On the German section of the line the conductors are bundles of four ropes consisting of steel and aluminum. Each conductor has a cross section of 340 mm² aluminum and 30 mm² steel. Between Weiden and Etzenricht this line is installed on 14 pylons of the "Danube type". One of these pylons was built after the shutdown of the GKK, in order to run the line directly - past the static inverter hall - into the switchyard of the Etzenricht substation. By this the length of the German section of the line grow by 180 metres to 33.8 kilometres. Except of the first pylon, these pylons were used before 1992 for the 110 kV-powerline from Etzenricht to Weiden. In 1992 this line was rebuilt on pylons running parallel to the old 110 kV-powerline to Weiden, whose pylons were equipped with a third crossbar for the ground conductors and with the 380 kV-conductors for the line to Czech.

The section between Weiden/Oberpfalz and Eslarn consists of 60 pylons with a fourth crossbar under the crossbars for the 380 kV conductors in order to carry the two 110 kV circuits of the powerline Weiden/Oberpfalz - Vohenstrauss and the two 30 kV-circuits for the powerline between Vohenstrauss and Eslarn. This was necessary because, due to environmental protection, only one right of way was available. Therefore, the circuits of these lines, which existed in 1992 already since several years, had to be installed on the pylons of the powerline with the 380 kV-circuits to the Czech Republic. In Vohenstrauss the 110 kV-circuits run to the local substation, which is situated close to the right of way of the powerline to the Czech Republic.

Behind Vohenstrauss on the lowest crossbar the circuits of the 30 kV-line Vohenstrauss-Eslarn are installed. For a future upgrade of this line to 110 kV, the conductors of this line are mounted on insulators for 110 kV on the pylons. Near Riedlhof this line leaves the track of the line to Czech and runs on concrete pylons to Eslarn substation. From Riedlhof the 380 kV-line to the Czech Republic runs on 15 pylons of "Danube type" to the border between Germany and the Czech Republic. The border is crossed close north of the border crossing of the motorway A6 near Furth in Forest.

After the border the construction type of pylon does not change, but their design and the type of conductors. In the Czech Republic the line uses conductors, which are bundles of 3 conductors with a cross section of 450 mm² aluminum and 50 mm² steel. 31.5 kilometers behind the frontier near Straz the line splits off in two 380kV-lines with a single circuit. One of these lines is the 97.5 kilometres (60.6 mi) long line section to Hradec in Northern Bohemia and the other is the line to Přeštice, which was built in 1997. Both lines are installed on Delta type pylons.

A very remarkable feature is, that the powerline to Hradec substation is implemented on its last section on the area of Hradec substation between the termination portal and the busbar as underground cable.

Directional Radio Tower

55 metres tall lattice tower south of Etzenricht substation used for directional radio links by E.ON Richtfunkturm Etzenricht.jpg
55 metres tall lattice tower south of Etzenricht substation used for directional radio links by E.ON

South of the facility on a hill at 49°37'28" N and 12°6'55" E there is a 55 meters tall free-standing lattice tower, which was built in 1973. It is used for directional radio links for remote controlling Etzenricht substation and GKK Etzenricht, which are both not permanently manned.

Natural gas compressor station

Southwest of the facility at 49°37'29" N and 12°7'33" E there is a compressor station for natural gas owned by MEGAL.

Bibliography

Related Research Articles

<span class="mw-page-title-main">Transmission tower</span> Structure used to support an overhead power line

A transmission tower is a tall structure, usually a lattice tower made of steel that is used to support an overhead power line. In electrical grids, transmission towers carry high-voltage transmission lines that transport bulk electric power from generating stations to electrical substations, from which electricity is delivered to end consumers; moreover, utility poles are used to support lower-voltage sub-transmission and distribution lines that transport electricity from substations to electricity customers.

<span class="mw-page-title-main">Kontek</span> HVDC connector between Germany and Denmark

The Kontek HVDC is a 170-kilometre (110 mi) long, monopolar 400 kV high-voltage direct current cable between Germany and the Danish island Zealand. Its name comes from "continent" and the name of the former Danish power transmission company "Elkraft", which operated the power grid on the Danish islands Lolland, Falster and Zealand and had the abbreviation "ek". As of today, the cable is operated by Energinet.dk in Denmark and 50Hertz Transmission GmbH in Germany.

<span class="mw-page-title-main">Baltic Cable</span>

The Baltic Cable is a monopolar HVDC power line running beneath the Baltic Sea that interconnects the electric power grids of Germany and Sweden. Its maximum transmission power is 600 megawatts (MW).

The HVDC Volgograd–Donbass is a 475 kilometres (295 mi) long bipolar ±400 kV high voltage direct current powerline used for transmitting electric power from Volga Hydroelectric Station at Volgograd in Russia to Donbas in eastern Ukraine and vice versa.

<span class="mw-page-title-main">Pacific DC Intertie</span> HVDC power line in the United States

The Pacific DC Intertie is an electric power transmission line that transmits electricity from the Pacific Northwest to the Los Angeles area using high voltage direct current (HVDC). The line capacity is 3.1 gigawatts, which is enough to serve two to three million Los Angeles households and represents almost half of the Los Angeles Department of Water and Power (LADWP) electrical system's peak capacity.

<span class="mw-page-title-main">GK Wien–Southeast</span>

The GK Vienna–Southeast was a back-to-back HVDC station linking the electric power grids of Austria and Hungary. It operated between June 1993 and October 1996.

<span class="mw-page-title-main">Pylons of Messina</span> Historic high-voltage towers in Italy

The Pylons of Messina are two free-standing steel towers, the Sicilian one in Torre Faro and the Calabrian one in Villa San Giovanni. They were used from 1955 to 1994 to carry a 220 kilovolt power line across the Strait of Messina, between the Scilla substation in Calabria on the Italian mainland at 38°14′42″N15°40′59″E and the Messina-Santo substation in Sicily at 38°15′57″N15°39′04″E.

<span class="mw-page-title-main">Pylons of Cádiz</span>

The Pylons of Cádiz, also known as the Towers of Cádiz, are two 158 m (518 ft)-tall pylons supporting a double-circuit 132 kV three-phase AC powerline over the bay of Cádiz, Spain, running from Puerto Real Substation to the substation of the former Cádiz Thermal Power Station, situated on the peninsula upon which the city of Cádiz stands.

<span class="mw-page-title-main">HVDC converter station</span> Type of substation

An HVDC converter station is a specialised type of substation which forms the terminal equipment for a high-voltage direct current (HVDC) transmission line. It converts direct current to alternating current or the reverse. In addition to the converter, the station usually contains:

<span class="mw-page-title-main">Overhead line crossing</span> Crossing of an immovable obstacle by an overhead power line

An overhead line crossing is the crossing of an obstacle—such as a traffic route, a river, a valley or a strait—by an overhead power line. The style of crossing depends on the local conditions and regulations at the time the power line is constructed. Overhead line crossings can sometimes require extensive construction and can also have operational issues. In such cases, those in charge of construction should consider whether a crossing of the obstacle would be better accomplished by an underground or submarine cable.

<span class="mw-page-title-main">Bentwisch</span> Municipality in Mecklenburg-Vorpommern, Germany

Bentwisch is a municipality in the Rostock district, in Mecklenburg-Vorpommern, Germany, to the east of Rostock. Since its merger with Klein Kussewitz in January 2018, the municipality has 3,174 inhabitants and covers 29.19 square kilometres. Due to its proximity to Rostock, the B 105, and the A 19, Bentwisch became a place of industry after German reunification.

<span class="mw-page-title-main">Overhead power line</span> Above-ground structure for bulk transfer and distribution of electricity

An overhead power line is a structure used in electric power transmission and distribution to transmit electrical energy along large distances. It consists of one or more conductors suspended by towers or poles. Since most of the insulation is provided by air, overhead power lines are generally the lowest-cost method of power transmission for large quantities of electric energy.

Square Butte is the designation of a high-voltage direct current transmission line in the United States between the Milton R. Young Power Plant near Center, North Dakota at 47°4′18″N101°11′45″W and the Arrowhead converter station near Adolph at 46°46′25″N92°17′39″W. It was built by Minnkota Power Cooperative and Minnesota Power and went in service in 1977. In 2009, an agreement was executed between the two companies whereby Minnkota gets the rights to all the power currently transmitted over the line while Minnesota Power takes full ownership of the line to transmit power from new sources in the Center area.

<span class="mw-page-title-main">Traction power network</span> Electricity grid for the supply of electrified rail networks

A traction network or traction power network is an electricity grid for the supply of electrified rail networks. The installation of a separate traction network generally is done only if the railway in question uses alternating current (AC) with a frequency lower than that of the national grid, such as in Germany, Austria and Switzerland.

<span class="mw-page-title-main">Neckarwestheim Nuclear Power Plant</span> Nuclear power plant in Neckarwestheim, Germany

Neckarwestheim Nuclear Power Station is a nuclear power plant in Neckarwestheim, Germany, sometimes abbreviated GKN, operated by EnBW Kernkraft GmbH, a subsidiary of EnBW.

<span class="mw-page-title-main">Wolmirstedt substation</span>

Wolmirstedt substation is a large node in the power grid of former East Germany and termination of Germany's longest powerline, running from Lubmin nuclear power station to Wolmirstedt substation.

<span class="mw-page-title-main">GK Dürnrohr</span>

The GK Dürnrohr was a high-voltage direct current back-to-back scheme west of Dürnrohr substation, which was used for the energy exchange between Austria and Czechoslovakia between 1983 and 1996. The installation is no longer in use.

<span class="mw-page-title-main">Albertirsa–Zakhidnoukrainska–Vinnytsia powerline</span>

The Albertirsa–Zakhidnoukrainska–Vinnytsia powerline is a power transmission line between Ukraine and Hungary. It is a part of the former "Mir" transmission system between the Soviet Union and Comecon countries. As of today, it is the only 750 kV-powerline in Hungary and one of the few powerlines operated with this voltage in the European Union.

HVDC Ekibastuz–Centre is an unfinished HVDC transmission line between Ekibastuz in Kazakhstan and Tambov in Russia whose construction was started in 1978. It was planned to have a length of 2,414 kilometres (1,500 mi), which would have made it the longest powerline of the world with a maximum transmission rate of 6,000 MW and a transmission voltage of 750 kV between conductor and ground. For this line the erection of 4,000 pylons, most 41 metres (135 ft) tall, were required. Several hundred kilometres were built, including a Volga crossing on three 124 metres (407 ft) tall towers near Saratov, which were erected between 1989 and 1991. At Ekibastuz construction work at the terminal was started, while it was not the case at Centre substation, Tambov.

The Levis De-Icer is a High voltage direct current (HVDC) system, aimed at de-icing multiple AC power lines in Quebec, Canada. It is the only HVDC system not used for power transmission.

References

  1. "Netztechnische Maßnahmen zur Wiedervereinigung" (PDF) (in German).

49°37′51.62″N12°6′56.3″E / 49.6310056°N 12.115639°E / 49.6310056; 12.115639