Harapaki Wind Farm

Last updated

Harapaki Wind Farm
Harapaki wind farm Hawke's Bay, taken from Napier.jpg
Harapaki Wind Farm from Napier
Harapaki Wind Farm
CountryNew Zealand
Location Hawke's Bay
Coordinates 39°11′2″S176°41′35″E / 39.18389°S 176.69306°E / -39.18389; 176.69306
StatusUnder construction
Owner(s)Meridian Energy Limited
Operator(s)
Wind farm
Hub height85 metres (279 ft)
Rotor diameter120 metres (390 ft)
Power generation
Units operational20 [1]
Units planned41
Nameplate capacity 176 MW
Annual net output 542 GWh [2]

The Harapaki Wind Farm is a wind farm project in the Hawke's Bay region of New Zealand. Construction began in June 2021 and is expected to continue for three years. [3] [4]

Contents

History

In 2006, Hawke's Bay Wind Farm Ltd was granted resource consent for a 75 turbine, 225 MW wind farm at Titiokura. [5] The same year Unison Networks was granted consent for a 15 turbine, 45 MW development. Both consents were upheld by the Environment Court in October 2006. [6] A proposed expansion of Unison's project [7] was rejected by the Environment Court in 2009. [8] [9]

In 2010 Hawke's Bay Wind Farm Ltd was purchased by Meridian Energy. [10] Unison's consent was purchased in 2011, and the sites combined. [11]

In August 2019 Meridian sought interest from potential contractors for the wind farm's construction. [11] Construction was expected to begin in 2020, but was delayed due to the possible closure of the Tiwai Point aluminium smelter. [12] In February 2021 Meridian announced that construction would begin later that year, and would take approximately three years. [13] [14] Site preparation began in mid-2021. [15] The first turbines arrived in Napier in March 2023 [16] and transportation of components to the wind farm site began in July 2023 when State Highway 5 had been sufficiently repaired following the damage caused by Cyclone Gabrielle. [17]

The wind farm began generating in November 2023 [18] [19] and is expected to reach full capacity by September 2024. [20] [1]

Location

The wind farm is being built on the Maungaharuru Range, near the Titiokura Summit, about 34 km northwest of Napier Airport. [5] The altitude of the range is approximately 1300 metres.

Operation

The wind farm will use 41 Siemens Gamesa 4.3 MW turbines, measuring 85 m (279 ft) from base to hub with a rotor diameter of 120 m (394 ft). Electricity will be supplied to the national grid via a new substation on Transpower's Redclyffe-Whirinaki-Wairakei 220 kV transmission line. [21]

See also

Related Research Articles

Meridian Energy Limited is a New Zealand electricity generator and retailer. The company generates the largest proportion of New Zealand's electricity, generating 35 percent of the country's electricity in the year ending December 2014, and is the fourth largest retailer, with 14 percent of market share in terms of customers as of December 2015.

<span class="mw-page-title-main">Mercury Energy</span> New Zealand electricity generating and retailing company

Mercury NZ Limited is a New Zealand electricity generation and multi-product utility retailer of electricity, gas, broadband and mobile telephone services. All the company's electricity generation is renewable. Mercury has a pre-paid electricity product sub-brand GLOBUG. Mercury Energy is also the largest electricity retailer in New Zealand.

The Makara Guardians Inc. is an incorporated society formed in 1997 to coordinate opposition to proposals to build wind turbines near where the members live. Mākara is a rural locality 10 km west of Wellington, New Zealand. The Makara Guardians represents some 85% of the families in the Mākara Valley, and consists of around 160 members. Membership is restricted to residents or owners of land in Mākara who support the objectives of the Society and who are aged over 18.

<span class="mw-page-title-main">Contact Energy</span> New Zealand electricity generating and retailing company

Contact Energy Limited is a New Zealand electricity generator, a wholesaler of natural gas, and a retailer of electricity, natural gas, broadband and LPG.

<span class="mw-page-title-main">Te Rere Hau Wind Farm</span> New Zealand wind farm company

Te Rere Hau is a wind farm owned and operated by New Zealand Windfarms Ltd. It is situated on the Tararua Ranges, approximately 11 km east of Palmerston North in New Zealand.

<span class="mw-page-title-main">Wind power in New Zealand</span> Overview of wind power in New Zealand

Wind power constitutes a small but growing proportion of New Zealand's electricity. As of December 2020, wind power accounts for 690 MW of installed capacity and over 5 percent of electricity generated in the country.

The electricity sector in New Zealand uses mainly renewable energy, such as hydropower, geothermal power and increasingly wind energy. As of 2021, the country generated 81.2% of its electricity from renewable sources. The strategy of electrification is being pursued to enhance the penetration of renewable energy sources and to reduce greenhouse gas (GHG) emissions across all sectors of the economy. In 2021, electricity consumption reached 40 Terawatt-hours (TWh), representing a 0.2% increase compared to the consumption levels in 2010.

<span class="mw-page-title-main">Waitahora Wind Farm</span> Abandoned renewable energy project

The Waitahora Wind Farm was a proposed renewable energy project in New Zealand planned by Contact Energy but which has now been abandoned without construction beginning. This development was proposed to be located on the Puketoi Range which forms one side of the picturesque Waitahora Valley, near Dannevirke in Southern Hawke’s Bay.

Turitea Wind Farm is a 222-megawatt wind farm near Turitea, Palmerston North, New Zealand. The farm is owned and operated by Mercury Energy.

The Kaiwera Downs Wind Farm is a wind farm in the Southland region of New Zealand. It is consented to have a maximum capacity of 240 MW and use up to 83 turbines. Originally proposed by Trustpower, it is now owned and operated by Mercury Energy. The 10 turbine, 43 MW stage 1 of the project was opened in November 2023.

Project Huriwaka is a proposed wind farm located on the Hihitahi Plateau between Waiouru and Taihape, New Zealand. The project was originally developed and consented by Meridian Energy, but the consents were allowed to lapse. In May 2023 the rights to develop the project were acquired by Manawa Energy.

Project Hurunui is a proposed wind farm located between Omihi and Greta Valley in north Canterbury, New Zealand. Meridian Energy is developing the wind farm, which is planned to produce up to 75.9 MW from 2014.

<span class="mw-page-title-main">WEL Networks</span> New Zealand electricity distribution company

WEL Networks Limited is an electricity distribution company, serving the northern and central Waikato region of New Zealand. WEL is the sixth largest electricity distribution company in New Zealand, with 100,142 connections and 7,021 km (4,363 mi) of lines and underground cables. The company is 100% owned by the WEL Energy Trust.

<span class="mw-page-title-main">Solar power in New Zealand</span> Overview of solar power in New Zealand

Solar power in New Zealand is increasing in capacity, despite no government subsidies or interventions being available. As of the end of February 2024, New Zealand has 400 MW of grid-connected photovoltaic (PV) solar power installed, of which 130 MW (33%) was installed in the last 12 months. In the 12 months to December 2023, 372 gigawatt-hours of electricity was estimated to have been generated by grid-connected solar, 0.85% of all electricity generated in the country.

The Castle Hill Wind Farm is a proposed wind farm being developed by Genesis Energy. It will have up to 286 wind turbines with potential output of up to 858 MW, depending on what model(s) of wind turbines are selected. The project is estimated to cost more than $1.6 billion and will be New Zealand's largest wind farm.

The Waipipi Wind Farm is a wind powered electricity generation project in New Zealand owned and operated by Mercury NZ Ltd. This site is located between Patea and Waverley in South Taranaki. The wind farm consists of 31 wind turbines over 980 hectares, generating up to 133 MW at a cost of approximately $277 million. The 4.3 MW machines are the largest wind turbines installed in New Zealand.

<span class="mw-page-title-main">Anna Lorck</span> New Zealand politician

Anna Louise Lorck is a New Zealand politician of the Labour Party. She served in the New Zealand House of Representatives as the MP for Tukituki from 2020 to 2023.

The Mayor of Central Hawke's Bay officiates over the Central Hawke's Bay District of New Zealand's North Island.

The Maungaharuru Range is located 34 km from Napier in the New Zealand region of Hawke's Bay. The name means in the mountain that resounded in Te Reo Māori due to the bird population.

References

  1. 1 2 "Harapaki Wind Farm Development, Hawke's Bay: March 2024 Update" (PDF). Meridian Energy Limited. Retrieved 29 March 2024.
  2. "Meridian kicks off $395m Harapaki development". BusinessDesk. 24 February 2021. Retrieved 18 December 2022.
  3. Marty Sharpe (24 February 2021). "Meridian Energy's huge new $395 million wind farm, and 260 jobs, coming to Hawke's Bay". Stuff. Retrieved 19 April 2021.
  4. "A lot of air . . ". Hawkes Bay Today. 15 June 2021. Retrieved 19 June 2021.
  5. 1 2 "Fact sheet: August 2007" (PDF). Hawke's bay wind farm ltd. August 2007. Archived from the original (PDF) on 14 October 2008. Retrieved 25 September 2008.
  6. "Environment Court says yes to Te Pohue turbines". 19 July 2007. ISSN   1170-0777 . Retrieved 17 June 2021.
  7. "Titiokura/Te Waka Wind Farm" (PDF). Unison. August 2008. Archived from the original (PDF) on 14 October 2008. Retrieved 25 September 2008.
  8. "Wind farm decision a waste, says lines company". RNZ. 24 February 2009. Retrieved 17 June 2021.
  9. Marty Sharpe (20 March 2009). "Maori issues cited as wind farm declined". Stuff. Retrieved 17 June 2021.
  10. Marty Sharpe (5 November 2010). "Meridian buys company with wind farm consent". Stuff. Retrieved 17 June 2021.
  11. 1 2 Marty Sharpe (5 August 2019). "Wind farm first approved 14 years ago may finally get underway". Stuff. Retrieved 5 August 2019.
  12. Doug Laing (27 August 2020). "Hawke's Bay windfarm shelved because of Tiwai Point closure plan". Hawke's Bay Today. Retrieved 17 June 2021.
  13. Tom Pullar-Strecker (24 February 2021). "Meridian aims to build new wind farm every three years". Stuff. Retrieved 19 April 2021.
  14. Gianina Schwanecke (23 February 2021). "Hawke's Bay wind farm will create 260 jobs in 3 years, but iwi's long term concerns remain". Hawke's Bay Today. Retrieved 17 June 2021.
  15. "Work on Harapaki Wind Farm, north of Napier, set to spin to full speed in spring". Hawke's Bay Today. 29 August 2021. Retrieved 31 August 2021.
  16. James Pocock (6 March 2023). "Turbine components arrive for Harapaki wind farm in Hawke's Bay". New Zealand Herald. Retrieved 7 March 2023.
  17. Doug Laing (19 July 2023). "New Hawke's Bay wind farm: Five months on the road to Harapaki". New Zealand Herald. Retrieved 20 July 2023.
  18. "Cyclone-delayed wind farm starts delivering power". Business Desk. 17 November 2023. Retrieved 24 November 2023.
  19. James Pocock (2 December 2023). "Hawke's Bay wind farm: What it's like in the hills as $448m Harapiki sustainable energy project takes shape". Hawke's Bay Today. Retrieved 2 December 2023.
  20. "Harapaki Wind Farm Development, Hawke's Bay: July 2023 Update" (PDF). Meridian Energy Limited. Retrieved 24 August 2023.
  21. "Harapaki Wind Farm, Hawke's Bay, New Zealand". www.power-technology.com. Retrieved 28 October 2021.